ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Ratnakamal Residency -B

Registration lapsed No litigation declared Residential / Group Housing project

Ratnakamal Residency -B

By ANANTA DEVELOPERS

RG-MH-10869 · RERA P52100004017 · Last updated on MahaRERA portal: 1 Aug 2020

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 91 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2019Possession promised91 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 19 documents Report an error

Ratnakamal Residency -B is a Residential / Group Housing project by ANANTA DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100004017 on 7 Aug 2017. Possession was promised by 31 Mar 2019 and is now 91 months past that date.

At a glance

Project

  • NameRatnakamal Residency -B
  • TypeResidential / Group Housing
  • Location
    • Shirur
    • Pune
    • 412210
  • Pincode412210
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004017
  • ReraGenie IDRG-MH-10869

Builder

  • NameANANTA DEVELOPERS
  • Entity typePartnership
  • PartnerPravin Vasant Adhav
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

91 months past promisethis monthRegisteredAug 2017PromisedMar 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Aug 2017
  • Promised completion31 Mar 2019
  • Revised completionNone
  • Buildings2 building records
  • Documents filed19 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ratnakamal Residency ANA70000
RATNAKAMAL RECIDENCY-B,WINGNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 1 Aug 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

Ratnakamal Residency A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RATNAKAMAL RECIDENCY-B,WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 1 Aug 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes45%
Water SupplyYes65%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes75%
Street LightingYes25%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes40%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes40%

Parking filed49

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots49
Closed/Covered17
Open Space32
BuildingClosed/CoveredOpen SpaceTotal
Ratnakamal Residency A162036
RATNAKAMAL RECIDENCY-B,WING11213

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,587 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SUMTILAL MANIKLAL KHABIYAShirurPune

Approvals and building plan

Permissible FSI2789.53
Proposed, not sanctioned2,789 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchranjangao ganpati ,shirur

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAJAKTA N JADHAV
EngineerDHANANJAY DESAI
PartnerRole in project
ANANTA DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed19

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Architect completion.pdf1 Aug 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Architect completion (2).pdf1 Aug 2020
Status of ConveyanceFile: Convenyance deed Rat A B.pdf1 Aug 2020
Status of Formation of Legal Entity (Society/Co Op etc.)File: society ratnakamal A B.pdf27 Jul 2020
Building plan approvalFile: Blue print b.pdf31 Jul 2017
Layout approvalFile: layout.pdf31 Jul 2017
Building plan approvalFile: Blue print b.pdf31 Jul 2017
PAN CardFile: Pan Card.pdf31 Jul 2017
Copy of the legal title reportFile: sarch report-ilovepdf-compressed.pdf31 Jul 2017
Details of encumbrancesFile: Tital Report.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: layout.pdf31 Jul 2017
Building Plan Approval (IOD)File: Blue print b.pdf31 Jul 2017
Building Plan Approval (IOD)File: Blue print b.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: construtionPermition-ilovepdf-compressed.pdf31 Jul 2017
Declaration in FORM BFile: From b 1.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect latter.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng ltr-ilovepdf-compressed.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA.pdf31 Jul 2017
Proforma of Allotment letterFile: Sample Agreement-Dalvi Adhav.pdf31 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ratnakamal Residency -B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shirur13,700+ in Pune

2 kmRatnakamal Residency -BCompleted 14Lapsed / revoked 15Other 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: ANANTA DEVELOPERS

ANANTA DEVELOPERS has 3 registrations on MahaRERA, including Ratnakamal Residency -B and ANANT APARTMENT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Ratnakamal Residency -B shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Ratnakamal Residency -B is delayed beyond 31 Mar 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ratnakamal Residency -B?

The registered promoter entity is ANANTA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ratnakamal Residency -B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Ratnakamal Residency -B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ratnakamal Residency -B?

The professionals named in the filing: Architect: PRAJAKTA N JADHAV; Engineer: DHANANJAY DESAI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ratnakamal Residency -B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ratnakamal Residency -B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ratnakamal Residency -B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.