Registered No litigation declared Residential / Group Housing project

Ram Residency

By OPULENT BUILDERS

RG-MH-14606 · RERA P52100022811 · Last updated on MahaRERA portal: 1 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 52 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2027Possession promisedmoved 52 months from the original
8 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 90%
2 of 16Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 218 documents Report an error

Ram Residency is a Residential / Group Housing project by OPULENT BUILDERS in Pune, Maharashtra, registered with MahaRERA as P52100022811 on 30 Oct 2019. Possession is promised by 31 Jan 2027. The completion date has moved by 52 months from the original filing. 14 of the 16 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete.

At a glance

Project

  • NameRam Residency
  • TypeResidential / Group Housing
  • Location
    • VIKAS NAGAR
    • WANAWADI
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411040
  • Pincode411040
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100022811
  • ReraGenie IDRG-MH-14606

Builder

  • NameOPULENT BUILDERS
  • Entity typePartnership
  • GSTIN27AAIFO2668L1ZP
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2019First promiseSep 2022Revised toJan 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Oct 2019
  • Promised completion31 Jan 2027
  • Revised completionRevised to 31 Jan 2027 (originally 30 Sep 2022)
  • Buildings2 building records
  • Documents filed218 files

Current status

88%14 of 16 units booked
81.3%Work done, per cost certificate

Figures as on 1 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA54808
BUILDING BNA54808

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 1 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.

BUILDING A68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
BUILDING B68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 1 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered24
BuildingClosed/CoveredTotal
BUILDING A1212
BUILDING B1212

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area900 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Aug 2025

Approvals and building plan

Sanctioning authorityPune Muncipal Corporation
Permissible FSI1250.45
Proposed, not sanctioned1,250 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHE RATNAKAR BANK LTD,NO-8,GROUND FLOOR,VEGA CENTER,SHANKARSETH ROAD,SWARGATE,PUNE-411042
Estimated costRs 5.36 cr
Cost incurredRs 4.36 cr
Work done81.27%
BuildingWingEstimatedIncurred
BUILDING ANARs 2.58 crRs 2.18 cr
BUILDING BNARs 2.58 crRs 2.18 cr
-NARs 19.94 lakh-

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBabasaheb Dhavale & Associates
EngineerDinesh Khedkar
EngineerAkash Mashale
EngineerPandurang Bhausaheb Khedkar
EngineerRohinee Kailas badgujar
Chartered AccountantRMR Shah & Company
Chartered AccountantPravin Pise
Chartered AccountantRSMS AND ASSOCIATES CHARTERED ACCOUNTANTS
Chartered AccountantYogesh D Mali
PartnerRole in project
OPULENT BUILDERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017213Sep 2022 → Jul 2026

Reason as filed by the promoterFINACIAL ISSUE & TAKE OVER

EA04022619700Sep 2022 → Jan 2027

Reason as filed by the promoterThe completion of the project has been delayed due to revisions in the sanctioned plans of the project. The process of obtaining revised sanctions involved submission of updated drawings, recalculation of permissible and sanctioned built-up area, and incorporation of changes in building configuration and statutory compliances as per prevailing regulations. The time consumed in scrutiny, observations, and approvals by the competent authorities was beyond the control of the promoter, which consequently affected the project execution schedule and led to delay in completion

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jan 2027

Documents filed218

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 218 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect certificate June 26.pdf1 Sep 2026
Withdrawal Update Form 2File: Ram residency june 26 (3) (1) (1).pdf1 Sep 2026
Withdrawal Update Form 3File: FORM-3 Ram Residency.pdf1 Sep 2026
Withdrawal Update Form 1File: ARCHITECH CERTIFICATE Q2.pdf24 Jul 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE Q2.pdf24 Jul 2026
Withdrawal Update Form 3File: CA CERTIFICATE Q2.pdf24 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A 24-25 (2).pdf17 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A 25-26.pdf17 Jun 2026
Form 2A (FY 2026-2027)File: Form 2A 26-27 (1).pdf17 Jun 2026
Layout approvalFile: Main layout highlighted.pdf11 May 2026
Building plan approvalFile: 2-2.pdf11 May 2026
Withdrawal Update Form 1File: Form 1.pdf9 May 2026
Withdrawal Update Form 2File: Form 2 (2026.pdf9 May 2026
Withdrawal Update Form 3File: ram Residency form 3.pdf9 May 2026
Withdrawal Update Form 1File: Form 1.pdf23 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf23 Apr 2026
Withdrawal Update Form 2File: Form 2 (2026.pdf23 Apr 2026
Withdrawal Update Form 2File: Form 2 (2026.pdf23 Apr 2026
Withdrawal Update Form 3File: Form 3-1_merged (2).pdf23 Apr 2026
Withdrawal Update Form 3File: ram Residency form 3.pdf23 Apr 2026
Withdrawal Update Form 1File: FORM 1 OPULENT BUILDERS.pdf4 Mar 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE Q3.pdf4 Mar 2026
Withdrawal Update Form 3File: Opulent builders- form -3.pdf4 Mar 2026
Withdrawal Update Form 1File: FORM 1 OPULENT BUILDERS.pdf3 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf3 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf3 Feb 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE Q3.pdf3 Feb 2026
Withdrawal Update Form 2File: Form 2 (1).pdf3 Feb 2026
Withdrawal Update Form 2File: Form 2 (1).pdf3 Feb 2026
Withdrawal Update Form 3File: Opulent builders- form -3.pdf3 Feb 2026
Withdrawal Update Form 3File: Form 3 (1).pdf3 Feb 2026
Withdrawal Update Form 3File: Form 3 (1).pdf3 Feb 2026
Layout approvalFile: 10-08-2023 1.pdf14 Jan 2026
Building plan approvalFile: 10-08-2023 2.pdf14 Jan 2026
Layout approvalFile: 23-12-2025 1.pdf14 Jan 2026
Building plan approvalFile: 23-12-2025 2.pdf14 Jan 2026
Building plan approvalFile: 23-12-2025 2.pdf14 Jan 2026
Withdrawal Update Form 1File: Opelant Builder.pdf13 Oct 2025
Withdrawal Update Form 1File: Opelant Builder.pdf13 Oct 2025
Withdrawal Update Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1) (1).pdf13 Oct 2025
Withdrawal Update Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1) (1).pdf13 Oct 2025
Withdrawal Update Form 3File: Ram Residency fom 3 (1) (1) (2).pdf13 Oct 2025
Withdrawal Update Form 3File: Ram Residency fom 3 (1) (1) (2).pdf13 Oct 2025
Withdrawal Update Form 1File: Opelant Builder.pdf9 Oct 2025
Withdrawal Update Form 1File: Opelant Builder.pdf9 Oct 2025
Withdrawal Update Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1) (1).pdf9 Oct 2025
Withdrawal Update Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1) (1).pdf9 Oct 2025
Withdrawal Update Form 3File: Revised CA Ram Residency (1) (1).pdf9 Oct 2025
Withdrawal Update Form 3File: Revised CA Ram Residency (1) (1).pdf9 Oct 2025
Withdrawal Update Form 1File: Opelant Builder.pdf8 Oct 2025
Withdrawal Update Form 2File: 6 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1) (1).pdf8 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf8 Oct 2025
Form 1File: Form 1.pdf15 Jul 2025
Form 2File: Form 2.pdf15 Jul 2025
Form 3File: Form 3.pdf15 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf15 Jul 2025
Form 2A (FY 2019-2020)File: Op Bld Form 2A F.Y.( 19-20).pdf8 Jul 2025
Form 2A (FY 2020-2021)File: Op Bld Form 2A F.Y. (20-21).pdf8 Jul 2025
Form 2A (FY 2021-2022)File: Op Bld Form 2A F.Y.(21-22).pdf8 Jul 2025
Form 2A (FY 2022-2023)File: Op Bld Form 2A F.Y. (22-23).pdf8 Jul 2025
Form 2A (FY 2023-2024)File: Op Bld Form 2A F.Y. (23-24).pdf8 Jul 2025
Form 1File: Form 1.pdf7 Jul 2025
Form 2File: Form 2.pdf7 Jul 2025
Form 3File: Form 3.pdf7 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 3rd Qtr 19-20.pdf7 Jul 2025
Form 1File: Form 1.pdf7 Jul 2025
Form 2File: Form 2.pdf7 Jul 2025
Form 3File: Form 3.pdf7 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsol 4th Qtr 19-20.pdf7 Jul 2025
Form 1File: Form 1.pdf7 Jul 2025
Form 2File: Form 2.pdf7 Jul 2025
Form 3File: Form 3.pdf7 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD -UNSOLD FY - 20-21 - 1st Quarter.pdf7 Jul 2025
Form 1File: Form 1.pdf7 Jul 2025
Form 2File: Form 2.pdf7 Jul 2025
Form 3File: Form 3.pdf7 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD -UNSOLD FY - 20-21 - 2nd Quarter.pdf7 Jul 2025
Form 1File: Form 1.pdf7 Jul 2025
Form 2File: Form 2.pdf7 Jul 2025
Form 3File: Form 3.pdf7 Jul 2025

How this compares with Pune

88%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 52 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ram Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WANAWADI13,700+ in Pune

Builder: OPULENT BUILDERS

OPULENT BUILDERS has 2 registrations on MahaRERA, including Ram Residency and Ram Residency. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Ram Residency is delayed beyond 31 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ram Residency?

The registered promoter entity is OPULENT BUILDERS, a partnership as per the filing. Its GSTIN 27AAIFO2668L1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ram Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Ram Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ram Residency?

The professionals named in the filing: Architect: Babasaheb Dhavale & Associates; Engineer: Dinesh Khedkar; Engineer: Akash Mashale; Engineer: Pandurang Bhausaheb Khedkar; Engineer: Rohinee Kailas badgujar; Chartered Accountant: RMR Shah & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ram Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ram Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ram Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.