One Place
RG-MH-53805 · RERA P52100016297 · Last updated on MahaRERA portal: 24 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 17 months past the filed date
- Completion date moved by 5 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
One Place is a Commercial project by U D Developers LLP in Pune, Maharashtra, registered with MahaRERA as P52100016297 on 2 May 2018. Possession was promised by 21 May 2025 and is now 17 months past that date. The completion date has moved by 5 months from the original filing. 132 of the 159 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameOne Place
- TypeCommercial
- Location
- Pune
- wanwadi
- Haveli
- 411040
- Pincode411040
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100016297
- ReraGenie IDRG-MH-53805
Builder
- NameU D Developers LLP
- Entity typePartnership
- GSTIN27AACFU8136B1ZB
- PartnerDilip Mittal
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 May 2018
- Promised completion21 May 2025
- Revised completionRevised to 21 May 2025 (originally 30 Dec 2024)
- Buildings1 building record
- Documents filed105 files
Current status
Figures as on 24 Jun 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| One Place | NA | 14 | 11 | 0 | 159 | 159 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.
One Place: 81% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 99% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 99% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 99% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 96% |
Progress on shared amenities15
As on 24 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | Yes | 75% |
| Landscaping & Tree Planting | Yes | 35% |
| Street Lighting | Yes | 80% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 65% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 85% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed80
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VKa Architecture |
| Engineer | Manjiri Desai |
| Chartered Accountant | SAC & Co LLP |
| Chartered Accountant | Priyanka Chordiya and Associates |
| Partner | Role in project |
|---|---|
| U D Developers LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterwe, M/s. U D Developers LLP, hereby declare the following with respect to the project One Place bearing registration number. P52100016297 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 21/05/2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timely execu
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Apr 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Aug 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 4 May 2025
Documents filed105
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Other - LegalFile: Form 4 Annexure E.pdf | 24 Jun 2025 |
| Other - LegalFile: Annexure E ( Form 4).pdf | 4 May 2025 |
| Other - LegalFile: Occupancy Certificate.pdf | 4 May 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf | 4 May 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Wanowrie Mar 2025.pdf | 2 May 2025 |
| Certificates of CA (Form 3)File: Form 3 One Place Wanowrie 30032025_compressed.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 One Place_UD.pdf | 29 Jan 2025 |
| Certificates of CA (Form 3)File: form 3 One Place Wanowrie 31-12-2024_compressed.pdf | 29 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 One Place.pdf | 29 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: UD Developers_compressed.pdf | 29 Jan 2025 |
| Declaration in FORM BFile: Form B U D DDEVELOPER.pdf | 28 Nov 2024 |
| Declaration about Commencement CertificateFile: Format D.pdf | 28 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_One Place_UD.pdf | 11 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_One Place_UD.pdf | 11 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_One Place_UD.pdf | 6 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 One Place Wanowrie SEPTSign_compressed.pdf | 6 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_One Place_UD.pdf | 6 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory One Place_U D June_compressed.pdf | 6 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory One Place UD Sep 2024.pdf | 6 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 One Place Wanovrie 31-03-2024.pdf | 8 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM_2A_One Place UDD.pdf | 13 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_One Place.pdf | 31 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_One Place.pdf | 31 Jul 2024 |
| Certificates of CA (Form 3)File: form 3 One Place Wanowrie 30-06-2024_compressed.pdf | 31 Jul 2024 |
| Certificates of CA (Form 3)File: form 3 one place wanowrie 31-03-2024_compressed.pdf | 30 May 2024 |
| Other - LegalFile: UD IGR INWORD LETTER.pdf | 29 May 2024 |
| Other - LegalFile: UD PMC INWORD LETTER.pdf | 29 May 2024 |
| Other - TechnicalFile: UD IGR INWORD LETTER.pdf | 29 May 2024 |
| Disclosure of sold/ booked inventoryFile: ud q1.pdf | 4 May 2024 |
| Disclosure of sold/ booked inventoryFile: ud q2.pdf | 4 May 2024 |
| Disclosure of sold/ booked inventoryFile: ud q3.pdf | 4 May 2024 |
| Disclosure of sold/ booked inventoryFile: ud q4.pdf | 4 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 One Place UD_compressed.pdf | 29 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 One Place-UD.pdf | 29 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Shop-Part-3 1 to 9th Floor 86 Shops Compl Cert.pdf | 22 Mar 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: UD C -902 completion.pdf | 22 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_ONE PACE_Wanori.pdf | 6 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_ONE PLACE Wanori.pdf | 6 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3 One Place Wanowrie 31122023-Both sign_compressed.pdf | 6 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 One Place Wanwadi.pdf | 7 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 One Place Wanwadi UD DEVELOPERS.pdf | 7 Dec 2023 |
| Certificates of CA (Form 3)File: form 3 One Place Wanowrie 30092023 both sign_compressed.pdf | 7 Dec 2023 |
| Other - LegalFile: UD IGR Office copy.pdf | 23 Oct 2023 |
| Other - LegalFile: UD PMC copy.pdf | 23 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A U D Developer LLP.pdf | 7 Sep 2023 |
| Certificates of CA (Form 3)File: Form 3 One Place Wanowrie 30032023 both sign_compressed.pdf | 7 Sep 2023 |
| Certificates of CA (Form 3)File: form 3 one place wanowrie 30062023 Both Sign-compressed.pdf | 7 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 PC FY 22-23 One Place_wanowrie_both sign_compressed.pdf | 7 Sep 2023 |
| Certificates of CA (Form 3)File: Form 3 One Place Wanowrie 31122022 both sign_compressed.pdf | 28 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 U D DEVELOPERS ARCHITECT CERTIFICATE.pdf | 31 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 U D DEVELOPERS ENGINEERING CERTIFICATE.pdf | 31 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: U D DEVELOPERS Form1.pdf | 1 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: U D DEVELOPERS Form 2.pdf | 1 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: U D DEVELOPERS LLP-FORM 2 June 2022.pdf | 20 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 One Place Wanowrie 30062022 Both sign_compressed.pdf | 20 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 One Place Wanowrie 30092022 Both sign_compressed.pdf | 20 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Wanorie Form 2A signed copy March 2022.pdf | 13 Feb 2023 |
| Other - LegalFile: WANAWADI PROJECT MUKHYA LEKHA V VITTA ADHIKARI PMC PUNE UNIT LIST SALE INWARD COPY.pdf | 1 Feb 2023 |
| Other - LegalFile: WANAWADI-IGR INWARD COPY-UNIT LIST STAMP DUTY AMOUNT PAY BEHALF CUSTOMER.pdf | 1 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 One Place Wanwadi 31-3 Sign_compressed.pdf | 17 Jan 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about New AC details.pdf | 6 Jan 2023 |
| Layout approvalFile: Layout plan_compressed.pdf | 29 Nov 2022 |
| Details of encumbrancesFile: Declaration about Encumbrance for One place wanwadi.pdf | 29 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: Layout plan_compressed.pdf | 29 Nov 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: NEW COMMENACEMENT CERTIFICATE 2021.pdf | 29 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM A-WANWADI.pdf | 29 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-WANAWADI -ONE PLACE 30-9-22.pdf | 29 Nov 2022 |
| Building plan approvalFile: WANAWADI NEW PLAN.pdf | 22 Aug 2022 |
| Layout approvalFile: WANAWADI NEW PLAN.pdf | 22 Aug 2022 |
| Copy of Layout Approval (in case of layout)File: WANAWADI NEW PLAN.pdf | 22 Aug 2022 |
| Building Plan Approval (IOD)File: WANAWADI NEW PLAN.pdf | 22 Aug 2022 |
| Other - LegalFile: U D Developers IGR Inword letter.pdf | 10 Aug 2022 |
| Certificates of CA (Form 3)File: Form 3 U D Developers 3103.pdf | 16 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: U D Develoeprs LLP Form 5 .pdf | 16 Mar 2022 |
| Layout approvalFile: Layout plan.pdf | 22 Nov 2021 |
| Building plan approvalFile: Layout plan.pdf | 22 Nov 2021 |
| Copy of Layout Approval (in case of layout)File: Layout plan.pdf | 22 Nov 2021 |
| Building Plan Approval (IOD)File: Layout plan.pdf | 22 Nov 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion1.pdf | 22 Nov 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 105 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep One Place on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pune13,700+ in Pune
Filed coordinates, straight-line distance. 114 registered projects within 2 km.
NYATI ELENOR
NYATI BUILDERS PRIVATE LIMITED
GANGA NAKSHATRA
MAHANAGAR REALTY
99 AVENUE
99 AVENUE REALTY LLP
Symphony of The Skies
Abhay Arvind Mandhare
ISHANAND
MAKAWANA BROS & CO (HWP)
WINDSOR SATYA VIHAR
WINDSOR INFRACON LLP
Builder: U D Developers LLP
U D Developers LLP has 1 registration on MahaRERA, including One Place. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that One Place shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if One Place is delayed beyond 21 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of One Place?
The registered promoter entity is U D Developers LLP, a partnership as per the filing. Its GSTIN 27AACFU8136B1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in One Place?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for One Place?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at One Place?
The professionals named in the filing: Architect: VKa Architecture; Engineer: Manjiri Desai; Chartered Accountant: SAC & Co LLP; Chartered Accountant: Priyanka Chordiya and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in One Place?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback