Registered Litigation declared Others project

GANGA NAKSHATRA

By MAHANAGAR REALTY

RG-MH-11325 · RERA P52100001668 · Last updated on MahaRERA portal: 10 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 15 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken
  • Rs 19.11 crore secured on the land, in favour of HDFC BANK LTD
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 24 months from the original
2 of 11Construction stages donefurthest along: Podiums (if any), 80%
124 of 198Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 112 documents Report an error

GANGA NAKSHATRA is a Others project by MAHANAGAR REALTY in Pune, Maharashtra, registered with MahaRERA as P52100001668 on 29 Jul 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 24 months from the original filing. 74 of the 198 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameGANGA NAKSHATRA
  • TypeOthers
  • Location
    • Pune Satara Road
    • Dhankwadi
    • Dhankawadi
    • Haveli
    • Pune
    • 411040
  • Pincode411040
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001668
  • ReraGenie IDRG-MH-11325

Builder

  • NameMAHANAGAR REALTY
  • Entity typePartnership
  • PartnersSUBHASH SITARAM GOEL, SURESHCHAND SUGANCHAND GARG, ROHIT SURESHCHAND GARG, ADITYA PURUSHOTTAM LOHIA, EISHA STRUCTURES LIMITED NA
  • Other registrations2 more →
  • Completed2 of 3

Key dates

this monthRegisteredJul 2017First promiseDec 2026Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jul 2017
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 30 Dec 2026)
  • Buildings1 building record
  • Documents filed112 files

Current status

37%74 of 198 units booked
20.7%Work done, per cost certificate

Figures as on 10 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing DNA32271926198

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 80%.

Wing D: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)75%
Podiums (if any)80%
Plinth75%
Stilt Floor100%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises13%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.17%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 10 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes10%
Street LightingYes25%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes20%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes5%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed977

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots977
Closed/Covered977

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area8,157 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofHDFC BANK LTD
Secured amountRs 19.11 crore
CERSAI search filedYes
Declared on16 Sep 2025

Approvals and building plan

Sanctioning authorityPune Municipal corporation
Permissible FSI60931.32
Proposed, not sanctioned28,132 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., 233, M.G. Rd, Camp, Pune.411001
Estimated costRs 87.80 cr
Cost incurredRs 18.18 cr
Work done20.71%
BuildingWingEstimatedIncurred
Wing DNARs 79.02 crRs 16.36 cr
-NARs 8.78 crRs 1.82 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUNIL CHINCHAWADE AND ASSOCIATES
EngineerDESIGN WERKZ ENGINEERING PVT,LTD.
EngineerChandrashekhar Tendulkar
EngineerAsif Lukade
Chartered AccountantMahesh Chandorkar & Associates
Chartered AccountantA W Hattarge & Co
PartnerRole in project
MAHANAGAR REALTY-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA04112518237Dec 2026 → Dec 2028

Reason as filed by the promoterWe had applied for the revision of sanctioned plans on 14/03/2022 (Payment Receipt Attached in other Tab - 22), and the project received the revised sanctioned plan along with the revised Commencement Certificate on 05/05/2025 for the upper floors. The approval was received after a delay of approximately 3 years, which consequently affected the overall project progress. We are seeking an extension to complete the construction as per the revised sanctioned building plans and to hand over the units to the allottees. 1. The project is 17% completed. 2. Consent of 70% of allottees has been uploade

Litigation declared15

CaseCourtStatus
301/2015HIGH COURTOngoing
668/2016PMCPENDING
1713/2019PMCOngoing
AT0O50O0OOO021309/21310/21311/2021Maha RERA Appellate TribunalPENDING
AT005000000052215/2021Maha RERA Appellate TribunalPENDING
AT005000000052216/2021Maha RERA Appellate TribunalPENDING
AT005000000052217/2021Maha RERA Appellate TribunalPENDING
281/283/282/285/286/288/2021HIGH COURT OF JUDICATURE AT BOMBAYPENDING
11524/2023High Court, MumbaiOngoing
14936/2023High Court MumbaiOngoing
1510/2025High Court MumbaiOngoing
Order No 645 with IA No 12501/2024High Court MumbaiOngoing
598/2023Civil JudgeOngoing
1028/2018Civil JudgeOngoing
1476/2023Civil judgeOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12400033kiran rajesh singhMAHANAGAR REALTY05/09/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed112

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 GANGA NAKSHATRA JUN 26.pdf10 Jul 2026
Withdrawal Update Form 2File: FORM 2 GANGA NAKSHATRA JUN 26.pdf10 Jul 2026
Withdrawal Update Form 3File: FORM 3 GANGA NAKSHATRA JUN 26.pdf10 Jul 2026
Withdrawal Update Form 1File: FORM 1 GANGA NAKSHATRA MAR 26.pdf6 Apr 2026
Withdrawal Update Form 1File: FORM 1 GANGA NAKSHATRA MAR 26.pdf6 Apr 2026
Withdrawal Update Form 2File: FORM 2 GANGA NAKSHATRA DEC 25.pdf6 Apr 2026
Withdrawal Update Form 2File: FORM 2 GANGA NAKSHATRA MAR 26.pdf6 Apr 2026
Withdrawal Update Form 3File: FORM 3 GANGA NAKSHATRA MAR 26.pdf6 Apr 2026
Withdrawal Update Form 3File: FORM 3 GANGA NAKSHATRA MAR 26.pdf6 Apr 2026
Withdrawal Update Form 1File: FORM 1 GANGA NAKSHATRA DEC 25.pdf9 Jan 2026
Withdrawal Update Form 2File: FORM 2 GANGA NAKSHATRA DEC 25.pdf9 Jan 2026
Withdrawal Update Form 3File: FORM 3 GANGA NAKSHATRA DEC 25.pdf9 Jan 2026
Withdrawal Update Form 1File: FORM 1 GANGA NAKSHATRA SEP 25.pdf4 Nov 2025
Withdrawal Update Form 2File: FORM 2 GANGA NAKSHATRA SEP 25.pdf4 Nov 2025
Withdrawal Update Form 3File: FORM 3 Ganga Nakshatra Sept 25.pdf4 Nov 2025
Form 5 (FY 2024-2025)File: FORM 5 GANGA NAKSHATRA 2024-25.pdf30 Sep 2025
Layout approvalFile: Layout.pdf25 Sep 2025
Building plan approvalFile: D Wing 26.pdf25 Sep 2025
Building plan approvalFile: D Wing 27.pdf25 Sep 2025
Building plan approvalFile: D Wing 28.pdf25 Sep 2025
Building plan approvalFile: D Wing 29.pdf25 Sep 2025
Building plan approvalFile: D Wing 30.pdf25 Sep 2025
Building plan approvalFile: D Wing 31.pdf25 Sep 2025
Building plan approvalFile: D Wing 32.pdf25 Sep 2025
Building plan approvalFile: D Wing 33.pdf25 Sep 2025
Building plan approvalFile: D Wing 34.pdf25 Sep 2025
Building plan approvalFile: D wing 35.pdf25 Sep 2025
Building plan approvalFile: D wing 38.pdf25 Sep 2025
Withdrawal Update Form 1File: FORM 1 GANGA NAKSHATRA JUN 25.pdf25 Sep 2025
Withdrawal Update Form 2File: FORM 2 GANGA NAKSHATRA JUN 25.pdf25 Sep 2025
Withdrawal Update Form 3File: FORM 3 GANGA NAKSHATRA JUN 25_.pdf25 Sep 2025
Form 2A (FY 2022-2023)File: FORM 2A GANGA NAKSHATRA 2022-23.pdf12 Aug 2025
Form 2A (FY 2023-2024)File: FORM 2A GANGA NAKSHATRA 2023-24.pdf12 Aug 2025
Form 2A (FY 2024-2025)File: FORM 2A GANGA NAKSHATRA 2024-25.pdf12 Aug 2025
Form 5 (FY 2022-2023)File: FORM 5 GANGA NAKSHATRA 2022-23.pdf12 Aug 2025
Form 5 (FY 2023-2024)File: FORM 5 GANGA NAKSHATRA 2023-24.pdf12 Aug 2025
Form 1File: FORM 1 GANGA NAKSHATRA MAR 23.pdf8 Aug 2025
Form 2File: FORM 2 GANGA NAKSHATRA MAR 23.pdf8 Aug 2025
Form 3File: FORM 3 GANGA NAKSHATRA MAR 23 (1).pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold GANGA NAKSHATRA MAR 23.pdf8 Aug 2025
Form 1File: FORM 1 GANGA NAKSHATRA JUN 23.pdf8 Aug 2025
Form 2File: FORM 2 GANGA NAKSHATRA JUN 23.pdf8 Aug 2025
Form 3File: FORM 3 GANGA NAKSHATRA JUN 23 (1).pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold GANGA NAKSHATRA JUN 23.pdf8 Aug 2025
Form 1File: FORM 1 GANGA NAKSHATRA SEP 23.pdf8 Aug 2025
Form 2File: FORM 2 GANGA NAKSHATRA SEP 23.pdf8 Aug 2025
Form 3File: FORM 3 GANGA NAKSHATRA SEP 23 (2).pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold GANGA NAKSHATRA SEP 23.pdf8 Aug 2025
Form 1File: FORM 1 GANGA NAKSHATRA DEC 23.pdf8 Aug 2025
Form 2File: FORM 2 GANGA NAKSHATRA DEC 23.pdf8 Aug 2025
Form 3File: FORM 3 GANGA NAKSHATRA DEC 23 (2).pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold GANGA NAKSHATRA DEC 23.pdf8 Aug 2025
Form 1File: FORM 1 GANGA NAKSHATRA MAR 24.pdf8 Aug 2025
Form 2File: FORM 2 GANGA NAKSHATRA MAR 24.pdf8 Aug 2025
Form 3File: FORM 3 GANGA NAKSHATRA MAR 24 (1).pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold GANGA NAKSHATRA MAR 24.pdf8 Aug 2025
Form 1File: FORM 1 GANGA NAKSHATRA JUN 24.pdf8 Aug 2025
Form 2File: FORM 2 GANGA NAKSHATRA JUN 24.pdf8 Aug 2025
Form 3File: FORM 3 GANGA NAKSHATRA JUN 24 (1).pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold GANGA NAKSHATRA JUN 24.pdf8 Aug 2025
Form 1File: FORM 1 GANGA NAKSHATRA SEP 24.pdf8 Aug 2025
Form 2File: FORM 2 GANGA NAKSHATRA SEP 24.pdf8 Aug 2025
Form 3File: FORM 3 GANGA NAKSHATRA SEP 24 (1).pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold GANGA NAKSHATRA SEP 24.pdf8 Aug 2025
Form 1File: FORM 1 GANGA NAKSHATRA DEC 24.pdf8 Aug 2025
Form 2File: FORM 2 GANGA NAKSHATRA DEC 24.pdf8 Aug 2025
Form 3File: FORM 3 GANGA NAKSHATRA DEC 24 (2).pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold GANGA NAKSHATRA DEC 24.pdf8 Aug 2025
Form 1File: FORM 1 GANGA NAKSHATRA MAR 25.pdf8 Aug 2025
Form 2File: FORM 2 GANGA NAKSHATRA MAR 25.pdf8 Aug 2025
Form 3File: FORM 3 GANGA NAKSHATRA MAR 25 (1).pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold GANGA NAKSHATRA MAR 25.pdf8 Aug 2025
Form 1File: FORM 1 GANGA NAKSHATRA JUN 25.pdf8 Aug 2025
Form 2File: FORM 2 GANGA NAKSHATRA JUN 25.pdf8 Aug 2025
Form 3File: FORM 3 GANGA NAKSHATRA JUN 25.pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold GANGA NAKSHATRA JUN 25.pdf8 Aug 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A_MR_Ganga Nakshatra_2019.pdf13 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A_MR_Ganga Nakshatra_2020.pdf13 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 MR-Nakshatra 2018-19.pdf31 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 MR-Nakshatra 2019-20.pdf31 Jan 2023

How this compares with Pune

37%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GANGA NAKSHATRA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhankwadi13,700+ in Pune

2 kmGANGA NAKSHATRACompleted 39Lapsed / revoked 19Other 58Dot size: filed unitsN

Filed coordinates, straight-line distance. 116 registered projects within 2 km.

Builder: MAHANAGAR REALTY

MAHANAGAR REALTY has 3 registrations on MahaRERA, including GANGA ISHANYA AB and GANGA ISHANYA C. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GANGA NAKSHATRA is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GANGA NAKSHATRA?

The registered promoter entity is MAHANAGAR REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GANGA NAKSHATRA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GANGA NAKSHATRA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GANGA NAKSHATRA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GANGA NAKSHATRA?

The professionals named in the filing: Architect: SUNIL CHINCHAWADE AND ASSOCIATES; Engineer: DESIGN WERKZ ENGINEERING PVT,LTD.; Engineer: Chandrashekhar Tendulkar; Engineer: Asif Lukade; Chartered Accountant: Mahesh Chandorkar & Associates; Chartered Accountant: A W Hattarge & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GANGA NAKSHATRA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GANGA NAKSHATRA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GANGA NAKSHATRA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.