ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Rajgruhi Residency Tower A

Completed No litigation declared Residential / Group Housing project

Rajgruhi Residency Tower A

By Wellbuild Merchants Private Limited

RG-MH-20853 · RERA P52100006776 · Last updated on MahaRERA portal: 25 Jan 2022

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2020Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

Rajgruhi Residency Tower A is a Residential / Group Housing project by Wellbuild Merchants Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100006776 on 16 Aug 2017. The registration is recorded completed; possession was promised by 29 Dec 2020. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameRajgruhi Residency Tower A
  • TypeResidential / Group Housing
  • Location
    • Gangadham Road
    • Kondhwa
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100006776
  • ReraGenie IDRG-MH-20853

Builder

  • NameWellbuild Merchants Private Limited
  • Entity typeCompany
  • Managing DirectorPravin Shivajirao Gawali
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseJun 2019Revised toDec 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on16 Aug 2017
  • Promised completion29 Dec 2020
  • Revised completionRevised to 29 Dec 2020 (originally 30 Jun 2019)
  • Buildings1 building record
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Rajgruhi Residency Tower ANA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Jan 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

Rajgruhi Residency Tower A: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises92%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.92%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities17

As on 25 Jan 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes25%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes60%
Solid Waste Management And DisposalYes60%
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
Under Ground Water TankYes100%
OtherNoNot applicable

Parking filed211

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots211
Closed/Covered194
Open Space17

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,161 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9864.34
Proposed, not sanctioned9,864 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCamp Pune

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDilip Govind Kale
EngineerJW Consultants
EngineerMohammad Gulam Walele
PartnerRole in project
Wellbuild Merchants Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100001945Jun 2019 → Jun 2020

Reason as filed by the promoterWe are the promoter of above mentioned housing project located at Sr. No. 63, Hissa No. 1/1, 1/2 and 2, Kondhwa Budruk, Pune - 411048. The said project consisting of one building, and the expected completion date for the same building as per earlier estimations and declaration is on 30.06.2019. But due to the labour scarcity and contractor sub-contractor labour problems the building could not be completed with-in the committed date i.e. 30.06.2019. We somehow managed the labour problems and came to normal work and also changed the contractors, sub-contractors few months back. Therefore we here

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Dec 2021

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CERSAI detailsFile: CERSAI_Search_Report_200228785213_For_Asset_Based_Search_25_01_2022_19_54_54_785.pdf25 Jan 2022
Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate Of Percentage of completion Tower A.pdf1 Jan 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Tower A Form 4.pdf28 Dec 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: A wing soc.pdf20 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Tower A.pdf7 Jul 2021
Declaration about Commencement CertificateFile: CC Declration A wing.pdf5 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate A Wing MArch 20.pdf5 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate A Wing March 21.pdf5 Jul 2021
Disclosure of sold/ booked inventoryFile: Slod Unsold A wing.pdf5 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FY 18-19.pdf5 Jul 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: A wing Soc.pdf5 Jul 2021
Certificates of CA (Form 5)File: Form 5 Audit Report Tower A.pdf30 Sep 2019
Certificates of CA (Form 5)File: Towe A-ilovepdf-compressed.pdf29 Sep 2018
Details of encumbrancesFile: Wellbuild Encumbrance certificat.PDF2 Aug 2018
OtherFile: Wellbuild index II.PDF2 Aug 2018
Details of encumbrancesFile: Certificate of Encrumbances.pdf20 Sep 2017
Details of encumbrancesFile: Index II.pdf20 Sep 2017
Building plan approvalFile: IOD.PDF30 Jul 2017
Building plan approvalFile: Tower A sheet 2.pdf30 Jul 2017
Building plan approvalFile: Tower A sheet 7.pdf30 Jul 2017
Building plan approvalFile: Tower A sheet 5.pdf30 Jul 2017
Building plan approvalFile: Tower A sheet 3.pdf30 Jul 2017
Building plan approvalFile: Tower A sheet 4.pdf30 Jul 2017
Building plan approvalFile: Tower A sheet 6.pdf30 Jul 2017
Building plan approvalFile: Parking Plan sheet 15.pdf30 Jul 2017
Layout approvalFile: Land Layout page 1 of 3.PDF30 Jul 2017
Building plan approvalFile: Parking Plan sheet 16.pdf30 Jul 2017
Building plan approvalFile: Tower A sheet 8.pdf30 Jul 2017
Building plan approvalFile: Tower A sheet 9.pdf30 Jul 2017
Layout approvalFile: Land Layout Page 2 of 3.PDF30 Jul 2017
Layout approvalFile: Land Layout page 3 of 3.PDF30 Jul 2017
PAN CardFile: Pan Wellbuild.pdf30 Jul 2017
Copy of the legal title reportFile: search and title report.pdf30 Jul 2017
Details of encumbrancesFile: Certificate of Encrumbance.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Land Layout page 1 of 3.PDF30 Jul 2017
Copy of Layout Approval (in case of layout)File: Land Layout Page 2 of 3.PDF30 Jul 2017
Copy of Layout Approval (in case of layout)File: Land Layout page 3 of 3.PDF30 Jul 2017
Building Plan Approval (IOD)File: IOD.PDF30 Jul 2017
Building Plan Approval (IOD)File: Tower A sheet 2.pdf30 Jul 2017
Building Plan Approval (IOD)File: Tower A sheet 3.pdf30 Jul 2017
Building Plan Approval (IOD)File: Tower A sheet 4.pdf30 Jul 2017
Building Plan Approval (IOD)File: Tower A sheet 5.pdf30 Jul 2017
Building Plan Approval (IOD)File: Tower A sheet 6.pdf30 Jul 2017
Building Plan Approval (IOD)File: Tower A sheet 7.pdf30 Jul 2017
Building Plan Approval (IOD)File: Tower A sheet 8.pdf30 Jul 2017
Building Plan Approval (IOD)File: Tower A sheet 9.pdf30 Jul 2017
Building Plan Approval (IOD)File: Parking Plan sheet 15.pdf30 Jul 2017
Building Plan Approval (IOD)File: Parking Plan sheet 16.pdf30 Jul 2017
Declaration in FORM BFile: Form B Tower A.pdf30 Jul 2017
Declaration in FORM BFile: Board Resolution.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Tower A.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Tower A.pdf30 Jul 2017
Certificates of CA (Form 3)File: CA Certificate A.pdf30 Jul 2017
Proforma of Allotment letterFile: Allotment letter -Tower A.pdf30 Jul 2017
Proforma of Allotment letterFile: Unit Agreement Tower A.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Building Comencement.pdf29 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rajgruhi Residency Tower A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kondhwa13,700+ in Pune

2 kmRajgruhi Residency TowerCompleted 65Lapsed / revoked 44Other 71Dot size: filed unitsN

Filed coordinates, straight-line distance. 180 registered projects within 2 km.

Builder: Wellbuild Merchants Private Limited

Wellbuild Merchants Private Limited has 3 registrations on MahaRERA, including Rajgruhi Residency Tower A and Rajgruhi Residency Tower B. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Rajgruhi Residency Tower A is delayed beyond 29 Dec 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rajgruhi Residency Tower A?

The registered promoter entity is Wellbuild Merchants Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rajgruhi Residency Tower A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Rajgruhi Residency Tower A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rajgruhi Residency Tower A?

The professionals named in the filing: Architect: Dilip Govind Kale; Engineer: JW Consultants; Engineer: Mohammad Gulam Walele. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rajgruhi Residency Tower A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rajgruhi Residency Tower A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rajgruhi Residency Tower A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.