Raj Residency
RG-MH-27186 · RERA P51800002739 · Last updated on MahaRERA portal: 31 Jan 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 46 months past the filed date
- 6 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Raj Residency is a Residential / Group Housing project by Rajesh Arvind Surti in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002739 on 4 Aug 2017. Possession was promised by 30 Dec 2022 and is now 46 months past that date. The completion date has moved by 12 months from the original filing. 6 complaints are on record with the regulator.
At a glance
Project
- NameRaj Residency
- TypeResidential / Group Housing
- Location
- Goregaon New Subhash Nagar off M G Road
- New Subhash Nagar Goregaon West
- Borivali
- Mumbai Suburban
- 400104
- Pincode400104
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800002739
- ReraGenie IDRG-MH-27186
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Aug 2017
- Promised completion30 Dec 2022
- Revised completionRevised to 30 Dec 2022 (originally 30 Dec 2021)
- Buildings1 building record
- Documents filed33 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RAJ RESIDENCY | NA | 24 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 31 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 48%.
RAJ RESIDENCY: 44% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 48% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 48% |
| Sanitary Fittings within the flats / premises | 48% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 48% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 48% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 48% |
Progress on shared amenities15
As on 31 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 98% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 80% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed7
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MAHENDRA N PANCHAL |
| Partner | Role in project |
|---|---|
| Raj builders & Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to COVID-19 & Lockdown nationwide and also non -availibility of labours, materials. we started construction of building but due to second wave of COVID-19 we stuck and cannot complete the construction on time. therefore we require some more time to complete the project.
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000000424 | VIDYAPRASAD VISHWAKARMA | RAJESH A SURTI | 06/09/2017 |
| CC006000000022836 | Bhailalbhai Danabhai Parmar | M/s. Raj Builders & Developers | 10/01/2018 |
| CC006000000056550 | Mrs Mughda G Nadkarni | M/s Raj Builders and Developers Pvt Ltd | 17/10/2018 |
| CC006000000057226 | Sunil Baburao Pawaskar | Rajesh Arvind Surti | 08/12/2018 |
| CC006000000408223 | SANJAY ANKUSH LUBDE | RAJESH ARVIND SURTI | 22/11/2023 |
| CC006000000408230 | jayshree Punjabi | raj builders and developers | 27/11/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed33
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A FY 21-22.pdf | 31 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY RR.pdf | 12 Jan 2023 |
| CERSAI detailsFile: CERSAI REPORT RR.pdf | 12 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FROM 5 FY 21-22 RR.pdf | 12 Jan 2023 |
| Proforma of Agreement for saleFile: Sale Agreement.pdf | 12 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF INVENTORY.pdf | 9 Apr 2022 |
| CERSAI detailsFile: Cersai Declaration (2).pdf | 9 Apr 2022 |
| Form 2AFile: Engineer form 2A, year 19-20.pdf | 28 Mar 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer form 2A year 20-21.pdf | 28 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA form 5 year 18-19.pdf | 28 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA form 5 year 19-20.pdf | 28 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA form 5 year 20-21.pdf | 28 Mar 2022 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 9 Mar 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Raj Residency Engineer Certificate.pdf | 7 Nov 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Raj Residency Engineer Certificate.pdf | 7 Nov 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Residency architect certificate.pdf | 3 Nov 2021 |
| Certificates of CA (Form 3)File: Raj Residency CA Certificate RERA.pdf | 3 Nov 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate.pdf | 30 Jun 2021 |
| Form 2AFile: From 2A.pdf | 28 Apr 2019 |
| Certificates of CA (Form 5)File: raj residency ca certificate.pdf | 28 Apr 2019 |
| Declaration in FORM BFile: Declaration in FORM B.pdf | 31 Jul 2017 |
| Layout approvalFile: Apply Layout RR.pdf | 29 Jul 2017 |
| Building plan approvalFile: Building Plan Approval (IOD).pdf | 29 Jul 2017 |
| PAN CardFile: Pan Card Rajeshbhai.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: Title certificate R-R.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: Details of encumbrances.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Apply Layout RR.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Building Plan Approval (IOD).pdf | 29 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Residency Architect From - 1.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificates of Engineer (Form 2).pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: Certificates of CA (Form 3).pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: RAJ RESIDENCY maharera agreementFINAL23-07-2017.pdf | 29 Jul 2017 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Raj VegaP51800078392 | Railwaymens Apnaghar CHSL, Mumbai Suburban | - | Dec 2024 | Certificate Signed | Dec 2029 | Not due yet |
| RAJ PANTHEONP51800003673 | New Subhash Nagar, Mumbai Suburban | 180 | Aug 2017 | Ongoing | Jun 2024Registered original: Dec 2022 | Not delivered |
| Raj SpacesP51800008872 | Borivali, Mumbai Suburban | - | Aug 2017 | Ongoing | Dec 2019Registered original: Dec 2018 | Not delivered |
| Sai Prasad | Subash Nagar NO 3 Motilal Nagar Nagar Goregaon West Mumbai 400104 | 20 | - | Completed | Sep 2006 | Late, Apr 2009 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 33 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Raj Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near New Subhash Nagar Goregaon West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 372 registered projects within 2 km.
Opulence
ARIHA BUILDTECH LLP
SHEETAL KIARA
A & A Developers
4TH AVENUE Sunteck City, ODC, Goregaon West
Satguru Corporate Services Pvt. Ltd.
Narang Valora
Narang Realty Private Limited
VIVAN
GOREGAON ELECTRICAL INDUSTRIES LLP
Integrated Ramicon
Integrated Affordable Home Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: Rajesh Arvind Surti
Rajesh Arvind Surti has 4 registrations on MahaRERA, including Raj Residency and RAJ PANTHEON. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Raj Residency shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Raj Residency is delayed beyond 30 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Raj Residency?
The registered promoter entity is Rajesh Arvind Surti, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Raj Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Raj Residency?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Raj Residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Raj Residency?
The professionals named in the filing: Architect: MAHENDRA N PANCHAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Raj Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback