Rajesh Arvind Surti: RERA track record

Individual ยท attribution by exact filing name, entity resolution in progress

Rajesh Arvind Surti has 4 registrations in this build, including Raj Residency and RAJ PANTHEON. Its filings disclose 5 earlier MahaRERA projects: 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations.

4Registrations in this build
5Past projects disclosed
+31 monthsMedian delivery slip
1Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Raj ResidencyMumbai Suburban, Maharashtra--Registration lapsed
RAJ PANTHEONMumbai Suburban, Maharashtra18058%Registration lapsed
Raj SpacesMumbai Suburban, Maharashtra--Registration lapsed
Raj VegaMumbai Suburban, Maharashtra--Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Sai Prasad
17 Sep 200618 Apr 2009+31 months
Raj Spaces
P51800008872
31 Dec 2019Not completed yetOngoing
Raj Residency
P51800002739
30 Dec 2022Not completed yetOngoing
RAJ PANTHEON
P51800003673
30 Jun 2024Not completed yetOngoing
Raj Vega
P51800078392
31 Dec 2029Not completed yetCertificate Signed

Frequently asked questions

How do I verify Rajesh Arvind Surti as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Rajesh Arvind Surti?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Rajesh Arvind Surti unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.