RAJ PANTHEON
RG-MH-47567 · RERA P51800003673 · Last updated on MahaRERA portal: 4 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 19 complaints at MahaRERA
- Completion date moved by 36 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RAJ PANTHEON is a Residential / Group Housing project by Rajesh Arvind Surti in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003673 on 6 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 36 months from the original filing. 105 of the 180 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 19 complaints are on record with the regulator.
At a glance
Project
- NameRAJ PANTHEON
- TypeResidential / Group Housing
- Location
- off M G Road
- New Subhash Nagar
- Borivali
- Mumbai Suburban
- 400104
- Pincode400104
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003673
- ReraGenie IDRG-MH-47567
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on6 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed125 files
Current status
Figures as on 4 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RAJ PANTHEON | NA | 24 | 22 | 174 | 6 | 180 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 70%.
RAJ PANTHEON: 75% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 4 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 25% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 75% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed1423
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| RAJ PANTHEON | NA | Rs 32.00 cr | Rs 30.40 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR VILAS DIKSHIT |
| Architect | MR MAHENDRA N PANCHAL |
| Engineer | shersinghchiltora |
| Chartered Accountant | Vishal R Trivedi |
| Chartered Accountant | RAMAN S SHAH |
| Chartered Accountant | ajay GUPTA |
| Partner | Role in project |
|---|---|
| Raj builders & Developers | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 1 YEAR
Reason as filed by the promoterDue to non-availability of labour & Materials & due to non-availability of financial add on time the project was not completed in time.
Reason as filed by the promoterWe would like to respectfully bring to your attention that the project has encountered cert unforeseen technical challenge that have adversely impacted the originally proposed timelin for completion. We wish to place on record the reason for the delay: Supply Chain Issues for Technical Equipment/Materials. Procurement of specialized materials and equipment (such as lifts, STP units, electrical panels) was delayed due to vendor-side manufacturing backlogs and import-related technic hold-ups. We would like to assure the Authority that despite these unavoidable delays, we rem committed to the com
Complaints filed with MahaRERA19
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000056311 | Bikram singh Butola | Rajesh Surti | 26/09/2018 |
| CC006000000193905 | Sanjay Sharma | Rajesh Surti | 04/09/2020 |
| CC006000000193906 | Ameeta Lewis | Rajesh Surti | 05/09/2020 |
| CC12400042 | james fredrick mascarenhas | Rajesh Arvind Surti | 05/09/2024 |
| CC12500247 | Kaustubh Prithviraj Inarkar | Rajesh Arvind Surti | 24/01/2025 |
| CC12401110 | Satyam Deepak Mokashi | Rajesh Arvind Surti | 12/12/2024 |
| CC12401296 | Sushma Kishor Nerurkar | Rajesh Arvind Surti | 31/12/2024 |
| CC12503805 | Damji Shah | Rajesh Arvind Surti | 31/10/2025 |
| CC12503803 | Premila Damji Shah | Rajesh Arvind Surti | 31/10/2025 |
| CC12503930 | Reshmi Raghunathan Nambiar | Rajesh Arvind Surti | 09/11/2025 |
| CC12600788 | Krishnakumar Shiv Jha | Rajesh Arvind Surti | 11/02/2026 |
| CC12600843 | ArunKumar Rambriksh Rai | Rajesh Arvind Surti | 14/02/2026 |
| CC12602008 | Balasubramanian Krishnamurthy Iyer | Raj builders & Developers | 05/04/2026 |
| CC12602012 | Shivkumar Sadashivan Nadar | Raj builders & Developers | 05/04/2026 |
| CC12602007 | Raj Narayana Sahu | Raj builders & Developers | 05/04/2026 |
| CC12602094 | Anwesha Datta Gupta | Raj builders & Developers | 09/04/2026 |
| CC12603627 | Franky Dsouza | Raj builders & Developers | 12/06/2026 |
| CC12603631 | Amita Chandrakant Shah | Raj builders & Developers | 12/06/2026 |
| CC12604488 | Bernadette Denis Dsouza | Raj builders & Developers | 18/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Oct 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed125
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form-1 Oct to Dec 2025.pdf | 4 May 2026 |
| Withdrawal Update Form 2File: Form-2 Oct to Dec 2025.pdf | 4 May 2026 |
| Withdrawal Update Form 3File: FINAL CA_compressed (1).pdf | 4 May 2026 |
| Withdrawal Update Form 1File: Form-1.pdf | 2 May 2026 |
| Withdrawal Update Form 2File: Form-2.pdf | 2 May 2026 |
| Withdrawal Update Form 3File: Signed Annexure-D_Form-3_Raj Pantheon CA Certificate July to Sept 2025.pdf | 2 May 2026 |
| Form 2A (FY 2023-2024)File: Form 2A 2023-2024.pdf | 29 Sep 2025 |
| Form 2A (FY 2024-2025)File: Form 2A 2024-25.pdf | 29 Sep 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 11 Sep 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 11 Sep 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 11 Sep 2025 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 14 Jul 2025 |
| Details of encumbrances concerned to FinanceFile: No Encumbrances Self Declaration legal.pdf | 11 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory January 24 to March 24.pdf | 11 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold inventory April 24 to june 24.pdf | 11 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold inventory July 24 to September 24.pdf | 11 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold inventory October 24 to December 24.pdf | 11 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold inventory jan 25 to mar 25.pdf | 11 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Sold unsold inventory April 25 to June 25.pdf | 11 Jul 2025 |
| Details of encumbrances concerned to LegalFile: No Encumbrances Self Declaration legal.pdf | 11 Jul 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: No Encumbrances self Declaration finance.pdf | 11 Jul 2025 |
| Form 1File: architect certificate Jan 24 to march 24.pdf | 11 Jul 2025 |
| Form 2File: Engineer Certificate 1st Jan 2024 to 31st March 2024.pdf | 11 Jul 2025 |
| Form 3File: 1 Annexure-D_Form-3_CA Certificate Jan to Mar 2024.pdf | 11 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory January 24 to March 24.pdf | 11 Jul 2025 |
| Self-declaration of Quarterly ProgressFile: self declaration.pdf | 11 Jul 2025 |
| Form 1File: architect certificate April 24 to June 24.pdf | 11 Jul 2025 |
| Form 2File: Engineer Certificate 1st April 2024 to 30th June 2024.pdf | 11 Jul 2025 |
| Form 3File: 2 Annexure-D_Form-3_CA Certificate Apr to Jun 2024.pdf | 11 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold inventory April 24 to june 24.pdf | 11 Jul 2025 |
| Self-declaration of Quarterly ProgressFile: self declaration.pdf | 11 Jul 2025 |
| Certificates of CA (Form 3)File: 1 Annexure-D_Form-3_CA Certificate Jan to Mar 2024.pdf | 10 Jul 2025 |
| Certificates of CA (Form 3)File: 2 Annexure-D_Form-3_CA Certificate Apr to Jun 2024.pdf | 10 Jul 2025 |
| Certificates of CA (Form 3)File: 3 Annexure-D_Form-3_CA Certificate Jul to Sept 2024.pdf | 10 Jul 2025 |
| Certificates of CA (Form 3)File: 4 Annexure-D_Form-3_CA Certificate Oct to Dec 2024.pdf | 10 Jul 2025 |
| Certificates of CA (Form 3)File: 5 Annexure-D_Form-3_CA Certificate Jan to Mar 2025.pdf | 10 Jul 2025 |
| Certificates of CA (Form 3)File: 6 Annexure-D_Form-3_CA Certificate Apr to Jun 2025.pdf | 10 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st Jan 2024 to 31st March 2024.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st April 2024 to 30th June 2024.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st July 2024 to 30th Sept 2024.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st Oct 2024 to 31st Dec 2024.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st Jan 2025 to 31st Mar 2025.pdf | 9 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st April 2025 to 30th June 2025.pdf | 9 Jul 2025 |
| Declaration about Commencement CertificateFile: Declation About Commencement Certificate.pdf | 15 Feb 2024 |
| Declaration in FORM BFile: affidavit Cum declaration.pdf | 15 Feb 2024 |
| CERSAI detailsFile: sersai declaration.pdf | 15 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 13 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 fy 22-23.pdf | 12 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate oct to dec 23.pdf | 8 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering certificate Oct to dec 23.pdf | 8 Feb 2024 |
| Certificates of CA (Form 3)File: CA certificate form 3 oct to dec 23_compressed_compressed.pdf | 8 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 fy 22-23.pdf | 8 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate Form 2 Jan To Mar 23.pdf | 6 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate form 2 Apr To June 23.pdf | 6 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate form 2 July To Sep 23.pdf | 6 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1 Jan To Mar 23.pdf | 3 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 Jan To Mar 23.pdf | 3 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1 Apr To June 23.pdf | 3 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1 July To Sep 23.pdf | 3 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer form 2 jan To mar 23.pdf | 3 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer form 2 Apr To June 23.pdf | 3 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer form 2 July To Sep 23.pdf | 3 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: engineer form 2A FY 22-2023.pdf | 3 Jan 2024 |
| Certificates of CA (Form 3)File: CA form 3 Jan To Mar 23.pdf | 3 Jan 2024 |
| Certificates of CA (Form 3)File: CA form 3 Apr To June 23.pdf | 3 Jan 2024 |
| Certificates of CA (Form 3)File: CA form 3 July To Sep 23.pdf | 3 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FORM 2 FY 21-22.pdf | 27 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf | 26 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer certificate.pdf | 26 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 CA.pdf | 26 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FROM 1 dt 30 JUNE 22.pdf | 24 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FORM 1 dt 30 SEPT 22.pdf | 24 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FORM 1 dt 31 DEC 22.pdf | 24 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FROM 2 FY 19-20.pdf | 24 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER Form 2 dt 31 MAR 22.pdf | 24 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FORM 2 dt 30 JUNE 22.pdf | 24 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FROM 2 dt 30 SEPT 22.pdf | 24 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FROM 2 dt 31 DEC 22.pdf | 24 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER FROM 2A FY 20-21.pdf | 24 Jan 2023 |
| Certificates of CA (Form 3)File: CA FORM 3 dt 31 MAR 22.pdf | 24 Jan 2023 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Raj VegaP51800078392 | Railwaymens Apnaghar CHSL, Mumbai Suburban | - | Dec 2024 | Certificate Signed | Dec 2029 | Not due yet |
| Raj ResidencyP51800002739 | New Subhash Nagar Goregaon West, Mumbai Suburban | - | Aug 2017 | Ongoing | Dec 2022Registered original: Dec 2021 | Not delivered |
| Raj SpacesP51800008872 | Borivali, Mumbai Suburban | - | Aug 2017 | Ongoing | Dec 2019Registered original: Dec 2018 | Not delivered |
| Sai Prasad | Subash Nagar NO 3 Motilal Nagar Nagar Goregaon West Mumbai 400104 | 20 | - | Completed | Sep 2006 | Late, Apr 2009 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 125 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep RAJ PANTHEON on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near New Subhash Nagar6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 345 registered projects within 2 km.
Opulence
ARIHA BUILDTECH LLP
SHEETAL KIARA
A & A Developers
4TH AVENUE Sunteck City, ODC, Goregaon West
Satguru Corporate Services Pvt. Ltd.
Narang Valora
Narang Realty Private Limited
VIVAN
GOREGAON ELECTRICAL INDUSTRIES LLP
Integrated Ramicon
Integrated Affordable Home Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: Rajesh Arvind Surti
Rajesh Arvind Surti has 4 registrations on MahaRERA, including Raj Residency and RAJ PANTHEON. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that RAJ PANTHEON shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if RAJ PANTHEON is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RAJ PANTHEON?
The registered promoter entity is Rajesh Arvind Surti, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RAJ PANTHEON?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RAJ PANTHEON?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RAJ PANTHEON?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RAJ PANTHEON?
The professionals named in the filing: Architect: MR VILAS DIKSHIT; Architect: MR MAHENDRA N PANCHAL; Engineer: shersinghchiltora; Chartered Accountant: Vishal R Trivedi; Chartered Accountant: RAMAN S SHAH; Chartered Accountant: ajay GUPTA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RAJ PANTHEON?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback