Home / Browse projects / Mumbai Suburban, Maharashtra / RAJ PANTHEON

Registration lapsed No litigation declared Residential / Group Housing project

RAJ PANTHEON

By Rajesh Arvind Surti

RG-MH-47567 · RERA P51800003673 · Last updated on MahaRERA portal: 4 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 19 complaints at MahaRERA
  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
7 of 11Construction stages donefurthest along: Installation of Lifts, 70%
75 of 180Units unsoldnot recorded sold or booked
19Complaints at MahaRERAon this registration
Jump to the 125 documents Report an error

RAJ PANTHEON is a Residential / Group Housing project by Rajesh Arvind Surti in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003673 on 6 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 36 months from the original filing. 105 of the 180 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 19 complaints are on record with the regulator.

At a glance

Project

  • NameRAJ PANTHEON
  • TypeResidential / Group Housing
  • Location
    • off M G Road
    • New Subhash Nagar
    • Borivali
    • Mumbai Suburban
    • 400104
  • Pincode400104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003673
  • ReraGenie IDRG-MH-47567

Builder

  • NameRajesh Arvind Surti
  • Entity typeIndividual
  • Other registrations3 more →
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseDec 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed125 files

Current status

58%105 of 180 units booked
95.0%Work done, per cost certificate

Figures as on 4 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RAJ PANTHEONNA24221746180

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 70%.

RAJ PANTHEON: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 4 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed1423

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,423
Closed/Covered63
Open Space1,360

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,104 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Aug 2025

Approvals and building plan

Sanctioning authorityMHADA
Permissible FSI9409.3
Proposed, not sanctioned5,171 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 5 6 7 LINK HOUSE MALAD W MUMBAI 400064
Estimated costRs 32.00 cr
Cost incurredRs 30.40 cr
Work done95.0%
BuildingWingEstimatedIncurred
RAJ PANTHEONNARs 32.00 crRs 30.40 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR VILAS DIKSHIT
ArchitectMR MAHENDRA N PANCHAL
Engineershersinghchiltora
Chartered AccountantVishal R Trivedi
Chartered AccountantRAMAN S SHAH
Chartered Accountantajay GUPTA
PartnerRole in project
Raj builders & Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013514Dec 2022 → Dec 2023

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 1 YEAR

EXT51800018944Dec 2022 → Jun 2024

Reason as filed by the promoterDue to non-availability of labour & Materials & due to non-availability of financial add on time the project was not completed in time.

EA05082502311Dec 2022 → Dec 2025

Reason as filed by the promoterWe would like to respectfully bring to your attention that the project has encountered cert unforeseen technical challenge that have adversely impacted the originally proposed timelin for completion. We wish to place on record the reason for the delay: Supply Chain Issues for Technical Equipment/Materials. Procurement of specialized materials and equipment (such as lifts, STP units, electrical panels) was delayed due to vendor-side manufacturing backlogs and import-related technic hold-ups. We would like to assure the Authority that despite these unavoidable delays, we rem committed to the com

Complaints filed with MahaRERA19

Case no.ComplainantRespondentFiled
CC006000000056311Bikram singh ButolaRajesh Surti26/09/2018
CC006000000193905Sanjay SharmaRajesh Surti04/09/2020
CC006000000193906Ameeta LewisRajesh Surti05/09/2020
CC12400042james fredrick mascarenhasRajesh Arvind Surti05/09/2024
CC12500247Kaustubh Prithviraj InarkarRajesh Arvind Surti24/01/2025
CC12401110Satyam Deepak MokashiRajesh Arvind Surti12/12/2024
CC12401296Sushma Kishor NerurkarRajesh Arvind Surti31/12/2024
CC12503805Damji ShahRajesh Arvind Surti31/10/2025
CC12503803Premila Damji ShahRajesh Arvind Surti31/10/2025
CC12503930Reshmi Raghunathan NambiarRajesh Arvind Surti09/11/2025
CC12600788Krishnakumar Shiv JhaRajesh Arvind Surti11/02/2026
CC12600843ArunKumar Rambriksh RaiRajesh Arvind Surti14/02/2026
CC12602008Balasubramanian Krishnamurthy IyerRaj builders & Developers05/04/2026
CC12602012Shivkumar Sadashivan NadarRaj builders & Developers05/04/2026
CC12602007Raj Narayana SahuRaj builders & Developers05/04/2026
CC12602094Anwesha Datta GuptaRaj builders & Developers09/04/2026
CC12603627Franky DsouzaRaj builders & Developers12/06/2026
CC12603631Amita Chandrakant ShahRaj builders & Developers12/06/2026
CC12604488Bernadette Denis DsouzaRaj builders & Developers18/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed125

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1 Oct to Dec 2025.pdf4 May 2026
Withdrawal Update Form 2File: Form-2 Oct to Dec 2025.pdf4 May 2026
Withdrawal Update Form 3File: FINAL CA_compressed (1).pdf4 May 2026
Withdrawal Update Form 1File: Form-1.pdf2 May 2026
Withdrawal Update Form 2File: Form-2.pdf2 May 2026
Withdrawal Update Form 3File: Signed Annexure-D_Form-3_Raj Pantheon CA Certificate July to Sept 2025.pdf2 May 2026
Form 2A (FY 2023-2024)File: Form 2A 2023-2024.pdf29 Sep 2025
Form 2A (FY 2024-2025)File: Form 2A 2024-25.pdf29 Sep 2025
Withdrawal Update Form 1File: Form 1.pdf11 Sep 2025
Withdrawal Update Form 2File: Form 2.pdf11 Sep 2025
Withdrawal Update Form 3File: Form 3.pdf11 Sep 2025
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf14 Jul 2025
Details of encumbrances concerned to FinanceFile: No Encumbrances Self Declaration legal.pdf11 Jul 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory January 24 to March 24.pdf11 Jul 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold inventory April 24 to june 24.pdf11 Jul 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold inventory July 24 to September 24.pdf11 Jul 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold inventory October 24 to December 24.pdf11 Jul 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold inventory jan 25 to mar 25.pdf11 Jul 2025
Disclosure of sold/ booked inventoryFile: Sold unsold inventory April 25 to June 25.pdf11 Jul 2025
Details of encumbrances concerned to LegalFile: No Encumbrances Self Declaration legal.pdf11 Jul 2025
Disclosure for secured/unsecured finance availed for the projectFile: No Encumbrances self Declaration finance.pdf11 Jul 2025
Form 1File: architect certificate Jan 24 to march 24.pdf11 Jul 2025
Form 2File: Engineer Certificate 1st Jan 2024 to 31st March 2024.pdf11 Jul 2025
Form 3File: 1 Annexure-D_Form-3_CA Certificate Jan to Mar 2024.pdf11 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory January 24 to March 24.pdf11 Jul 2025
Self-declaration of Quarterly ProgressFile: self declaration.pdf11 Jul 2025
Form 1File: architect certificate April 24 to June 24.pdf11 Jul 2025
Form 2File: Engineer Certificate 1st April 2024 to 30th June 2024.pdf11 Jul 2025
Form 3File: 2 Annexure-D_Form-3_CA Certificate Apr to Jun 2024.pdf11 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold inventory April 24 to june 24.pdf11 Jul 2025
Self-declaration of Quarterly ProgressFile: self declaration.pdf11 Jul 2025
Certificates of CA (Form 3)File: 1 Annexure-D_Form-3_CA Certificate Jan to Mar 2024.pdf10 Jul 2025
Certificates of CA (Form 3)File: 2 Annexure-D_Form-3_CA Certificate Apr to Jun 2024.pdf10 Jul 2025
Certificates of CA (Form 3)File: 3 Annexure-D_Form-3_CA Certificate Jul to Sept 2024.pdf10 Jul 2025
Certificates of CA (Form 3)File: 4 Annexure-D_Form-3_CA Certificate Oct to Dec 2024.pdf10 Jul 2025
Certificates of CA (Form 3)File: 5 Annexure-D_Form-3_CA Certificate Jan to Mar 2025.pdf10 Jul 2025
Certificates of CA (Form 3)File: 6 Annexure-D_Form-3_CA Certificate Apr to Jun 2025.pdf10 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st Jan 2024 to 31st March 2024.pdf9 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st April 2024 to 30th June 2024.pdf9 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st July 2024 to 30th Sept 2024.pdf9 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st Oct 2024 to 31st Dec 2024.pdf9 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st Jan 2025 to 31st Mar 2025.pdf9 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 1st April 2025 to 30th June 2025.pdf9 Jul 2025
Declaration about Commencement CertificateFile: Declation About Commencement Certificate.pdf15 Feb 2024
Declaration in FORM BFile: affidavit Cum declaration.pdf15 Feb 2024
CERSAI detailsFile: sersai declaration.pdf15 Feb 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf13 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 fy 22-23.pdf12 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate oct to dec 23.pdf8 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering certificate Oct to dec 23.pdf8 Feb 2024
Certificates of CA (Form 3)File: CA certificate form 3 oct to dec 23_compressed_compressed.pdf8 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 fy 22-23.pdf8 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate Form 2 Jan To Mar 23.pdf6 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate form 2 Apr To June 23.pdf6 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate form 2 July To Sep 23.pdf6 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1 Jan To Mar 23.pdf3 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 Jan To Mar 23.pdf3 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1 Apr To June 23.pdf3 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1 July To Sep 23.pdf3 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer form 2 jan To mar 23.pdf3 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer form 2 Apr To June 23.pdf3 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer form 2 July To Sep 23.pdf3 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: engineer form 2A FY 22-2023.pdf3 Jan 2024
Certificates of CA (Form 3)File: CA form 3 Jan To Mar 23.pdf3 Jan 2024
Certificates of CA (Form 3)File: CA form 3 Apr To June 23.pdf3 Jan 2024
Certificates of CA (Form 3)File: CA form 3 July To Sep 23.pdf3 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FORM 2 FY 21-22.pdf27 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf26 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer certificate.pdf26 Jan 2023
Certificates of CA (Form 3)File: Form 3 CA.pdf26 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FROM 1 dt 30 JUNE 22.pdf24 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FORM 1 dt 30 SEPT 22.pdf24 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FORM 1 dt 31 DEC 22.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FROM 2 FY 19-20.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER Form 2 dt 31 MAR 22.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FORM 2 dt 30 JUNE 22.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FROM 2 dt 30 SEPT 22.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FROM 2 dt 31 DEC 22.pdf24 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER FROM 2A FY 20-21.pdf24 Jan 2023
Certificates of CA (Form 3)File: CA FORM 3 dt 31 MAR 22.pdf24 Jan 2023

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late2 not delivered by the promised date1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Raj VegaP51800078392Railwaymens Apnaghar CHSL, Mumbai Suburban-Dec 2024Certificate SignedDec 2029Not due yet
Raj ResidencyP51800002739New Subhash Nagar Goregaon West, Mumbai Suburban-Aug 2017OngoingDec 2022Registered original: Dec 2021Not delivered
Raj SpacesP51800008872Borivali, Mumbai Suburban-Aug 2017OngoingDec 2019Registered original: Dec 2018Not delivered
Sai PrasadSubash Nagar NO 3 Motilal Nagar Nagar Goregaon West Mumbai 40010420-CompletedSep 2006Late, Apr 2009

How this compares with Mumbai Suburban

58%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 36 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RAJ PANTHEON on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near New Subhash Nagar6,700+ in Mumbai Suburban

2 kmRAJ PANTHEONCompleted 142Lapsed / revoked 66Other 137Dot size: filed unitsN

Filed coordinates, straight-line distance. 345 registered projects within 2 km.

Builder: Rajesh Arvind Surti

Rajesh Arvind Surti has 4 registrations on MahaRERA, including Raj Residency and RAJ PANTHEON. Its filings disclose 5 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that RAJ PANTHEON shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if RAJ PANTHEON is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RAJ PANTHEON?

The registered promoter entity is Rajesh Arvind Surti, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RAJ PANTHEON?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RAJ PANTHEON?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for RAJ PANTHEON?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RAJ PANTHEON?

The professionals named in the filing: Architect: MR VILAS DIKSHIT; Architect: MR MAHENDRA N PANCHAL; Engineer: shersinghchiltora; Chartered Accountant: Vishal R Trivedi; Chartered Accountant: RAMAN S SHAH; Chartered Accountant: ajay GUPTA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAJ PANTHEON?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAJ PANTHEON. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAJ PANTHEON to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.