Registered No litigation declared Others project

RAJ REGALIA PHASE-2

By AMRUT LAXMI DEVELOPERS

RG-MH-87955 · RERA P51700034369 · Last updated on MahaRERA portal: 23 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 24 months from the original
18 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 97%
73 of 245Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

RAJ REGALIA PHASE-2 is a Others project by AMRUT LAXMI DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700034369 on 4 Apr 2022. Possession is promised by 30 Jun 2027. The completion date has moved by 24 months from the original filing. 172 of the 245 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.

At a glance

Project

  • NameRAJ REGALIA PHASE-2
  • TypeOthers
  • Location
    • SHIV MADIR ROAD
    • NXT TO RELIANCE RESIDENCY
    • Ambarnath (R)
    • Ambarnath
    • Thane
    • 421501
  • Pincode421501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700034369
  • ReraGenie IDRG-MH-87955

Builder

  • NameAMRUT LAXMI DEVELOPERS
  • Entity typePartnership
  • PartnersISHWARLAL NATHU CHAVAN, RAJENDRA MAHADEV PATEL, MAHENDRA JAYANTILAL NAGADA, ROUNAK VASANT NAGADA, HASMUKH RAYSHI HARIYA, VASANT GANGJI NAGADA
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects2 →

Key dates

this monthRegisteredApr 2022First promiseJun 2025Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Apr 2022
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2025)
  • Buildings2 building records
  • Documents filed92 files

Current status

70%172 of 245 units booked
88.5%Work done, per cost certificate

Figures as on 23 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1NA141310919128
BUILDING NO 2NA141310215117

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 97%.

BUILDING NO 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
BUILDING NO 291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%

Progress on shared amenities15

As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed101

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots101
Closed/Covered46
Open Space55
BuildingClosed/CoveredOpen SpaceTotal
BUILDING NO 1232750
BUILDING NO 2232851

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,518 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Apr 2026

Approvals and building plan

Sanctioning authorityAmbernath Municipal Corporation
Permissible FSI16182.88
Proposed, not sanctioned16,183 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAXMI SAGAR APT STATION ROAD AMBERNATH EASE
Estimated costRs 8.36 cr
Cost incurredRs 7.40 cr
Work done88.53%
BuildingWingEstimatedIncurred
-NARs 4.40 crRs 3.52 cr
BUILDING NO 1NARs 1.98 crRs 1.94 cr
BUILDING NO 2NARs 1.98 crRs 1.94 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPIYUSH BANSAL
EngineerPRAMOD KAMBLE
EngineerSantosh Jugalkishore Mall
EngineerSurendra Velji Patel
Chartered AccountantMAYUR JAIN
Chartered AccountantANKIT PARAS JAIN & CO
PartnerRole in project
AMRUT LAXMI DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700024383Jun 2025 → Jun 2026

Reason as filed by the promoterName of the Developer:- M/s Amrutlaxmi Developers Sub:- Application for Extension of RERA Project " Raj Regalia Phase-2 " Respected Sir, We, M/s Amrutlaxmi Developers, have registered for our real estate project "Raj Regalia Phase-2" bearing registration no. P51700034369. The date of completion of the project was given as 30.06.2025 at the time of registration. However, we couldn’t complete said project within the stipulated period due to the finishing work, fire-fighting NOC, electricity main line connection and solar work are yet to be completed. We request to kindly accept our application a

EA23042620712Jun 2025 → Jun 2027

Reason as filed by the promoterDear Sir/Madam, We, Amrut Laxmi Developers, ("AMRUT"), and we are writing you with regards to our application for extension of time till 30th June, 2027; 1. As you are aware that the company is engaged in the constructing a real estate project at Ambernath, Maharashtra on its plot of land comprising of 1 Building Wings having 13 floors.” [hereinafter collectively referred to as "the Project"). 2. We say that we obtained the Rera registration number for Project RAJ REGALIA PHASE-2 at Ambernath, Thane bearing number P51700034369. 3. We say that our project 80% completed in March-2026. Due to dis

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 16th Form 1 ALD P-2 30062026_11zon.pdf23 Jul 2026
Withdrawal Update Form 2File: 16th Form 2 ALD P-2 30062026_11zon.pdf23 Jul 2026
Withdrawal Update Form 3File: 16th Form 3 ALD P-2 30062026_11zon.pdf23 Jul 2026
Withdrawal Update Form 1File: 15th Form 1 ALD P-2 31032026.pdf16 Apr 2026
Withdrawal Update Form 2File: 15th Form 2 ALD P-2 31032026.pdf16 Apr 2026
Withdrawal Update Form 3File: 15th Form 3 ALD P-2 31032026_11zon.pdf16 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A for FY 2025-26_11zon.pdf16 Apr 2026
Withdrawal Update Form 1File: 14th Form 1 ALD P-2 31122025_11zon.pdf14 Jan 2026
Withdrawal Update Form 1File: 14th Form 1 ALD P-2 31122025_11zon.pdf14 Jan 2026
Withdrawal Update Form 2File: 14th Form 2 ALD P-2 31122025_11zon.pdf14 Jan 2026
Withdrawal Update Form 2File: 14th Form 2 ALD P-2 31122025_11zon.pdf14 Jan 2026
Withdrawal Update Form 3File: 14th Form 3 ALD P-2 31122025_11zon.pdf14 Jan 2026
Withdrawal Update Form 3File: 14th Form 3 ALD P-2 31122025_11zon.pdf14 Jan 2026
Withdrawal Update Form 1File: 13th Form 2 ALD P-2 30092025_compressed.pdf24 Nov 2025
Withdrawal Update Form 1File: 13th Form 2 ALD P-2 30092025_compressed.pdf24 Nov 2025
Withdrawal Update Form 1File: 13th Form 2 ALD P-2 30092025_compressed.pdf24 Nov 2025
Withdrawal Update Form 2File: 13th Form 2 ALD P-2 30092025_compressed.pdf24 Nov 2025
Withdrawal Update Form 2File: 13th Form 2 ALD P-2 30092025_compressed.pdf24 Nov 2025
Withdrawal Update Form 2File: 13th Form 2 ALD P-2 30092025_compressed.pdf24 Nov 2025
Withdrawal Update Form 3File: 13th Form 3 ALD P-2 30092025_11zon.pdf24 Nov 2025
Withdrawal Update Form 3File: 13th Form 3 ALD P-2 30092025_11zon.pdf24 Nov 2025
Withdrawal Update Form 3File: 13th Form 3 ALD P-2 30092025_11zon.pdf24 Nov 2025
Form 5 (FY 2024-2025)File: FY 2024-25 Amrut Laxmi Form-5.pdf30 Sep 2025
Form 1File: 12th Form 1 ALD P-2 30062025_11zon.pdf5 Aug 2025
Form 2File: 12th Form 2 ALD P-2 30062025_11zon.pdf5 Aug 2025
Form 3File: 12th Form 3 ALD P-2 30062025_11zon.pdf5 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold June-2025_11zon.pdf5 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10th Form 1 ALD P-2 3112024_11zon.pdf22 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10th Form 3 ALD P-2 3112024_11zon.pdf22 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10th Form 2 ALD P-2 3112024_11zon.pdf22 Feb 2025
Proforma of Agreement for saleFile: Format-Agreement for sale-Phase Plot no 3-Raj Regalia Nx.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9th Form 3 ALD P-2 30092024_11zon.pdf9 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9th Form 1 ALD P-2 30092024_11zon.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9th Form 2 ALD P-2 30092024_11zon.pdf7 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 Raj Regalia Ph 2.pdf7 Nov 2024
Declaration in FORM BFile: Revised Affidavit cum Declaration for Extention_11zon (1).pdf6 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8th Form 1 ALD P-2 30062024.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8th Form 2 ALD P-2 30062024_11zon.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8th Form 3 ALD P-2 30062024_11zon.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A No 3 FY 2021-22_11zon.pdf24 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A No 5 FY 2023-24_11zon.pdf24 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7th Form 1 ALD P-2 31032024_11zon.pdf23 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7th Form 2 ALD P-2 31032024_11zon.pdf23 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7th Form 3 ALD P-2 31032024_11zon.pdf23 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6th Form 1 ALD P-2 31122023_11zon.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6th Form 2 ALD P-2 31122023.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6th Form 3 ALD P-2 31122023_11zon.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5th Form 1 ALD P-2 30092023_11zon.pdf27 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5th Form 2 ALD P-2 30092023_11zon.pdf27 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5th Form 3 ALD P-2 30092023_11zon.pdf27 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: From 5 Raj Regalia Phase-2 FY 2022-23.pdf18 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3rd Form 1 ALD Phase-1A 31032023_11zon.pdf4 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3rd Form 1 ALD P-2 31032023_11zon.pdf4 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4th Form 1 ALD P-2 30062023_11zon.pdf4 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3rd Form 2 ALD P-2 31032023.pdf4 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4th Form 2 ALD P-2 30062023.pdf4 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 31-03-2023_compressed.pdf4 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4th Form 3 ALD P-2 30062023_11zon.pdf4 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3rd Form 1 ALD Phase-1A 31032023_compressed.pdf3 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3rd Form 2 ALD Phase-1A 31032023_compressed.pdf3 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3rd Form 3 ALD P-2 31032023 signed_11zon.pdf3 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ALD Phase-2_compressed.pdf9 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 03-01-23.pdf9 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 06-01-2023_11zon.pdf9 Jan 2023
CERSAI detailsFile: CERSAI_Search_Report_200233277451_For_Asset_Based_Search_24_03_2022_13_28_04_542.pdf25 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase 2_11zon.pdf23 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 compressed.pdf23 Mar 2022
Layout approvalFile: MYSCAN_20211030_0001.pdf10 Mar 2022
Building plan approvalFile: MYSCAN_20211030_0002.pdf10 Mar 2022
Building plan approvalFile: MYSCAN_20211030_0003.pdf10 Mar 2022
Building plan approvalFile: MYSCAN_20211030_0004.pdf10 Mar 2022
Building plan approvalFile: MYSCAN_20211030_0005.pdf10 Mar 2022
Building plan approvalFile: MYSCAN_20211030_0006.pdf10 Mar 2022
PAN CardFile: Amrut pan card.pdf10 Mar 2022
Copy of the legal title reportFile: Legal Title Report Amrut Laxmi Phase2.pdf10 Mar 2022
Copy of the legal title reportFile: Search Report Amrut Laxmi Phase2.pdf10 Mar 2022
Details of encumbrancesFile: Non Encumberance certificate.pdf10 Mar 2022
Copy of Layout Approval (in case of layout)File: MYSCAN_20211030_0001.pdf10 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20211030_0002.pdf10 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20211030_0003.pdf10 Mar 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationRegisteredStatusPromisedDelivered
RAJ REGALIA PHASE-1AP51700024748NR ANAND GREENLAND, ThaneMar 2020Certificate SignedJun 2024Registered original: Jun 2023Jan 2024
RAJ REGALIA - PHASE IP51700017364AMBARNATH, ThaneAug 2018CompletedJun 2021Late, Dec 2021

How this compares with Thane

70%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RAJ REGALIA PHASE-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NXT TO RELIANCE RESIDENCY7,600+ in Thane

2 kmRAJ REGALIA PHASE-2Completed 34Lapsed / revoked 31Other 53Dot size: filed unitsN

Filed coordinates, straight-line distance. 118 registered projects within 2 km.

Builder: AMRUT LAXMI DEVELOPERS

AMRUT LAXMI DEVELOPERS has 3 registrations on MahaRERA, including RAJ REGALIA - PHASE I and RAJ REGALIA PHASE-1A. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if RAJ REGALIA PHASE-2 is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RAJ REGALIA PHASE-2?

The registered promoter entity is AMRUT LAXMI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RAJ REGALIA PHASE-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RAJ REGALIA PHASE-2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RAJ REGALIA PHASE-2?

The professionals named in the filing: Architect: PIYUSH BANSAL; Engineer: PRAMOD KAMBLE; Engineer: Santosh Jugalkishore Mall; Engineer: Surendra Velji Patel; Chartered Accountant: MAYUR JAIN; Chartered Accountant: ANKIT PARAS JAIN & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAJ REGALIA PHASE-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAJ REGALIA PHASE-2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAJ REGALIA PHASE-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.