Home / Browse projects / Mumbai Suburban, Maharashtra / RAJ ALTEZZA
RAJ ALTEZZA
By RAJGURU DEVELOPERS PRIVATE LIMITED
RG-MH-11003 · RERA P51800007125 · Last updated on MahaRERA portal: 27 Feb 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 27 months past the filed date
- 13 complaints at MahaRERA
- Completion date moved by 55 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RAJ ALTEZZA is a Residential / Group Housing project by RAJGURU DEVELOPERS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007125 on 17 Aug 2017. Possession was promised by 31 Jul 2024 and is now 27 months past that date. The completion date has moved by 55 months from the original filing. 13 complaints are on record with the regulator.
At a glance
Project
- NameRAJ ALTEZZA
- TypeResidential / Group Housing
- Location
- J N ROAD
- MULUND WEST
- Kurla
- Mumbai Suburban
- 400080
- Pincode400080
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800007125
- ReraGenie IDRG-MH-11003
Builder
- NameRAJGURU DEVELOPERS PRIVATE LIMITED
- Entity typeCompany
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on17 Aug 2017
- Promised completion31 Jul 2024
- Revised completionRevised to 31 Jul 2024 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed87 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RAJ ALTEZZA | NA | 33 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.
RAJ ALTEZZA: 55% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 83% |
| Podiums (if any) | 85% |
| Plinth | 83% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 83% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 26% |
| Sanitary Fittings within the flats / premises | 1% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 46% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 9% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
Progress on shared amenities15
As on 27 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 40% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 10% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 80% |
Parking filed141
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESIGN CREST |
| Partner | Role in project |
|---|---|
| RAJGURU DEVELOPERS PRIVATE LIMITED | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. Majority of our customers were seeking 98% Home Loan Finance. Loans were sanctioned & / or under process for sanction majorly by NBFC’s i.e. Indiabulls, DHFL etc. Since Sept-2018 there has been a liquidity crunch at these NBFC’s hence they are not able to disburse funds which in turn affected our construction progress leading to a virtual halt in construction activities. Further to add to woes: a) Institutions which were earlier funding upto 98% put a cap on funding of upto 90%. This lead to delays in receipt of payments as customers had to make alternate arrangements for the increase in ow
Reason as filed by the promoter1) In view of COVID-19 pandemic and consequent nation-wide lockdown with effect from March, 2020, reverse migration of labourers to their native places and caused break in supply chain of construction material, the construction activities of real estate projects across the country which severely detrimentally impacted all project across the nation and specifically in Mumbai. 2) Eventually, after struggling to find labourers due to the reverse migration attributable to COVID-19. The construction work began, though slowly due to the restrictions imposed in the city of Mumbai. There was impositio
Complaints filed with MahaRERA13
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000171847 | BHAKTI SAWANT | PRATIK PATEL | 13/01/2020 |
| CC006000000193694 | Pratibha Bahulkar | Rajguru Developers Private Limited | 10/08/2020 |
| CC006000000196856 | Budhia Sutari Patta | Rajguru Developers Pvt. Ltd | 10/05/2021 |
| CC006000000198349 | Roshan Sylvester Castelino | Rajguru Developers Pvt Ltd | 21/09/2021 |
| CC006000000196297 | RAHUL VISANJI VISARIYA | PRATIK HARISH PATEL | 19/03/2021 |
| CC006000000195810 | Om Shanti Ambika Welfare Association | Rajguru Developers Private Limited | 04/02/2021 |
| CC006000000196520 | Veeren Velji Shah | Rajguru Developers Private Limited | 27/03/2021 |
| CC006000000197037 | Reena Bipin Apandkar | Rajguru Developers Pvt Ltd | 25/05/2021 |
| CC006000000197479 | VIJAY LAXMINARAYAN KUSHWAHA | RAJGURU DEVELOPERS PRIVATE LIMITED | 26/07/2021 |
| CC006000000197827 | Manisha Rakesh Rathod | Rajguru developers private limited | 31/07/2021 |
| CC006000000197982 | Suresh Jha | Rajguru Developers Pvt. Ltd. | 15/08/2021 |
| CC006000000282117 | Dhansukh Akhai Patel | Rajguru Developers Private Limited | 27/07/2022 |
| CC006000000429610 | MAHESH JETHALAL JOSHI | PRATIK PATEL | 14/03/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Jul 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed87
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Form 3 Raj Altezza 13-02-24.pdf | 27 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 31-7-21 RA An.pdf | 22 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 14-7-22 RA An.pdf | 22 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 30-6-2023 RA An.pdf | 22 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate RA 13-2-24.pdf | 17 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Rajguru F5.pdf | 17 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Rajguru F5.pdf | 17 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Rajguru F5.pdf | 17 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Rajguru F5.pdf | 17 Feb 2024 |
| Declaration in FORM BFile: Form B RA declaration 2024.pdf | 15 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QAC 13_02_2024_001.pdf | 15 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20_10_2019_001 (2).pdf | 13 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10_04_2020_001.pdf | 13 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10_09_2020_001.pdf | 13 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 15_02_2021_001.pdf | 13 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 31 _07 _2021_001.pdf | 13 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20 _01 _2022_001.pdf | 13 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 14_07_2022_001.pdf | 13 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10 _01_2023_001.pdf | 13 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30_06_2023_001.pdf | 13 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC_ 28_11_2023_001.pdf | 13 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EC _13_03_2024_001.pdf | 13 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: RA Sold -unsold 31-01-2024.pdf | 13 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 20-10-19 Altezza.pdf | 13 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 10-4-20 Altezza.pdf | 13 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 10-9-20 Altezza.pdf | 13 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: RA Sold And Unsold Unit Details.pdf | 10 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2) Architect Certificate__25-10-2021.pdf | 18 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5) Architect Certificate__21-04-2022.pdf | 18 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7) Architect Certificate__13-10-2022.pdf | 18 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 10) Architect Certificate__06-04-2023.pdf | 18 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUC _31_03_2020_001.pdf | 15 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUC 31_03_2021_001.pdf | 15 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUC 31_03_2022_001.pdf | 15 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUC _31_03_2023_001.pdf | 15 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Altezza ARC 20102019.pdf | 8 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Altezza ARC 15012020.pdf | 8 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-10-04-2020.PDF | 8 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-15-06-2020.PDF | 8 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-10-09-2020.PDF | 8 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-30-11-2020.PDF | 8 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-15-02-2021.PDF | 8 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-10-5-2021.PDF | 8 Oct 2021 |
| Certificates of CA (Form 5)File: Rajguru - Form 5 31032018.pdf | 27 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5 Raj Altezza 2019 AJK.pdf | 27 Dec 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Altezza ARC 250719.pdf | 25 Sep 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Raj Altezza Sale Bldg Engineer Cft.pdf | 23 Aug 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: RAJ ALTEZZA SALE - 3 CC COPY.PDF | 22 Jul 2019 |
| Certificates of CA (Form 3)File: RAJ ALTEZZA CA CERTIFICATE 11072019.pdf | 11 Jul 2019 |
| Certificates of CA (Form 3)File: CA CERTIFICATE RAJ ALTEZZA 20082018.pdf | 13 May 2019 |
| Certificates of CA (Form 3)File: RAJ ALTEZA CA CERTIFICATE 15112018.pdf | 13 May 2019 |
| Certificates of CA (Form 3)File: RAJ ALTEZZA CA CERTIFICATE 05022019.pdf | 13 May 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Altezza RERA ARC 300419.pdf | 9 May 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Altezza Sale 30_04_2019.pdf | 9 May 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Altezza ARC 050219.pdf | 20 Feb 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Altezza Sale 05_02_2019.pdf | 20 Feb 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Altezza 15-11-18-20181122133507 COMP.pdf | 17 Dec 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rajguru Arc 200818.pdf | 17 Dec 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rajguru ARCH 310518.PDF | 17 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Altezza Sale 15_11_18.pdf | 4 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Altezza Sale 20_08_18.pdf | 22 Nov 2018 |
| Certificates of CA (Form 3)File: CA CERTIFICATE RAJ ALTEZZA 31052018.pdf | 26 Oct 2018 |
| Certificates of CA (Form 5)File: Rajaltezza F5.pdf | 8 Oct 2018 |
| Certificates of CA (Form 3)File: CA CERTIFICATE RAJ ALTEEZA 28022018.pdf | 3 Aug 2018 |
| Details of encumbrancesFile: altezza pdf 26042018.pdf | 26 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Alteza Rera_Certificate.pdf | 9 Apr 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Altezza Sale 05_03_18.pdf | 9 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Altezza.pdf | 12 Feb 2018 |
| Certificates of CA (Form 3)File: RAJ ALTEZZA 31 DEC 2017.pdf | 12 Feb 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Altezza.pdf | 7 Feb 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Altezza Sale 04_01_18.pdf | 7 Feb 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 01 Raj Altezza.pdf | 10 Nov 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RAJ ALTEZZA.pdf | 10 Nov 2017 |
| Certificates of CA (Form 3)File: RAJ ALTEZZA.pdf | 10 Nov 2017 |
| Declaration in FORM BFile: Altezza.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RAJ ALTEZZA ENGG CERTIFICATE SALE BLDG.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: Raj Altezza CA Certificate.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: Altezza.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Altezza.pdf | 24 Jul 2017 |
| Copy of the legal title reportFile: Raj Altezza.pdf | 20 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 87 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep RAJ ALTEZZA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MULUND WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 382 registered projects within 2 km.
Eternia Towers A to D
Oberoi Constructions Limited
Bellanza Phase 1 - Wing A, B, C at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Atmosphere O2
Atmosphere Realty Pvt Ltd
Bellanza Phase 2 - Wing D, E, F at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Forest Hills Ph 1 at The Prestige City
PRESTIGE MULUND REALTY PRIVATE LIMITED
Kalpataru Elitus
Arimas Real Estate Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: RAJGURU DEVELOPERS PRIVATE LIMITED
RAJGURU DEVELOPERS PRIVATE LIMITED has 1 registration on MahaRERA, including RAJ ALTEZZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that RAJ ALTEZZA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if RAJ ALTEZZA is delayed beyond 31 Jul 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RAJ ALTEZZA?
The registered promoter entity is RAJGURU DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RAJ ALTEZZA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RAJ ALTEZZA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RAJ ALTEZZA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RAJ ALTEZZA?
The professionals named in the filing: Architect: DESIGN CREST. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RAJ ALTEZZA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback