ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / RAHEJA ANTARES - TOWER A

Registered No litigation declared Mixed project

RAHEJA ANTARES - TOWER A

By K RAHEJA CORP REAL ESTATE PRIVATE LIMITED

RG-MH-18553 · RERA P51800077483 · Last updated on MahaRERA portal: 10 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2029Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Podiums (if any), 60%
87 of 196Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 172 documents Report an error

RAHEJA ANTARES - TOWER A is a Mixed project by K RAHEJA CORP REAL ESTATE PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800077483 on 16 Aug 2024. Possession is promised by 30 Nov 2029. 109 of the 196 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRAHEJA ANTARES - TOWER A
  • TypeMixed
  • Location
    • LBS ROAD
    • KANJURMARG
    • Hariyali
    • Kurla
    • Mumbai Suburban
    • 400078
  • Pincode400078
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800077483
  • ReraGenie IDRG-MH-18553

Builder

  • NameK RAHEJA CORP REAL ESTATE PRIVATE LIMITED
  • Entity typeCompany
  • CINU40300MH2007PTC287012
  • GSTIN27AABCF1838M1ZF
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsSUNIL MADHAV HINGORANI, RAMESH RANGANATHAN, RAVI CHANDRU RAHEJA, NEEL CHANDRU RAHEJA
  • Company SecretoryJIGNASHA CHETAN THAKKAR
  • Other registrations20 more →
  • Completed1 of 21
  • No longer live8 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2024PromisedNov 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Aug 2024
  • Promised completion30 Nov 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed172 files

Current status

56%109 of 196 units booked
9.8%Work done, per cost certificate

Figures as on 10 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower ANA353416036196

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 60%.

Tower A: 33% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)60%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed453

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots453
Closed/Covered451
Open Space2

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,784 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Sep 2024
LandownerVillageDistrict
Cinevista LimitedBandraMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI25357.93
Proposed, not sanctioned22,526 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch.5 C/ II, MITTAL COURT,224, NARIMAN POINT,MUMBAI - 400 021
Estimated costRs 175.95 cr
Cost incurredRs 17.23 cr
Work done9.79%
BuildingWingEstimatedIncurred
Tower ANARs 134.09 crRs 15.94 cr
-NARs 41.86 crRs 1.29 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSumit Save
ArchitectSambaprasad Pinge
EngineerVinod Gajananrao Vaidya
EngineerManish Kothari
Chartered AccountantAKPJ & Associates
Chartered AccountantG M Kapadia & Co
PartnerRole in project
K RAHEJA CORP REAL ESTATE PRIVATE LIMITED-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12502097Rahul ChawlaK RAHEJA CORP REAL ESTATE PRIVATE LIMITED26/06/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Aug 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Nov 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Nov 2029

Documents filed172

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 172 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: 2A Antares-A Engineers Quality Assurance Certificate FYE2026 UPLOAD.pdf10 Jun 2026
Commencement certificateFile: 2026-01-22 CC Antares Plans 31102025 UPLOAD.pdf14 Apr 2026
Withdrawal Update Form 1File: 1 Antares-A Architect Certificate 2026-01-08 Dec2025 KRCREPL Plans 311022025 UPLOAD.pdf14 Apr 2026
Withdrawal Update Form 2File: 2 Antares-A Engineer Certificate 2026-01-12 Dec2025 Plans 31102025 UPLOAD.pdf14 Apr 2026
Withdrawal Update Form 3File: 3 Antares-A CA Certificate 2026-03-02 CONSOL with Annxs Dec2025 Plans 31102025 UPLOAD.pdf14 Apr 2026
Withdrawal Update Form 1File: 1 Antares-A Architect Certificate 2026-01-08 Dec2025 KRCREPL Plans 311022025 UPLOAD.pdf5 Mar 2026
Withdrawal Update Form 2File: 2 Antares-A Engineer Certificate 2026-01-12 Dec2025 Plans 31102025 UPLOAD.pdf5 Mar 2026
Withdrawal Update Form 3File: 3 Antares-A CA Certificate 2026-03-02 CONSOL with Annxs Dec2025 Plans 31102025 UPLOAD.pdf5 Mar 2026
Withdrawal Update Form 1File: 1 Antares-A Architect Certificate 2025-11-11 Sept2025 KRCREPL Plans 311022025 UPLOAD.pdf6 Feb 2026
Withdrawal Update Form 2File: 2 Antares-A Engineer Certificate 2025-11-12 Sept2025 Plans 31102025 UPLOAD.pdf6 Feb 2026
Withdrawal Update Form 3File: 3 Antares-A CA Certificate 2026-01-21 CONSOL with Annxs Sept2025 Plans 31102025 UPLOAD.pdf6 Feb 2026
Withdrawal Update Form 1File: 1 Antares-A Architect Certificate 2025-07-17 Jun2025 KRCREPL Plans 11022025 UPLOAD.pdf9 Jan 2026
Withdrawal Update Form 2File: 2 Antares-A Engineer Certificate 2025-07-16 Jun2025 Plans 11022025 UPLOAD.pdf9 Jan 2026
Withdrawal Update Form 3File: 3 Antares-A CA Certificate 2025-08-01 CONSOL with Annxs Jun2025 Plans 11022025 UPLOAD.pdf9 Jan 2026
Building plan approvalFile: 2025-10-31 Antares-A Letter amended approval UPLOAD.pdf24 Nov 2025
Building plan approvalFile: 2025-10-31 Antares-A Drawings Part1 page 1-6 of 27 UPLOAD.pdf24 Nov 2025
Building plan approvalFile: 2025-10-31 Antares-A Drawings Part2 page 7-17 of 27 UPLOAD.pdf24 Nov 2025
Building plan approvalFile: 2025-10-31 Antares-A Drawings Part3 page 18-27 of 27 UPLOAD.pdf24 Nov 2025
Withdrawal Update Form 1File: 1 Antares-A Architect Certificate 2025-07-17 Jun2025 KRCREPL Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 1File: 1 Antares-A Architect Certificate 2025-07-17 Jun2025 KRCREPL Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 1File: 1 Antares-A Architect Certificate 2025-07-17 Jun2025 KRCREPL Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 1File: 1 Antares-A Architect Certificate 2025-07-17 Jun2025 KRCREPL Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 2File: 2 Antares-A Engineer Certificate 2025-07-16 Jun2025 Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 2File: 2 Antares-A Engineer Certificate 2025-07-16 Jun2025 Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 2File: 2 Antares-A Engineer Certificate 2025-07-16 Jun2025 Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 2File: 2 Antares-A Engineer Certificate 2025-07-16 Jun2025 Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 3File: 3 Antares-A CA Certificate 2025-08-01 CONSOL with Annxs Jun2025 Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 3File: 3 Antares-A CA Certificate 2025-08-01 CONSOL with Annxs Jun2025 Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 3File: 3 Antares-A CA Certificate 2025-08-01 CONSOL with Annxs Jun2025 Plans 11022025 UPLOAD.pdf13 Oct 2025
Withdrawal Update Form 3File: 3 Antares-A CA Certificate 2025-08-01 CONSOL with Annxs Jun2025 Plans 11022025 UPLOAD.pdf13 Oct 2025
Form 5 (FY 2024-2025)File: 5 Antares-A FYE2025 Form-5 SET consol+krcrepl+cvl UPLOAD.pdf29 Sep 2025
Withdrawal Update Form 1File: 1 Antares-A Architect Certificate 2025-07-17 Jun2025 KRCREPL Plans 11022025 UPLOAD.pdf4 Aug 2025
Withdrawal Update Form 2File: 2 Antares-A Engineer Certificate 2025-07-16 Jun2025 Plans 11022025 UPLOAD.pdf4 Aug 2025
Withdrawal Update Form 3File: 3 Antares-A CA Certificate 2025-08-01 CONSOL with Annxs Jun2025 Plans 11022025 UPLOAD.pdf4 Aug 2025
Withdrawal Update Form 1File: 1 Antares-A Architect Certificate 2025-04-15 Mar2025 KRCREPL Plans 11022025 UPLOAD.pdf16 Jul 2025
Withdrawal Update Form 2File: 2 Antares-A Engineer Certificate 2025-04-16 Mar2025 Plans 11022025 UPLOAD.pdf16 Jul 2025
Withdrawal Update Form 3File: 3 Antares-A CA Certificate 2025-04-25 CONSOL with Anns Mar2025 Plans 11022025 UPLOAD.pdf16 Jul 2025
Form 2A (FY 2024-2025)File: 2A Antares-A Engineer's Quality Assurance Certificate FYE2025 UPLOAD.pdf22 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Antares-A Architect Certificate 2025-04-15 Mar2025 KRCREPL Plans 11022025 UPLOAD.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Antares-A CA Certificate 2025-04-25 CONSOL with Anns Mar2025 Plans 11022025 UPLOAD.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Antares-A Engineer Certificate 2025-04-16 Mar2025 Plans 11022025 UPLOAD.pdf28 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: 2025-04-16 - CC Plinth Antares (Cinevista) Plans 11022025 UPLOAD.pdf25 Apr 2025
Declaration about Commencement CertificateFile: CC Declaration Antares-A 2025-04-24 UPLOAD.pdf25 Apr 2025
Details of encumbrances concerned to FinanceFile: Encumbrance Antares A KRCREPL 2025-04-10 Finance UPLOAD.pdf16 Apr 2025
Proforma of Allotment letterFile: AL Antares-A KRCREPL-Cinevista 2025-04-04 UPLOAD.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Antares-A Self Declaration on Form 1-2-3 Q4 FY25 Consol UPLOAD.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Antares-A Self Declaration on Form 1-2-3 Q4 FY25 Consol UPLOAD.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Antares-A Self Declaration on Form 1-2-3 Q4 FY25 Consol UPLOAD.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: Antares-A Inventory 2025-03-31 UPLOAD.pdf16 Apr 2025
CERSAI detailsFile: CERSAI Declaration and Cersai Report Antares-A 2025-04-10 UPLOAD.pdf16 Apr 2025
Details of encumbrances concerned to LegalFile: Encumbrance Antares A KRCREPL 2025-04-10 Finance UPLOAD.pdf16 Apr 2025
Proforma of Agreement for saleFile: AFS Antares-A KRCREPL 2025-03-18 UPLOAD.pdf16 Apr 2025
Home Buyer /Allottee Grievance Redressal CellFile: Antares-A Greivance Cell and Complaints Status Q4FY25 UPLOAD.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Antares-A Architect Certificate 2025-03-07 Jan2025 KRCREPL Plans 11022025 UPLOAD.pdf14 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Antares-A CA Certificate 2025-03-13 Consol with Anns Jan2025 Plans 11022025 UPLOAD.pdf14 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Antares-A Engineer Certificate 2025-03-07 Jan2025 Plans 11022025 UPLOAD.pdf14 Mar 2025
Building plan approvalFile: 2025-02-11 Antares Letter Amended approval UPLOAD.pdf7 Mar 2025
Building plan approvalFile: 2025-02-11 Antares-A Drawings HL Part1 UPLOAD.pdf7 Mar 2025
Building plan approvalFile: 2025-02-11 Antares-A Drawings HL Part2 UPLOAD.pdf7 Mar 2025
Building plan approvalFile: 2025-02-11 Antares-A Drawings HL Part3 UPLOAD.pdf7 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025-02-11 Antares Letter Amended approval UPLOAD.pdf7 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025-02-11 Antares-A Drawings HL Part1 UPLOAD.pdf7 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025-02-11 Antares-A Drawings HL Part2 UPLOAD.pdf7 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025-02-11 Antares-A Drawings HL Part3 UPLOAD.pdf7 Mar 2025
Proforma of Allotment letterFile: AL Antares-A KRCREPL-Cinevista 2024-10-18 UPLOAD.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Antares-A Self Declaration on Form 1-2-3 Q3 FY25 Consol UPLOAD.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Antares-A Self Declaration on Form 1-2-3 Q3 FY25 Consol UPLOAD.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Antares-A Self Declaration on Form 1-2-3 Q3 FY25 Consol UPLOAD.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Antares-A Inventory 2024-12-31 UPLOAD.pdf18 Jan 2025
Proforma of Agreement for saleFile: AFS Antares-A KRCREPL 2024-10-28 UPLOAD.pdf18 Jan 2025
Home Buyer /Allottee Grievance Redressal CellFile: Antares-A Complaints Status Q4FY25 UPLOAD.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Antares-A Architect Certificate 2024-12-23 Oct2024 KRCREPL Plans 29042024 UPLOAD.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Antares-A CA Certificate 2024-12-18 Consol with Annexures (Oct2024) UPLOAD.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Antares-A Engineer Certificate 2024-12-17 Oct2024 Plans 29042024 UPLOAD.pdf3 Jan 2025
Proforma of Agreement for saleFile: AFS Antares-A KRCREPL 2024-10-07 revised UPLOAD.pdf11 Dec 2024
Proforma of Allotment letterFile: AL Antares-A KRCREPL-Cinevista 2024-10-08 UPLOAD.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Antares-A Self Declaration on Form 1-2-3 Q2 FY25 Consol UPLOAD.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Antares-A Self Declaration on Form 1-2-3 Q2 FY25 Consol UPLOAD.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Antares-A Self Declaration on Form 1-2-3 Q2 FY25 Consol UPLOAD.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Antares-A Inventory 2024-09-30 UPLOAD.pdf18 Oct 2024

How this compares with Mumbai Suburban

56%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RAHEJA ANTARES - TOWER A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANJURMARG6,700+ in Mumbai Suburban

2 kmRAHEJA ANTARES - TOWER ACompleted 47Lapsed / revoked 32Other 114Dot size: filed unitsN

Filed coordinates, straight-line distance. 193 registered projects within 2 km.

Builder: K RAHEJA CORP REAL ESTATE PRIVATE LIMITED

K Raheja Corp Real Estate Private Limited has 21 registrations on MahaRERA, including Estrella, Viva, Pirangut and Orion, Viva, Pirangut. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 16 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if RAHEJA ANTARES - TOWER A is delayed beyond 30 Nov 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RAHEJA ANTARES - TOWER A?

The registered promoter entity is K RAHEJA CORP REAL ESTATE PRIVATE LIMITED, a company as per the filing. Its CIN U40300MH2007PTC287012 and GSTIN 27AABCF1838M1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RAHEJA ANTARES - TOWER A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RAHEJA ANTARES - TOWER A?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for RAHEJA ANTARES - TOWER A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RAHEJA ANTARES - TOWER A?

The professionals named in the filing: Architect: Sumit Save; Architect: Sambaprasad Pinge; Engineer: Vinod Gajananrao Vaidya; Engineer: Manish Kothari; Chartered Accountant: AKPJ & Associates; Chartered Accountant: G M Kapadia & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAHEJA ANTARES - TOWER A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAHEJA ANTARES - TOWER A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAHEJA ANTARES - TOWER A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.