Home / Browse projects / Mumbai Suburban, Maharashtra / RAGHAV ONE

Completed No litigation declared Residential / Group Housing project

RAGHAV ONE

By RAGHAV RAJ BUILDERS & DEVELOPERS LLP

RG-MH-03093 · RERA P51800020496 · Last updated on MahaRERA portal: 31 Dec 2021

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • 1 extension taken

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 3 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2021Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
2Complaints at MahaRERAon this registration
Jump to the 36 documents Report an error

RAGHAV ONE is a Residential / Group Housing project by RAGHAV RAJ BUILDERS & DEVELOPERS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800020496 on 18 Apr 2019. The registration is recorded completed; possession was promised by 30 Jun 2021. 2 complaints are on record with the regulator.

At a glance

Project

  • NameRAGHAV ONE
  • TypeResidential / Group Housing
  • Location
    • Ashtvinayak Marg
    • Nehru Nagar
    • Kurla
    • Mumbai Suburban
    • 400024
  • Pincode400024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800020496
  • ReraGenie IDRG-MH-03093

Builder

  • NameRAGHAV RAJ BUILDERS & DEVELOPERS LLP
  • Entity typePartnership
  • LLPINAAD-0888
  • LLPIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersSUDHANSHU RAMAVTAR AGARWAL, SUSHMA LALIT GOLECHA
  • Other registrations9 more →
  • Completed2 of 10
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredApr 2019PromisedJun 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 Apr 2019
  • Promised completion30 Jun 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed36 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RAGHAV ONENA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

RAGHAV ONE: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 31 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable
GYMYes100%

Parking filed7

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots7
Closed/Covered1
Open Space6

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area883 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
RAGHAV RAJ BUILDERS & DEVELOPERS LLPAndheriMumbai Suburban

Approvals and building plan

Permissible FSI6993.66
Proposed, not sanctioned2,503 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Maurya Estate, Link Road, Andheri West, Mumbai 400053

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCREATIVE CONSULTANCY
PartnerRole in project
RAGHAV RAJ BUILDERS & DEVELOPERS LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009963Jun 2021 → Dec 2021

Reason as filed by the promoterExtension sought for further 6 months till 31 December 2021 because of the present COVID-19 senerio and shortage of manpower.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000196987Ashapurti Co-operative Housing Society Ltd., Nehru Nagar Kurla EastMr. Sudhanshu Agarwal13/05/2021
CC006000000220981nitin chandrakant ShindeSudhanshu Ramavtar Agarawal27/04/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Apr 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Dec 2021

Documents filed36

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 CA certificate FY 2020-21.pdf31 Dec 2021
OtherFile: OC Full.pdf16 Dec 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full OC.pdf10 Dec 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC upto 16th floor.pdf2 Nov 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Intimation to RERA regarding Ashapurti Society Formation.pdf8 Oct 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architect's Certificate.pdf7 Oct 2021
OtherFile: Society formation Declaration.pdf30 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.pdf27 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A QUALITY CERTIFICATE June 2020.pdf18 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A QUALITY CERTIFICATE Sept 2020.pdf18 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A QUALITY CERTIFICATE December 2020.pdf18 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A QUALITY CERTIFICATE March 2021.pdf18 Sep 2021
Disclosure of sold/ booked inventoryFile: Circular 29 Disclosure of sold and unsold units.pdf18 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FROM 5 CA CERTIFICATE.pdf18 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 For annual report of CA(FY 2018-19).pdf18 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FROM 5 CA CERTIFICATE.pdf18 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FROM 5 CA CERTIFICATE FY 19-20.pdf5 Jul 2021
Copy of the legal title reportFile: Legal Title Report as per RERA.pdf2 Jul 2021
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf2 Jul 2021
OtherFile: Encumberance Information.pdf2 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: Full C C.pdf1 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A QUALITY CERTIFICATE.pdf1 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf17 Sep 2020
Proforma of Allotment letterFile: Proforma of Agreement for Sale.pdf17 Sep 2020
Details of Restarting of Construction work post lockdownFile: Construction Status.pdf23 Jun 2020
Building plan approvalFile: Building Plan Approval IOD.pdf8 Apr 2019
Building Plan Approval (IOD)File: Building Plan Approval IOD.pdf8 Apr 2019
Certificates of CA (Form 3)File: Certificate of CA (Form 3).pdf8 Apr 2019
Proforma of Allotment letterFile: Allotment Letter - draft.pdf8 Apr 2019
Layout approvalFile: Part Layout - Nehru Nagar.pdf6 Apr 2019
PAN CardFile: PAN.pdf6 Apr 2019
Copy of the legal title reportFile: Title Certificate.pdf6 Apr 2019
Details of encumbrancesFile: Details of Encumbrances.pdf6 Apr 2019
Copy of Layout Approval (in case of layout)File: Part Layout - Nehru Nagar.pdf6 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf6 Apr 2019
Declaration in FORM BFile: Form B - notarised.pdf6 Apr 2019

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
RAGHAV MARVELP51800045396Nehrunagar, Mumbai Suburban-May 2022CompletedAug 2025Registered original: Aug 2024Aug 2025
RAGHAV AMARAP51800030338Kurla East, Mumbai Suburban-Aug 2021CompletedSep 2024Registered original: Jul 2023Sep 2024
RAGHAV ONE45KURLA EAST93-CompletedFeb 2023Feb 2023

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RAGHAV ONE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nehru Nagar6,700+ in Mumbai Suburban

2 kmRAGHAV ONECompleted 126Lapsed / revoked 118Other 160Dot size: filed unitsN

Filed coordinates, straight-line distance. 404 registered projects within 2 km.

Builder: RAGHAV RAJ BUILDERS & DEVELOPERS LLP

RAGHAV RAJ BUILDERS & DEVELOPERS LLP has 10 registrations on MahaRERA, including RAGHAV ONE and RAGHAV ONE45. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if RAGHAV ONE is delayed beyond 30 Jun 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RAGHAV ONE?

The registered promoter entity is RAGHAV RAJ BUILDERS & DEVELOPERS LLP, a partnership as per the filing. Its LLPIN AAD-0888 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RAGHAV ONE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RAGHAV ONE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for RAGHAV ONE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RAGHAV ONE?

The professionals named in the filing: Architect: CREATIVE CONSULTANCY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAGHAV ONE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAGHAV ONE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAGHAV ONE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.