RAGHAV RAJ BUILDERS & DEVELOPERS LLP has 10 registrations in this build, including RAGHAV ONE and RAGHAV ONE45. Its filings disclose 4 earlier MahaRERA projects: 3 of 4 past projects completed on time.

10Registrations in this build
4Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
RAGHAV ONEMumbai Suburban, Maharashtra--Completed
RAGHAV ONE45Mumbai Suburban, Maharashtra--Completed
RAGHAV AMARAMumbai Suburban, Maharashtra--Registration lapsed
RAGHAV MARVELMumbai Suburban, Maharashtra--Registration lapsed
RAGHAV ANANTAMumbai Suburban, Maharashtra--Registered
RAGHAV ENCLAVEMumbai Suburban, Maharashtra4738%Registered
RAGHAV VISTAMumbai Suburban, Maharashtra9954%Registered
RAGHAV SERENITYMumbai Suburban, Maharashtra1464%Registered
RAGHAV AVENUEMumbai Suburban, Maharashtra8642%Registered
RAGHAV ORCHIDMumbai Suburban, Maharashtra--Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
RAGHAV ONE
P51800020496
30 Jun 20219 Dec 2021+5 months
RAGHAV ONE45
28 Feb 202328 Feb 2023On time
RAGHAV AMARA
P51800030338
20 Sep 202420 Sep 2024On time
RAGHAV MARVEL
P51800045396
30 Aug 202528 Aug 2025On time

Frequently asked questions

How do I verify RAGHAV RAJ BUILDERS & DEVELOPERS LLP as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with RAGHAV RAJ BUILDERS & DEVELOPERS LLP?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.