ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / RADHARAMAN PARK

Registration lapsed No litigation declared Residential / Group Housing project

RADHARAMAN PARK

By MAHALAXMI CONSTRUCTION

RG-MH-25843 · RERA P52100013324 · Last updated on MahaRERA portal: 12 Mar 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 37 months past the filed date
  • Completion date moved by 45 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2023Possession promised37 months past this date
4 of 11Construction stages donefurthest along: Staircases, 80%
0Complaints at MahaRERAon this registration
Jump to the 24 documents Report an error

RADHARAMAN PARK is a Residential / Group Housing project by MAHALAXMI CONSTRUCTION in Pune, Maharashtra, registered with MahaRERA as P52100013324 on 22 Sep 2017. Possession was promised by 30 Sep 2023 and is now 37 months past that date. The completion date has moved by 45 months from the original filing.

At a glance

Project

  • NameRADHARAMAN PARK
  • TypeResidential / Group Housing
  • Location
    • WAGHOLI
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100013324
  • ReraGenie IDRG-MH-25843

Builder

  • NameMAHALAXMI CONSTRUCTION
  • Entity typePartnership
  • PartnersVIJAY DNYANOBA MORE, DNYANESHWAR MAHADEV KALBHOR, CHETAN KASHINATH SALUNKE
  • Other registrations9 more →
  • Completed4 of 10
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

37 months past promisethis monthRegisteredSep 2017First promiseDec 2019Revised toSep 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Sep 2017
  • Promised completion30 Sep 2023
  • Revised completionRevised to 30 Sep 2023 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed24 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RADHARAMAN PARKNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 80%.

RADHARAMAN PARK: 52% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area735 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI945.58
Proposed, not sanctioned746 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKADAMWAK WASTI PUNE

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR MILIND NAGNATH PANCHAL
PartnerRole in project
MAHALAXMI CONSTRUCTION-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005241Dec 2019 → Dec 2020

Reason as filed by the promoterAs per form E

EXT52100011481Dec 2019 → Sep 2022

Reason as filed by the promoterNo single booking is received till the date. No revenue is generated from the site till the date and hence there is delay in completion of the project. Considering no booking and no revenue is generated kindly extend the project completion date.

EXT52100012602Dec 2019 → Sep 2023

Reason as filed by the promoterNO single booking is received till the date hence there is fund problem and delay in the project

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed24

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CERSAI detailsFile: CERSAI - Debtor_Based_Search Mahalaxmi.pdf12 Mar 2022
CERSAI detailsFile: CERSAI -Asset_Based_Search Mahalaxmi.pdf12 Mar 2022
Declaration about Commencement CertificateFile: Declaration of Commencement Cert.pdf7 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A FY 20-21.pdf7 Mar 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf7 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-2020.pdf7 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 20-21.pdf7 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2A.pdf31 Dec 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf27 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 1718.pdf27 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 1819.pdf25 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf31 May 2018
Layout approvalFile: Layout.pdf19 Sep 2017
Building plan approvalFile: floor plan.pdf19 Sep 2017
Building plan approvalFile: elevation.pdf19 Sep 2017
PAN CardFile: PAN CARD.pdf19 Sep 2017
Copy of the legal title reportFile: search titile report.pdf19 Sep 2017
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf19 Sep 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf19 Sep 2017
Building Plan Approval (IOD)File: floor plan.pdf19 Sep 2017
Building Plan Approval (IOD)File: elevation.pdf19 Sep 2017
Declaration in FORM BFile: form B.pdf19 Sep 2017
Certificates of CA (Form 3)File: C A Certificate.PDF19 Sep 2017
Proforma of Allotment letterFile: allotment letter and agreement to sale.pdf19 Sep 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 45 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RADHARAMAN PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WAGHOLI13,700+ in Pune

2 kmRADHARAMAN PARKCompleted 62Lapsed / revoked 26Other 43Dot size: filed unitsN

Filed coordinates, straight-line distance. 131 registered projects within 2 km.

Builder: MAHALAXMI CONSTRUCTION

MAHALAXMI CONSTRUCTION has 10 registrations on MahaRERA, including AKSHARDHAM and Shiv Kuteer. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that RADHARAMAN PARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if RADHARAMAN PARK is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RADHARAMAN PARK?

The registered promoter entity is MAHALAXMI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RADHARAMAN PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RADHARAMAN PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RADHARAMAN PARK?

The professionals named in the filing: Architect: MR MILIND NAGNATH PANCHAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RADHARAMAN PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RADHARAMAN PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RADHARAMAN PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.