Home / Browse projects / Nagpur, Maharashtra / RACHANA ASHWINI

Completed No litigation declared Residential / Group Housing project

RACHANA ASHWINI

By Rachana Developers

RG-MH-90548 · RERA P50500020724 · Last updated on MahaRERA portal: 13 Dec 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 11 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Apr 2022Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

RACHANA ASHWINI is a Residential / Group Housing project by Rachana Developers in Nagpur, Maharashtra, registered with MahaRERA as P50500020724 on 6 May 2019. The registration is recorded completed; possession was promised by 30 Apr 2022.

At a glance

Project

  • NameRACHANA ASHWINI
  • TypeResidential / Group Housing
  • Location
    • NEAR KATOL ROAD
    • BESIDE FIRE ENGINEERING COLLEGE JAGDISH NAGAR BOREGAON
    • Borgaon Khu.
    • Nagpur (Rural)
    • Nagpur
    • 440013
  • Pincode440013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500020724
  • ReraGenie IDRG-MH-90548

Builder

  • NameRachana Developers
  • Entity typePartnership
  • Partnersshishir shankarrao Diote, Nilima shishir Diote, Raunak Shishir Diote
  • Other registrations11 more →
  • Completed8 of 12
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2019PromisedApr 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 May 2019
  • Promised completion30 Apr 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed63 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RACHANA ASHWININA1110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

RACHANA ASHWINI: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes30%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes30%
Landscaping & Tree PlantingYes10%
Street LightingYes0%
Community BuildingsYes80%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes60%
Open ParkingYes0%

Parking filed100

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots100
Closed/Covered40
Open Space60

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,639 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
RACHANA DEVELOPERSNagpur (M Corp.)Nagpur

Approvals and building plan

Permissible FSI6466.47
Proposed, not sanctioned6,399 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCHANDAK BHAVAN GROUND FLOOR NORTH AMBAZARI ROAD SHANKAR NAGAR NAGPUR

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectULLAS MUDE
PartnerRole in project
Rachana Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 May 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 May 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Dec 2021

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: occupancy certificate.pdf13 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: Arch Completion Form 4.pdf13 Dec 2021
OtherFile: DEVELOPER MARCH22.pdf12 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ULHAS MUDE R-ASHWINI.pdf5 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PRANIL KACHOLE RACHANA-ASHWINI.pdf5 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: MOHAN INGLE RACHANA ASHWINI 2.pdf5 Oct 2021
Certificates of CA (Form 3)File: SB RACHANA ASHWINI_compressed.pdf5 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ashwini 31-03-21.pdf14 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ashwini 30-06-21.pdf14 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC Ashwini 31-03-21.pdf14 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC Ashwini 30-06-21.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ashwini 004-March 21.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ashwini 001-June 21.pdf14 Aug 2021
Disclosure of sold/ booked inventoryFile: Ashwini 30-06-21.pdf14 Aug 2021
Certificates of CA (Form 3)File: CA Ashwini_31-03-21.pdf14 Aug 2021
Certificates of CA (Form 3)File: CA Ashwini_30-06-21.pdf14 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Ashwini 19-20 FORM 5.pdf31 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ashwini March 20.pdf17 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ashwini June 20.pdf17 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ashwini Sept 20.pdf17 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ashwini Dec 20.pdf17 May 2021
Certificates of CA (Form 3)File: Ashwini 31032020compressed.pdf15 May 2021
Certificates of CA (Form 3)File: Ashwini 30062020compressed.pdf15 May 2021
Certificates of CA (Form 3)File: Ashwini 30092020compressed.pdf15 May 2021
Certificates of CA (Form 3)File: Ashwini 31122020compressed.pdf15 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ashwini 31032020.pdf11 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ashwini 31032020.pdf11 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ashwini 30062020.pdf11 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ashwini 30092020.pdf11 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ashwini 31122020.pdf11 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ashwini 31032020.pdf11 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ashwini30062020.pdf11 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ashwini 30092020.pdf11 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ashwini 31122020.pdf11 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATES 300619.pdf23 Oct 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATES 300619.pdf23 Oct 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE 300919.pdf23 Oct 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE 311219.pdf23 Oct 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 300619.pdf23 Oct 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 300919.pdf23 Oct 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 311219.pdf23 Oct 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY CERTIFICATE 300619.pdf23 Oct 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY CERTIFICATE 300919.pdf23 Oct 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY CERTIFICATE 311219.pdf23 Oct 2020
Certificates of CA (Form 3)File: C A CERTIFICATE 300619.pdf23 Oct 2020
Certificates of CA (Form 3)File: CA CERTIFICATE 300919.pdf23 Oct 2020
Certificates of CA (Form 3)File: C A CERTIFICATE 311219.pdf23 Oct 2020
OtherFile: Developer Certificate.pdf22 Jan 2020
Building plan approvalFile: parking.pdf2 May 2019
Building plan approvalFile: Elevation.pdf2 May 2019
Building plan approvalFile: Floor Plan.pdf2 May 2019
Layout approvalFile: scan map.pdf2 May 2019
Copy of the legal title reportFile: Tittle Search report.pdf2 May 2019
Copy of Layout Approval (in case of layout)File: scan map.pdf2 May 2019
Building Plan Approval (IOD)File: parking.pdf2 May 2019
Building Plan Approval (IOD)File: Elevation.pdf2 May 2019
Building Plan Approval (IOD)File: Floor Plan.pdf2 May 2019
Certificates of CA (Form 3)File: C A FORM 3.pdf2 May 2019
Proforma of Allotment letterFile: Allotment letter.pdf2 May 2019
PAN CardFile: pan card mithila.pdf29 Apr 2019
Details of encumbrancesFile: Emcumbrance.pdf29 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: NIT Letter.pdf29 Apr 2019
Declaration in FORM BFile: FORM B.pdf29 Apr 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationStatusPromisedDelivered
Rachana Mithila Phase 1KH No 8 Mouza- Pipla Nagpur Rural 440034CompletedJul 2017Jul 2017

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RACHANA ASHWINI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BESIDE FIRE ENGINEERING COLLEGE JAGDISH NAGAR BOREGAON2,800+ in Nagpur

2 kmRACHANA ASHWINICompleted 13Lapsed / revoked 2Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: Rachana Developers

Rachana Developers has 12 registrations on MahaRERA, including Rachana Samruddhi and GURUVIHAR. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if RACHANA ASHWINI is delayed beyond 30 Apr 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RACHANA ASHWINI?

The registered promoter entity is Rachana Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RACHANA ASHWINI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for RACHANA ASHWINI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RACHANA ASHWINI?

The professionals named in the filing: Architect: ULLAS MUDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RACHANA ASHWINI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RACHANA ASHWINI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RACHANA ASHWINI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.