ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / QUE 914 PHASE I

Completed No litigation declared Residential / Group Housing project

QUE 914 PHASE I

By Unique Choice Associates LLP

RG-MH-41778 · RERA P52100046034 · Last updated on MahaRERA portal: 14 Mar 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
16 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
3 of 257Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

QUE 914 PHASE I is a Residential / Group Housing project by Unique Choice Associates LLP in Pune, Maharashtra, registered with MahaRERA as P52100046034 on 15 Jun 2022. The registration is recorded completed; possession was promised by 31 Dec 2026. 254 of the 257 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete.

At a glance

Project

  • NameQUE 914 PHASE I
  • TypeResidential / Group Housing
  • Location
    • 24 mtr DP Road
    • Keshavnagar
    • Mundhwa
    • Keshavnagar-Mundwa
    • Pune City
    • Pune
    • 411036
  • Pincode411036
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100046034
  • ReraGenie IDRG-MH-41778

Builder

  • NameUnique Choice Associates LLP
  • Entity typePartnership
  • PartnersNikhil Vinod Goyal, Ashok Rajendraprasad Agarwal, Navin Rajendra Agarwal, Abhishek Raj Agrawal, Vipul Ashok Agarwal, Manoj Ashok Agarwal, Vijay Anantram Goyal, Mukesh Anantram Goyal, Amit Ashok Agrawal, Prannay Arun Agrawal, Pratik Vinod Agarwal, Seema Hemant Jain
  • Other registrations2 more →
  • Completed1 of 3

Key dates

this monthRegisteredJun 2022PromisedDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Jun 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed99 files

Current status

99%254 of 257 units booked
100.0%Work done, per cost certificate

Figures as on 14 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA131144044
BNA24222130213

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

A90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
B90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 14 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes20%
Community BuildingsYes95%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes80%
Energy managemcntYes80%
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed235

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots235
Closed/Covered202
Open Space33
BuildingClosed/CoveredOpen SpaceTotal
A13922
B18924213

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,428 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI28152.2
Proposed, not sanctioned28,152 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch3, Signet House, Alandi Road, Yerwada, Pune - 411006
Estimated costRs 97.66 cr
Cost incurredRs 97.66 cr
Work done100.0%
BuildingWingEstimatedIncurred
BNARs 79.70 crRs 79.70 cr
-NARs 9.77 crRs 9.77 cr
ANARs 8.20 crRs 8.20 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnish Damodar Tambe
EngineerPrashant Tike
Chartered AccountantHarsh Julaniya
Chartered AccountantAGH & Associates
PartnerRole in project
Unique Choice Associates LLP-

Litigation declared2

CaseCourtStatus
1007/2016H S Puradupadhye Jt CJSD PuneWithdrawn
1276/2023D T Vasave CJSD PunePending Adjudication

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Completion Certificate.pdf14 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf18 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf18 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf18 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf22 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf22 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf22 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf22 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf22 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf22 Dec 2025
Form 5 (FY 2022-2023)File: Form 5 (2022-23).pdf22 Dec 2025
Form 5 (FY 2023-2024)File: Form 5 (2023-24).pdf22 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 (2024-25).pdf22 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf14 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf14 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure Of Inventory.pdf6 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf28 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 (2023-24).pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf18 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf18 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf25 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf25 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf25 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf25 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf16 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory 15-07-2023.pdf21 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Jul 2023
Layout approvalFile: Layout - 1.pdf22 Jun 2023
Layout approvalFile: Layout - 2.pdf22 Jun 2023
Building plan approvalFile: Plan 1.pdf22 Jun 2023
Building plan approvalFile: Plan 2.pdf22 Jun 2023
Building plan approvalFile: Plan 3.pdf22 Jun 2023
Building plan approvalFile: Plan 4.pdf22 Jun 2023
Building plan approvalFile: Plan 5.pdf22 Jun 2023
Building plan approvalFile: Plan 6.pdf22 Jun 2023
Building plan approvalFile: Plan 7.pdf22 Jun 2023
Building plan approvalFile: Plan 8.pdf22 Jun 2023
Copy of Layout Approval (in case of layout)File: Layout - 1.pdf22 Jun 2023
Copy of Layout Approval (in case of layout)File: Layout - 2.pdf22 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 1.pdf22 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 2.pdf22 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 3.pdf22 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 4.pdf22 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 5.pdf22 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 6.pdf22 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 7.pdf22 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 8.pdf22 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate - 1.pdf22 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate - 2.pdf22 Jun 2023
Declaration about Commencement CertificateFile: Format D.pdf22 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf1 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf16 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf16 Apr 2023
Proforma of Allotment letterFile: Final Agreement Draft A_Mhada_Building.pdf3 Sep 2022
Proforma of Allotment letterFile: Final Agreement Draft B Building.pdf3 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf31 May 2022
Proforma of Allotment letterFile: Final Agreement to sale draft (1).pdf31 May 2022
Layout approvalFile: Layout Sanction.pdf30 May 2022
Layout approvalFile: Layout Commencement.pdf30 May 2022
Building plan approvalFile: Building Sanction.pdf30 May 2022

How this compares with Pune

99%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep QUE 914 PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Keshavnagar, Mundhwa13,700+ in Pune

2 kmQUE 914 PHASE ICompleted 58Lapsed / revoked 14Other 43Dot size: filed unitsN

Filed coordinates, straight-line distance. 115 registered projects within 2 km.

Builder: Unique Choice Associates LLP

Unique Choice Associates LLP has 3 registrations on MahaRERA, including QUE 914 PHASE I and QUE 914 PHASE II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if QUE 914 PHASE I is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of QUE 914 PHASE I?

The registered promoter entity is Unique Choice Associates LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in QUE 914 PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for QUE 914 PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at QUE 914 PHASE I?

The professionals named in the filing: Architect: Anish Damodar Tambe; Engineer: Prashant Tike; Chartered Accountant: Harsh Julaniya; Chartered Accountant: AGH & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in QUE 914 PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About QUE 914 PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save QUE 914 PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.