ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / PUSHKAR CO OP HSG SOCIETY PRAPOSED

Completed No litigation declared Others project

PUSHKAR CO OP HSG SOCIETY PRAPOSED

By AMEYA DEVELOPERS

RG-MH-28284 · RERA P51700025616 · Last updated on MahaRERA portal: 19 Apr 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 11 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Feb 2024Possession promisedregistration recorded completed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 8%
0Complaints at MahaRERAon this registration
Jump to the 27 documents Report an error

PUSHKAR CO OP HSG SOCIETY PRAPOSED is a Others project by AMEYA DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700025616 on 1 Jul 2020. The registration is recorded completed; possession was promised by 12 Feb 2024.

At a glance

Project

  • NamePUSHKAR CO OP HSG SOCIETY PRAPOSED
  • TypeOthers
  • Location
    • NANDIVALI ROAD
    • OPP DNC HIGH SCHOOL
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700025616
  • ReraGenie IDRG-MH-28284

Builder

  • NameAMEYA DEVELOPERS
  • Entity typePartnership
  • PartnersPRASHANT SUDHIR KHADILKAR, MILIND YASHWANT PHATAK, ALANKAR RAJESH SOMWANSHI, MAHALAXMI DARSHAN INDULKAR, PARESH GOVIND VELANKAR, ANUP DINKAR MHATRE, SANTOSH SHANKAR PATIL, SOHAM MANOJ PHATAK
  • Other registrations11 more →
  • Completed5 of 12
  • No longer live5 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

this monthRegisteredJul 2020PromisedFeb 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Jul 2020
  • Promised completion12 Feb 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed27 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AMEYA DEVELOPERSNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 8%.

AMEYA DEVELOPERS: 28% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered2
Open Space4

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area516 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1006.0
Proposed, not sanctioned514 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHAHID BHAGAT SINGH ROAD DOMBIVALI EAST BRANCH

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAUNAK PRASHANT KHADILKAR
EngineerMANJUNATH VENKATESH PAI
Chartered AccountantAVINASH MORE & ASSOCIATES
PartnerRole in project
AMEYA DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Mar 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Apr 2023

Documents filed27

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Pushkar CHS Completion Certificate.pdf19 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: New Engineer Certificate.pdf8 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ameya Develpopers - RERA (1).pdf7 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: New CC Copy.pdf2 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: New Architect Certificate.pdf22 Sep 2021
Building plan approvalFile: New Ranade Kulkarni Plan.pdf7 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: New Ranade Kulkarni Plan.pdf7 Sep 2021
Building plan approvalFile: New Plan Copy upto 7th Floors.pdf16 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: New Plan Copy upto 7th Floors.pdf16 Jun 2021
OtherFile: Plan Sanction Copy 1.pdf16 Jun 2021
Layout approvalFile: Layout Plan.pdf20 Mar 2020
Building plan approvalFile: FINAL PLAN COPY.pdf20 Mar 2020
PAN CardFile: Ameya Developers Pan Card.pdf20 Mar 2020
Copy of the legal title reportFile: Title Report Anjali Kulkarni.pdf20 Mar 2020
Copy of the legal title reportFile: Title Report Ujawala Ranade.pdf20 Mar 2020
Copy of the legal title reportFile: Search Report Anjali Kularni.pdf20 Mar 2020
Copy of the legal title reportFile: Search Report Ujawala Ranade.pdf20 Mar 2020
Details of encumbrancesFile: Letter of Emcumbrances.pdf20 Mar 2020
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf20 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: FINAL PLAN COPY.pdf20 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Copy Ranade Kulkarni.pdf20 Mar 2020
Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf20 Mar 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Architect Certificate.pdf20 Mar 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf20 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Rera Certificate Annexure A(1).pdf20 Mar 2020
Proforma of Allotment letterFile: SALE AGREEMENT of PUSHKAR CHS.pdf20 Mar 2020
Proforma of Allotment letterFile: Allotment letter.pdf20 Mar 2020

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PUSHKAR CO OP HSG SOCIETY PRAPOSED on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OPP DNC HIGH SCHOOL7,600+ in Thane

2 kmPUSHKAR CO OP HSG SOCIETCompleted 38Lapsed / revoked 30Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 91 registered projects within 2 km.

Builder: AMEYA DEVELOPERS

Ameya Developers has 12 registrations on MahaRERA, including Priya Girish Vihar CHS Ltd and UMEDS CENTRAL APARTMENT CHS. Its filings disclose 7 earlier MahaRERA projects: declares 7 of 7 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if PUSHKAR CO OP HSG SOCIETY PRAPOSED is delayed beyond 12 Feb 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PUSHKAR CO OP HSG SOCIETY PRAPOSED?

The registered promoter entity is AMEYA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PUSHKAR CO OP HSG SOCIETY PRAPOSED?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PUSHKAR CO OP HSG SOCIETY PRAPOSED?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PUSHKAR CO OP HSG SOCIETY PRAPOSED?

The professionals named in the filing: Architect: RAUNAK PRASHANT KHADILKAR; Engineer: MANJUNATH VENKATESH PAI; Chartered Accountant: AVINASH MORE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PUSHKAR CO OP HSG SOCIETY PRAPOSED?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PUSHKAR CO OP HSG SOCIETY PRAPOSED. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PUSHKAR CO OP HSG SOCIETY PRAPOSED to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.