Home / Browse projects / Pune, Maharashtra / Purvanchal F Building

Registration lapsed Litigation declared Residential / Group Housing project

Purvanchal F Building

By VTP Corpartion LLP

RG-MH-12875 · RERA P52100021535 · Last updated on MahaRERA portal: 29 Aug 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • Litigation declared, 2 cases
  • 2 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 45.00 crore secured on the land, in favour of CAPRI GLOBAL CAPITAL LIMITED

Clear

  • Separate project account declared
  • Allotment letter follows the model form

7 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 75%
6 of 84Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 87 documents Report an error

Purvanchal F Building is a Residential / Group Housing project by VTP Corpartion LLP in Pune, Maharashtra, registered with MahaRERA as P52100021535 on 8 Jul 2019. Possession was promised by 29 Jun 2025 and is now 16 months past that date. The completion date has moved by 12 months from the original filing. 78 of the 84 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NamePurvanchal F Building
  • TypeResidential / Group Housing
  • Location
    • Wagholi kesnand Road
    • kesnand
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100021535
  • ReraGenie IDRG-MH-12875

Builder

  • NameVTP Corpartion LLP
  • Entity typePartnership
  • PartnersVilaskumar Thanmal Palresha, Nilesh Vilaskumar Palresha, Dheeraj Prabhakar Malineni, Manoj Prabhakar Malineni
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredJul 2019First promiseJun 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Jul 2019
  • Promised completion29 Jun 2025
  • Revised completionRevised to 29 Jun 2025 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed87 files

Current status

93%78 of 84 units booked

Figures as on 29 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
F1 and F2 buildingNA9784084

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 75%.

F1 and F2 building: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 29 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes88%
Water SupplyYes88%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes75%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes55%
Solid Waste Management And DisposalYes40%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes25%
Electrical meter room, sub-station, receiving stationYes45%
Aggregate area of recreational Open SpaceYes45%
Open ParkingYes0%

Parking filed110

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots110
Closed/Covered100
Open Space10

Land and ownership10

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,138 sq m
Land owned byThe promoter, with other names on the file
Named landowners10
Encumbrance on the landDeclared present
Charge in favour ofCAPRI GLOBAL CAPITAL LIMITED
Secured amountRs 45.00 crore
CERSAI search filedYes
Declared on9 Jul 2025
LandownerVillageDistrict
Ramchandra JadhavKesnandPune
Balasaheb JadhavKesnandPune
Nandkumar JadhavKesnandPune
Dattatray JadhavKesnandPune
Vilas Waval-Pune
Sunil Gaikwad-Pune
Pandurang Waval-Pune
Nitin Dhumal-Pune
Lata Satav-Pune
Dattatray Hargude-Pune

Approvals and building plan

Sanctioning authorityPUNE METROPOLITAN REGIONAL DEVELOPMENT AUTHORITY
Permissible FSI6702.78
Proposed, not sanctioned6,703 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSAKORE NAGAR

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVTP Realty
ArchitectAnkur Associates
ArchitectMinal Firake
EngineerRAJESH MORE
EngineerVTP Realty
Chartered AccountantCA Priyanka Chordiya
Chartered AccountantS A C CO & LLP
PartnerRole in project
VTP Corpartion LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024237Jun 2024 → Jun 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

Litigation declared2

CaseCourtStatus
87/2015/2015CJSDPending
57/2015CJSDOngoing

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12601046VTP Corpartion LLPMr ABDUL KADAR MOHAMMED HAROON26/02/2026
CC12601053VTP Corpartion LLPBAJIRAO BALASAHEB KADAM26/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jun 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jun 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jun 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jun 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Jun 2024

Documents filed87

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: FORM 5- PURVANCHAL F.pdf29 Aug 2025
Form 2A (FY 2024-2025)File: FORM 2A PURVANCHAL F BUILDING.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Purvanchal F Building.pdf22 Apr 2025
Certificates of CA (Form 3)File: FORM 3 Purvanchal F Building.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Purvanchal F FORM 2.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: PURVANCHAL F BLDG 31032025.pdf7 Apr 2025
Disclosure of sold/ booked inventoryFile: PURVANCHAL F BLDG 31122024.pdf16 Jan 2025
Certificates of CA (Form 3)File: Form 3 - Purvanchal F.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM PURVANCHAL F 31122024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Phase III.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Purvanchal F Building 30092024.pdf29 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PURVANCHAL F BUILDING 30092024.pdf19 Oct 2024
Certificates of CA (Form 3)File: FORM_3_Purvanchal_Building_30-09-2024_compressed.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: PURVANCHAL F.pdf14 Oct 2024
Declaration in FORM BFile: AFFIDAVIT-PURVANCHAL F BUILDING.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Phase III - Form 5.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Purvanchal F Building 30062024.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PURVANCHAL F BUILDING 30062024.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Phase III.pdf18 Jul 2024
Certificates of CA (Form 3)File: form 3 Purvanchal 3.pdf18 Jul 2024
Disclosure of sold/ booked inventoryFile: PURVANCHAL F 30062024.pdf10 Jul 2024
Declaration in FORM BFile: 20240703004050_rotated.pdf3 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: kesnand F1 building completion certificate.pdf4 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A PURVANCHAL PHASE 3 31032024.pdf16 May 2024
Disclosure of sold/ booked inventoryFile: INVENTIORY PURVANCHAL PHASE 3 31122023.pdf10 May 2024
Disclosure of sold/ booked inventoryFile: INVENTIORY PURVANCHAL PHASE 3 31032024.pdf10 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PURVANCHAL PHASE 3 31032024.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PURVANCHAL PHASE 3 31032024.pdf26 Apr 2024
Certificates of CA (Form 3)File: FORM 3 PURVANCHAL PHASE 3 31032024.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PURVANCHAL F 31122023.pdf23 Jan 2024
Certificates of CA (Form 3)File: FORM 3 PURVANCHAL F 31122023.pdf23 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PURVANCHAL F 31122023.pdf13 Jan 2024
Disclosure of sold/ booked inventoryFile: INVENTORY PURVANCHAL F 30062022.pdf8 Nov 2023
Disclosure of sold/ booked inventoryFile: INVENTORY PURVANCHAL F 30092022.pdf8 Nov 2023
Disclosure of sold/ booked inventoryFile: INVENTORY PURVANCHAL F 31122022.pdf8 Nov 2023
Disclosure of sold/ booked inventoryFile: INVENTORY PURVANCHAL F 31032023.pdf8 Nov 2023
Disclosure of sold/ booked inventoryFile: INVENTORY PURVANCHAL F 30062023.pdf8 Nov 2023
Disclosure of sold/ booked inventoryFile: INVENTORY PURVANCHAL F 30092023.pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PURVANCHAL PHASE 3 30092023.pdf28 Oct 2023
Certificates of CA (Form 3)File: FORM 3 PURVANCHAL PHASE 3 30092023.pdf28 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PURVANCHAL F 30092023.pdf9 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Form 5 Purvanchal phase 3 22-23.pdf14 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM 1 PURVNCHAL F 30062023.pdf12 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Purvanchal Phase III - 300623.pdf25 Aug 2023
Certificates of CA (Form 3)File: FORM 3 PURVANCHAL PHASE 3 30062023_compressed.pdf21 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PURVANCHAL PH 3 30062022.pdf26 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PURVANCHAL PH 3 30092022.pdf26 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PURVANCHAL PH 3 31122022.pdf26 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PURVANCHAL PH 3 31032023.pdf26 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate PhIII Dec-21.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate Purvanchal PhIII Mar22.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate Purvanchal PhIII Jun-22.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate Purvanchal PhIII Dec-22.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate Purvanchal PhIII Sep-22.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate Purvanchal PhIII Mar-23.pdf23 Jun 2023
Certificates of CA (Form 3)File: Form 3 Purvanchal PhIII Dec-22_compressed.pdf23 Jun 2023
Certificates of CA (Form 3)File: Form 3 Purvanchal PhIII Mar-23_compressed.pdf23 Jun 2023
Certificates of CA (Form 3)File: VTP Corp PhIII, Jun-22_compressed.pdf25 May 2023
Certificates of CA (Form 3)File: VTP Corp PhIII, Sept-22_compressed.pdf25 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Purvanchal PhIII 300621.pdf13 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Purvanchal PhIII 300921.pdf13 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31122021.pdf13 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31032022.pdf13 Mar 2023
Certificates of CA (Form 3)File: Form 3 30062021_compressed (2).pdf13 Mar 2023
Certificates of CA (Form 3)File: Form 3 30092021_compressed (2).pdf13 Mar 2023
Certificates of CA (Form 3)File: Form 3 31122021_compressed (2).pdf13 Mar 2023
Certificates of CA (Form 3)File: Form 3 31032022_compressed (3).pdf13 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Purvanchal Phase III.pdf3 Dec 2022
Details of encumbrancesFile: Purvanchal F.pdf14 Nov 2022
Disclosure of sold/ booked inventoryFile: Purvanchal F.pdf12 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SIGNED FORM-5_PH III_compressed.pdf1 Mar 2022
Disclosure of sold/ booked inventoryFile: Purvanchal F.pdf12 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: f bldg-jan 21 to march 21.pdf11 Dec 2021
Declaration about Commencement CertificateFile: Purvanchal F.pdf18 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: f bldg-jan 20 to march 20.pdf18 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Purvanchal Phase III 2019-20.pdf14 Jul 2021
Certificates of CA (Form 3)File: fORM 3 (2).pdf28 Jun 2019
Details of encumbrancesFile: Encumbrance_Certificate.pdf17 Jun 2019
Building plan approvalFile: NEW BLOCK-Model-compressed (1).pdf15 Jun 2019
Layout approvalFile: NEW BLOCK-Model-compressed (1).pdf15 Jun 2019

How this compares with Pune

93%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Purvanchal F Building on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near kesnand13,700+ in Pune

2 kmPurvanchal F BuildingCompleted 12Lapsed / revoked 10Other 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: VTP Corpartion LLP

VTP Corpartion LLP has 2 registrations on MahaRERA, including Purvanchal Phase1 AB and Purvanchal F Building. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Purvanchal F Building shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Purvanchal F Building is delayed beyond 29 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Purvanchal F Building?

The registered promoter entity is VTP Corpartion LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Purvanchal F Building?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Purvanchal F Building?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Purvanchal F Building?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Purvanchal F Building?

The professionals named in the filing: Architect: VTP Realty; Architect: Ankur Associates; Architect: Minal Firake; Engineer: RAJESH MORE; Engineer: VTP Realty; Chartered Accountant: CA Priyanka Chordiya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Purvanchal F Building?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Purvanchal F Building. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Purvanchal F Building to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.