ReraGenieLog inGet a buyer report

Home / Browse projects / Ratnagiri, Maharashtra / PTK Heights

Completed No litigation declared Residential / Group Housing project

PTK Heights

By Santosh Ramchandra Tadsare

RG-MH-19858 · RERA P52800006399 · Last updated on MahaRERA portal: 19 May 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
20 of 33Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 80%
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

PTK Heights is a Residential / Group Housing project by Santosh Ramchandra Tadsare in Ratnagiri, Maharashtra, registered with MahaRERA as P52800006399 on 14 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2023.

At a glance

Project

  • NamePTK Heights
  • TypeResidential / Group Housing
  • Location
    • guhagar bypass road
    • pagmala chiplun
    • Chiplun (M Cl)
    • Chiplun
    • Ratnagiri
    • 415605
  • Pincode415605
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800006399
  • ReraGenie IDRG-MH-19858

Builder

  • NameSantosh Ramchandra Tadsare
  • Entity typeIndividual
  • Other registrations2 more →
  • Completed1 of 3
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2017PromisedJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Aug 2017
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings3 building records
  • Documents filed88 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WingNA50000
A WingNA100000
C wingNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 19 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 80%.

B Wing73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A Wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C wing39%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%

Progress on shared amenities15

As on 19 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed188

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots188
Closed/Covered157
Open Space31
BuildingClosed/CoveredOpen SpaceTotal
B Wing891099
A Wing672087
C wing112

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
Shakuntala Govind ShindeChiplun (M Cl)Ratnagiri
Anil Dattatraya PalandeChiplun (M Cl)Ratnagiri
Aruna Ramesh SawantChiplun (M Cl)Ratnagiri
Yashwant Shamrao MoreChiplun (M Cl)Ratnagiri
Preshit Yashwant MoreChiplun (M Cl)Ratnagiri
Pravin Yashwant MoreChiplun (M Cl)Ratnagiri

Approvals and building plan

Permissible FSI4144.12
Proposed, not sanctioned3,004 sq m
Buildings approved3
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchChiplun Karad Road chiplun Dist - Ratnagiri

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectChaitanya P Peshve
EngineerRavindra M Patil
PartnerRole in project
Santosh Ramchandra Tadsare-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Feb 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Jan 2022

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: ca.pdf19 May 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: soc.pdf29 Jan 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc 20.pdf21 Jan 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc 21.pdf21 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ptk 4qtr eng 20-compressed.pdf29 Oct 2021
Certificates of CA (Form 3)File: ptk 4qtr ca 20-compressed.pdf29 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect-cert-14-170321.pdf18 Mar 2021
Certificates of CA (Form 5)File: PTK HEIGHTS - 2020-Q3-compressed.pdf17 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ptk 3rd-compressed.pdf10 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q3 engg.pdf4 Jun 2020
Certificates of CA (Form 3)File: Q3 ca.pdf4 Jun 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3rd qtr-compressed.pdf6 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PTK HEIGHTS_RERA CERTIFICATE_3rd qtr.pdf26 Feb 2020
Certificates of CA (Form 5)File: PTK HEIGHTS_RERA CERTIFICATE_3rd qtr.pdf25 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect-cert-11-311219 2nd qtr-compressed.pdf10 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: architect-cert-11-311219 2nd qtr-compressed.pdf10 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 0001-converted-compressed.pdf28 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 0005-converted-compressed.pdf28 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 0009-converted-compressed.pdf28 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 0013-converted-compressed.pdf28 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 0014-converted-compressed.pdf28 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 0021-converted-compressed.pdf28 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 0025-converted-compressed.pdf28 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 0029-converted-compressed.pdf28 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 0033-converted-compressed (1).pdf28 Dec 2019
Building plan approvalFile: 0001-converted-compressed.pdf19 Dec 2019
Building plan approvalFile: 0003-converted-compressed.pdf19 Dec 2019
Building plan approvalFile: 0006-converted-compressed.pdf19 Dec 2019
Building plan approvalFile: permission-compressed.pdf19 Dec 2019
Building Plan Approval (IOD)File: 0001-converted-compressed.pdf19 Dec 2019
Building Plan Approval (IOD)File: 0003-converted-compressed.pdf19 Dec 2019
Building Plan Approval (IOD)File: 0006-converted-compressed.pdf19 Dec 2019
Building Plan Approval (IOD)File: permission-compressed.pdf19 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: com.pdf19 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 0003-converted.pdf19 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1st qtr.pdf17 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2qtr-compressed.pdf17 Dec 2019
Certificates of CA (Form 5)File: SUMITRA RERA CERTIFICATE Q 2 2019-20 2nd qtr-compressed.pdf17 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect-cert-7-190219 3rd qtr.pdf11 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect-cert-6-171018 2nd qtr.pdf11 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's certificate-1qtr 17919-compressed.pdf29 Nov 2019
Certificates of CA (Form 5)File: FORM 3- CA CERTIFICATE (1).pdf29 Nov 2019
OtherFile: completion certificate.pdf29 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Doc 2019-07-09 1.pdf9 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Doc 22219 3rd qtr.pdf9 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Doc 22219 3rd qtr.pdf9 Jul 2019
Certificates of CA (Form 3)File: 8719.pdf8 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect-cert- 18519.pdf18 May 2019
Certificates of CA (Form 3)File: FORM 3 CERTIFICATE-compressed.pdf4 Mar 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 221118.pdf22 Nov 2018
Certificates of CA (Form 3)File: 221118.pdf22 Nov 2018
Certificates of CA (Form 5)File: CERTIFICATE-compressed.pdf13 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Doc 2018-08-18.pdf18 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Doc 2018-08-18 (1).pdf18 Aug 2018
Certificates of CA (Form 3)File: 123(1).pdf4 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Doc 2018-07-25d (1).pdf25 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect-cert 20718.pdf24 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect-30418.pdf1 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30418.pdf1 May 2018
Certificates of CA (Form 3)File: 1-5-18.pdf1 May 2018
Certificates of CA (Form 3)File: 15218.pdf15 Feb 2018
Building plan approvalFile: images (2).pdf10 Feb 2018
Building plan approvalFile: images.pdf10 Feb 2018
Building Plan Approval (IOD)File: images (2).pdf10 Feb 2018
Building Plan Approval (IOD)File: images.pdf10 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: nagarpalika new.pdf10 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg.pdf10 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.pdf30 Jan 2018
Certificates of CA (Form 3)File: 123.pdf7 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: images.pdf30 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5.pdf28 Oct 2017
Copy of the legal title reportFile: New Doc 2017-07-28 (2).pdf28 Jul 2017
Layout approvalFile: New Doc 2017-07-27.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: New Doc 2017-07-27.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New Doc 2017-07-27.pdf27 Jul 2017
Proforma of Allotment letterFile: Sumitra Developers - Allotment - booking letter.pdf27 Jul 2017
Proforma of Allotment letterFile: Agreement - Sumitra Developers - Chiplun - RERA (1).pdf27 Jul 2017
Building plan approvalFile: New Doc 2017-07-26 (1).pdf26 Jul 2017
Building plan approvalFile: New Doc 2017-07-26.pdf26 Jul 2017
Building Plan Approval (IOD)File: New Doc 2017-07-26.pdf26 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Ramchandra ParkShivaji Nagar Chiplun45CompletedMar 2012Oct 2011

How this compares with Ratnagiri

15%of Ratnagiri projects moved their completion datethis one has not
30%of Ratnagiri registrations have lapsed or been cancelledthis one is completed

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep PTK Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near pagmala chiplun1,100+ in Ratnagiri

2 kmPTK HeightsCompleted 39Lapsed / revoked 23Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 80 registered projects within 2 km.

Builder: Santosh Ramchandra Tadsare

Santosh Ramchandra Tadsare has 3 registrations on MahaRERA, including PTK Heights and SAROJINI PLAZA. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if PTK Heights is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PTK Heights?

The registered promoter entity is Santosh Ramchandra Tadsare, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PTK Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PTK Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PTK Heights?

The professionals named in the filing: Architect: Chaitanya P Peshve; Engineer: Ravindra M Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PTK Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PTK Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PTK Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.