Home / Browse projects / Mumbai Suburban, Maharashtra / PSK ALTAIR 77

Registered No litigation declared Others project

PSK ALTAIR 77

By JAYDEEP DEVELOPERS

RG-MH-18878 · RERA P51800077820 · Last updated on MahaRERA portal: 15 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2028Possession promisedmoved 4 months from the original
2 of 11Construction stages donefurthest along: Basement (if any), 93%
14 of 17Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

PSK ALTAIR 77 is a Others project by JAYDEEP DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800077820 on 7 Nov 2024. Possession is promised by 30 Apr 2028. The completion date has moved by 4 months from the original filing. 3 of the 17 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NamePSK ALTAIR 77
  • TypeOthers
  • Location
    • SARASWATI ROAD
    • SANTACRUZ WEST
    • Bandra
    • Andheri
    • Mumbai Suburban
    • 400054
  • Pincode400054
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800077820
  • ReraGenie IDRG-MH-18878

Builder

  • NameJAYDEEP DEVELOPERS
  • Entity typePartnership
  • Declared earlier projects2 →

Key dates

this monthRegisteredNov 2024First promiseDec 2027Revised toApr 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Nov 2024
  • Promised completion30 Apr 2028
  • Revised completionRevised to 30 Apr 2028 (originally 31 Dec 2027)
  • Buildings1 building record
  • Documents filed56 files

Current status

18%3 of 17 units booked
33.0%Work done, per cost certificate

Figures as on 15 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PSK ALTAIR 77NA11013417

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 93%.

PSK ALTAIR 77: 53% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)93%
Podiums (if any)85%
Plinth100%
Stilt Floor85%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks48%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed68

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots68
Closed/Covered68

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,356 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Jul 2025
LandownerVillageDistrict
LOPA CO-OPERATIVE SOCIETY LIMITEDBandraMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI4552.08
Proposed, not sanctioned2,320 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 3 CENTRUM BUILDING WAGLE ESTATE THANE WEST 400604
Estimated costRs 29.49 cr
Cost incurredRs 9.73 cr
Work done32.99%
BuildingWingEstimatedIncurred
PSK ALTAIR 77NARs 17.69 crRs 9.73 cr
-NARs 11.80 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTaranath Shetty & Associates
EngineerRajesh Ganpat Choudhari
Chartered AccountantNehali & Co.
Chartered AccountantVikram Viresh Bhate
PartnerRole in project
JAYDEEP DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P51800077820/WarDec 2027 → Apr 2028

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2028

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form - 1_Q1_JDN.pdf15 Sep 2026
Withdrawal Update Form 2File: JDN_Form 2_Q1.pdf15 Sep 2026
Withdrawal Update Form 3File: JDN_Form-3_Q4.pdf15 Sep 2026
Withdrawal Update Form 1File: Form 1_Q4_JDN.pdf6 Jun 2026
Withdrawal Update Form 2File: JDN_Form-2_Q4.pdf6 Jun 2026
Withdrawal Update Form 3File: JDN_Form-3_Q4.pdf6 Jun 2026
Withdrawal Update Form 1File: Form - 1_Q3_JDN.pdf20 May 2026
Withdrawal Update Form 2File: JDN_Form-2_Q3.pdf20 May 2026
Withdrawal Update Form 3File: JDN_Form-3_Q3.pdf20 May 2026
Withdrawal Update Form 1File: Form - 1_Q2_JDN.pdf4 May 2026
Withdrawal Update Form 2File: JDN_Form-2_Q2.pdf4 May 2026
Withdrawal Update Form 3File: JDN_Form-3_Q2.pdf4 May 2026
Withdrawal Update Form 1File: Form - 1_Q1_JDN.pdf16 Apr 2026
Withdrawal Update Form 2File: JDN_Form-2_Q1.pdf16 Apr 2026
Withdrawal Update Form 3File: Declaration in form 3.pdf16 Apr 2026
Form 1File: Form 1 (1).pdf12 Jul 2025
Form 2File: Form 2 (2).pdf12 Jul 2025
Form 3File: Form 3 (3).pdf12 Jul 2025
Disclosure of Sold and Booked InventoryFile: Discoluser of Inventory.pdf12 Jul 2025
Other - TechnicalFile: Unit details statement certificate.pdf24 Jan 2025
Other - TechnicalFile: Unit details statement certificate.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration in form 3.pdf23 Oct 2024
Building plan approvalFile: APPROVED IOD CERTIFICATE_LOPA CHS.pdf11 Oct 2024
Layout approvalFile: FINAL 3 PLAN.pdf11 Oct 2024
PAN CardFile: Pan Card.pdf11 Oct 2024
Copy of the legal title reportFile: Legal Title Report Dt FINAL.pdf11 Oct 2024
Details of encumbrances concerned to FinanceFile: No Encumbrance of Project_rotated.pdf11 Oct 2024
Details of encumbrances concerned to FinanceFile: No Encumbrance of land (1)_rotated (1).pdf11 Oct 2024
Copy of Layout Approval (in case of layout)File: FINAL 3 PLAN.pdf11 Oct 2024
Proforma of Allotment letterFile: ALLOTMENT LETTER FINAL (10) (1).pdf11 Oct 2024
Declaration in FORM BFile: Form b Declaration project_compressed.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_rotated (1).pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (5).pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_rotated.pdf11 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: PSK Altair 77 FirstCC_signed.pdf11 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: APPROVED IOD CERTIFICATE_LOPA CHS.pdf11 Oct 2024
Declaration about Commencement CertificateFile: Format D (2).pdf11 Oct 2024
CERSAI detailsFile: Cersai_rotated.pdf11 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A (10).pdf11 Oct 2024
Deviation Report with respect to Allotment letterFile: Deviation Report (2).pdf11 Oct 2024
Details of encumbrances concerned to LegalFile: No Encumbrance of Project_rotated.pdf11 Oct 2024
Details of encumbrances concerned to LegalFile: No Encumbrance of land (1)_rotated (1).pdf11 Oct 2024
Other - TechnicalFile: Annexure A (10).pdf11 Oct 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report on Agreement 08-10-2024.pdf11 Oct 2024
Proforma of Agreement for saleFile: AGREEMENT FOR SALE MARKED IN YELLOW DEVIATION (1) (1) (1).pdf11 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Premji Patel_rotated.pdf11 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Annexure-A (Disclosure of Interest in Other Real Estate Organisation (4-10-2024).pdf11 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 7 Disclosure of Interest on Other real estate Organisation (5-10-2024).pdf11 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf11 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosuer (1)_rotated.pdf11 Oct 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
CREST AND CELESTIAP51800030894AMBEDKAR NAGAR MULUND EAST, Mumbai Suburban83Sep 2021CompletedDec 2024Registered original: Dec 2022Jul 2024
ANUTHAMP51800006653mulund east, Mumbai Suburban-Aug 2017CompletedJun 2023Registered original: Nov 2020Jun 2023

How this compares with Mumbai Suburban

18%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 4 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PSK ALTAIR 77 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SANTACRUZ WEST6,700+ in Mumbai Suburban

2 kmPSK ALTAIR 77Completed 120Lapsed / revoked 67Other 125Dot size: filed unitsN

Filed coordinates, straight-line distance. 312 registered projects within 2 km.

Builder: JAYDEEP DEVELOPERS

JAYDEEP DEVELOPERS has 1 registration on MahaRERA, including PSK ALTAIR 77. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if PSK ALTAIR 77 is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PSK ALTAIR 77?

The registered promoter entity is JAYDEEP DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PSK ALTAIR 77?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PSK ALTAIR 77?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PSK ALTAIR 77?

The professionals named in the filing: Architect: Taranath Shetty & Associates; Engineer: Rajesh Ganpat Choudhari; Chartered Accountant: Nehali & Co.; Chartered Accountant: Vikram Viresh Bhate. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PSK ALTAIR 77?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PSK ALTAIR 77. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PSK ALTAIR 77 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.