ReraGenieLog inGet a buyer report

Home / Browse projects / Pristine Heights

Registered No litigation declared Residential / Group Housing project

Pristine Heights

By GOLD SUKH LIFESCAPES LLP

RG-MH-05496 · RERA P51900050986 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Mar 2027Possession promisedmoved 12 months from the original
3 of 11Construction stages donefurthest along: Internal walls, 90%
4 of 30Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

Pristine Heights is a Residential / Group Housing project by GOLD SUKH LIFESCAPES LLP in Parel, 400012, registered with MahaRERA as P51900050986 on 19 May 2023. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 26 of the 30 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NamePristine Heights
  • TypeResidential / Group Housing
  • Location
    • Dr Babasaheb Ambedkar Road
    • Parel
    • 400012
  • Pincode400012
  • RERA no.P51900050986
  • ReraGenie IDRG-MH-05496

Builder

  • NameGOLD SUKH LIFESCAPES LLP
  • Entity typePartnership
  • GSTIN27AALFG6006F1ZJ
  • PartnersKAMLESH HARISH JAIN, RUPA HARISH JAIN, RITESH HARISH JAIN

Key dates

this monthRegisteredMay 2023First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 May 2023
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed66 files

Current status

87%26 of 30 units booked
55.3%Work done, per cost certificate

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Pristine HeightsNA222230030

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

Pristine Heights: 59% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered32

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area576 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jul 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI4941.22
Proposed, not sanctioned4,230 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShrin Manzil coop hsg society Shop No 3 to 7 mazgaon mumbai 10
Estimated costRs 23.00 cr
Cost incurredRs 12.73 cr
Work done55.33%
BuildingWingEstimatedIncurred
Pristine HeightsNARs 23.00 crRs 12.73 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNilesh Kadakia
EngineerPiyush Sura
Chartered AccountantChintan Shah
PartnerRole in project
GOLD SUKH LIFESCAPES LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA26032620384Mar 2026 → Mar 2027

Reason as filed by the promoterI, Kamlesh Jain, Partner of M/s Gold Sukh Lifescapes LLp, the promoter of the above-mentioned redevelopment project, hereby submit this application seeking extension of the project registration period under section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The subject project is a redevelopment project and the construction could not be completed within the stipulated period due to reasons beyond the control of the Promoter. At the initiai stage of the project, during excavation, the site encountered substantial hard rock strata, which significantly impacted the progress o

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Apr 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jul 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: FULL CC_signed.pdf16 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf16 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf16 Jul 2026
Withdrawal Update Form 3File: form 3 CA Form.pdf16 Jul 2026
Withdrawal Update Form 1File: Arch Form 1.pdf29 Apr 2026
Withdrawal Update Form 2File: Engineer Form 2 Q4 - 27-04-2026.pdf29 Apr 2026
Withdrawal Update Form 3File: Gold sukh lifesvcapes llp-CA certificate-form-3.pdf29 Apr 2026
Commencement certificateFile: FULL CC_signed.pdf12 Mar 2026
Withdrawal Update Form 1File: Architect form 1.pdf12 Mar 2026
Withdrawal Update Form 1File: Architect form 1.pdf12 Mar 2026
Withdrawal Update Form 1File: Architect form 1.pdf12 Mar 2026
Withdrawal Update Form 1File: form 1.pdf12 Mar 2026
Withdrawal Update Form 1File: arch certificate.pdf12 Mar 2026
Withdrawal Update Form 1File: Architect form 1.pdf12 Mar 2026
Withdrawal Update Form 2File: Engineer Form 2 Q2 - 17-01-2026.pdf12 Mar 2026
Withdrawal Update Form 2File: Engineer Form 2 Q2 - 17-01-2026.pdf12 Mar 2026
Withdrawal Update Form 2File: Engineer Form 2 Q2 - 17-01-2026.pdf12 Mar 2026
Withdrawal Update Form 2File: Engineer Form 2 Q1.pdf12 Mar 2026
Withdrawal Update Form 2File: Engineer Form 2 Q2 - 08-10-2025.pdf12 Mar 2026
Withdrawal Update Form 2File: Engineer Form 2 Q2 - 17-01-2026.pdf12 Mar 2026
Withdrawal Update Form 3File: CA Form 3 Certificate.pdf12 Mar 2026
Withdrawal Update Form 3File: CA Form 3 Certificate.pdf12 Mar 2026
Withdrawal Update Form 3File: CA Form 3 Certificate.pdf12 Mar 2026
Withdrawal Update Form 3File: Form-3 Gold sukh lifescapes llp.pdf12 Mar 2026
Withdrawal Update Form 3File: Form-3 Gold sukh lifescapes llp.pdf12 Mar 2026
Withdrawal Update Form 3File: CA Form 3 Certificate.pdf12 Mar 2026
Withdrawal Update Form 1File: arch certificate.pdf28 Nov 2025
Withdrawal Update Form 2File: Engineer Form 2 Q2 - 08-10-2025.pdf28 Nov 2025
Withdrawal Update Form 3File: Certificate.pdf28 Nov 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Excel - (Q3).pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Excel - (Q2).pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Excel - (Q1).pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Form 1.pdf10 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 Q3.pdf10 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 new - 13-06-2024.pdf24 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: 2418046_FurtherCC_signed.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificate.pdf12 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate17112023172603.pdf18 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate17112023172706.pdf18 Nov 2023
Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale (1) (1) (1) (1).pdf9 May 2023
Layout approvalFile: Plan aproved (4)_1-1.pdf25 Apr 2023
Layout approvalFile: Plan aproved (4)_2-2.pdf25 Apr 2023
Layout approvalFile: Plan aproved (4)_3-3.pdf25 Apr 2023
Layout approvalFile: Plan aproved (4)_4-4.pdf25 Apr 2023
Layout approvalFile: Plan aproved (4)_5-end.pdf25 Apr 2023
Copy of Layout Approval (in case of layout)File: Plan aproved (4)_1-1.pdf25 Apr 2023
Copy of Layout Approval (in case of layout)File: Plan aproved (4)_2-2.pdf25 Apr 2023
Copy of Layout Approval (in case of layout)File: Plan aproved (4)_3-3.pdf25 Apr 2023
Copy of Layout Approval (in case of layout)File: Plan aproved (4)_4-4.pdf25 Apr 2023
Copy of Layout Approval (in case of layout)File: Plan aproved (4)_5-end.pdf25 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: certificate (1).pdf25 Apr 2023
Building plan approvalFile: IOD.pdf24 Apr 2023
Copy of the legal title reportFile: Title certificate.pdf24 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: IOD.pdf24 Apr 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER FINAL.pdf24 Apr 2023
Deviation Report with respect to Allotment letterFile: No Deviation allotment.pdf24 Apr 2023
Deviation Report with respect to model copy of AgreementFile: parel deviation clause16052023162516.pdf24 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank acc (1).pdf22 Apr 2023
PAN CardFile: Gold Sukh Lifescapes - Pan.pdf20 Apr 2023
Details of encumbrances concerned to FinanceFile: No Encumbrance.pdf20 Apr 2023
Details of encumbrances concerned to LegalFile: No Encumbrance.pdf20 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf20 Apr 2023
Declaration about Commencement CertificateFile: CC DECLARATION NEW.pdf20 Apr 2023
Declaration in FORM BFile: Form B - Parel.pdf20 Apr 2023
CERSAI detailsFile: Cersai Declaration.pdf20 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf20 Apr 2023

Keep Pristine Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Parel

Builder: GOLD SUKH LIFESCAPES LLP

GOLD SUKH LIFESCAPES LLP has 1 registration on MahaRERA, including Pristine Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if Pristine Heights is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Pristine Heights?

The registered promoter entity is GOLD SUKH LIFESCAPES LLP, a partnership as per the filing. Its GSTIN 27AALFG6006F1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Pristine Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Pristine Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Pristine Heights?

The professionals named in the filing: Architect: Nilesh Kadakia; Engineer: Piyush Sura; Chartered Accountant: Chintan Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pristine Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pristine Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pristine Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.