Registered No litigation declared Residential / Group Housing project

Primo

By Ceear Land Developers LLP

RG-MH-10148 · RERA P51800001724 · Last updated on MahaRERA portal: 7 Jul 2025

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • 38 complaints at MahaRERA
  • Completion date moved by 63 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
6 of 11Construction stages donefurthest along: Internal walls, 73%
38Complaints at MahaRERAon this registration
Jump to the 131 documents Report an error

Primo is a Residential / Group Housing project by Ceear Land Developers LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001724 on 29 Jul 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 63 months from the original filing. 38 complaints are on record with the regulator.

At a glance

Project

  • NamePrimo
  • TypeResidential / Group Housing
  • Location
    • Off. LBS Road
    • Near Shangrilla Biscuit Factory
    • Kurla
    • Mumbai Suburban
    • 400078
  • Pincode400078
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800001724
  • ReraGenie IDRG-MH-10148

Builder

  • NameCeear Land Developers LLP
  • Entity typePartnership
  • DirectorAmit Avinash Parab
  • Declared earlier projects1 →

Key dates

1 months past promisethis monthRegisteredJul 2017First promiseJun 2021Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jul 2017
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed131 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PrimoNA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 73%.

Primo: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises73%
Sanitary Fittings within the flats / premises27%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.17%

Progress on shared amenities15

As on 7 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes8%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed126

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots126
Closed/Covered126

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,620 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI7381.31
Proposed, not sanctioned7,381 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHarbhajjan, Ground Floor, Opp CST Road, Near Vidyanagri Post,Kalina, Santacruz East, Mumbai

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTushar Bhor
PartnerRole in project
Ceear Land Developers LLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800006070Jun 2021 → Jun 2022

Reason as filed by the promoterThe Promoter was totally in control of the project timelines at the time when initial approvals were obtained until the time the DCPR 2034 was decided to be sanctioned. Lot of time was wasted in the wait for DCPR 2034 sanction, • The policy to follow stringent of two set of rules, • The Excluded Portion (EP) confirmations, and • The Transition policies (the T1 was published on 2nd Nov 2018 and the T5 was published on 04th Sept 2019). There was utter chaos of misinformation. The responsible sections of officers were totally unaware about in the implementation of the DCPR 2034. The detailed sequ

EXT51800013058Jun 2021 → Mar 2024

Reason as filed by the promoterThe RERA certificate of the project has expired on 31.12.2022 and all sales and financial inflows to the project have stopped. Which has reduced the ongoing construction activities at site. However, we have receivables of Approx. 15 crores from existing flat purchaser and approx. 50 crores from unsold inventory over next 8 to 12 months Thus, Applicant would like to request for additional time. As format attached

EXT51800019424Jun 2021 → Sep 2026

Reason as filed by the promoter1. The Applicant further states that the Applicant couldn’t obtain requisite consent of 51% in spite of all the efforts. The RCC structure is complete till 17th Residential floor/fully complete. Including the Rooftop water tanks, and roof top amenities like seating and barbeque stations etc and safety glass are in process of being installed. The Developer states that an amount of Rs. 10.13 Crores is raised by way of Barter Agreements mentioned above. This amount raised is the reason the Developer could proceed with the Construction further to completion. The Developer states that as most of th

Complaints filed with MahaRERA38

Case no.ComplainantRespondentFiled
CC006000000209909KRUPESH PRAMOD THAKKAR/ KOMAL KRUPESH THAKKARCEEAR LAND DEVELOPERS LLLP22/02/2022
CC006000000210091Abhishek WalavalkarCEEAR LAND DEVELOPERS LLP18/02/2022
CC006000000210082Amey Ram WalavalkarCEEAR LAND DEVELOPERS LLP18/02/2022
CC006000000210088DEEPAK POTADARCEEAR LAND DEVELOPERS LLP18/02/2022
CC006000000210094Vivek KalambeCEEAR LAND DEVELOPERS LLP18/02/2022
CC006000000210092Ravindra PawarCEEAR LAND DEVELOPERS LLP18/02/2022
CC006000000210518Minakshi Pappu YadavCeear Land developers LLP24/03/2022
CC006000000220870SHIVSHANKAR SAHUCEEAR LAND DEVELOPERS LLP18/04/2022
CC006000000220883MAHESHKKUMAR G SAHUCEAAR LAND DEVELOPERS LLP19/04/2022
CC006000000220884MAHESHKKUMAR G SAHUCEAAR LAND DEVELOPERS LLP19/04/2022
CC006000000220889GIRISH G GUPTACEAAR LAND DEVELOPERS LLP20/04/2022
CC006000000220893KALPESH G KAMBLECEAAR LAND DEVELOPERS LLP20/04/2022
CC006000000220901NIKHIL V KANADECEAAR LAND DEVELOPERS LLP21/04/2022
CC006000000220902JAYESH KAILASH POTWADECEAAR LAND DEVELOPERS LLP21/04/2022
CC006000000220910MRS LAVANYA LAXMAN DHURICEAAR LAND DEVELOPERS LLP21/04/2022
CC006000000231153MANUBHAI PANCHALCEAAR LAND DEVELOPERS LLP12/05/2022
CC006000000231266VINAY SITARAM GUPTACEAAR LAND DEVELOPERS LLP23/05/2022
CC006000000231268VIKAS SITARAM GUPTACEAAR LAND DEVELOPERS LLP23/05/2022
CC006000000231294JITENDRA GUPTACEAAR LAND DEVELOPERS LLP25/05/2022
CC006000000261957Merwyn PawarCeeat Land Developers LLP18/07/2022
CC006000000292319Umeshchand Shyambihari PandeyM/s. Ceear Land Developers LLP25/08/2022
CC006000000303489SAMEER A SHAIKHCEEAR LAND DEVELOPERS29/11/2022
CC006000000344237Prasad Chandrakant KhadpeCEEAR LAND DEVELOPERS LLP14/02/2023
CC006000000344271RAJAN ASWANICEEAR LAND DEVELOPERS LLP10/02/2023
CC006000000354364Nitin ShettyCeear Land Developers LLP15/02/2023
CC006000000354366SURESH BABURAV AMBOKARCEEAR LAND DEVELOPERS LLP15/02/2023
CC006000000396384RAJU GUPTACEAAR LAND DEVELOPERS22/06/2023
CC006000000396594MR DAYANAND TUKARAM KADAMCEEAR LAND DEVELOPERS LLP11/07/2023
CC006000000396825Subhan Allah Ikramullah KhanCeear Land Developers LLP02/08/2023
CC006000000428939Vaibhav Pradeep PalavCeear Land Developers24/01/2024
CC006000000429036Shankar Nagesh KaduCEEAR Land Developers01/02/2024
CC006000000429097Sadanand Ganpat SatamCeear Land Developers LLP04/02/2024
CC006000000429099Alekh GuptaCeear Land Developer LLP04/02/2024
CC006000000429101Sachin Shridhar DhumalCeear Land Developers LLP04/02/2024
CC006000000429425PRIMO ALLOTTEES ASSOCIATIONCeear Land Developers LLP06/03/2024
CC12400091Vivek Basant Kumar PorwalCeear Land Developers LLP13/09/2024
CC12503782Sheeba David NadarCeear Land Developers LLP29/10/2025
CC12604072Biju Francis KoolaCeear Land Developers LLP30/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed131

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 131 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form_3 March 2024 CA_compressed.pdf7 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Primo Arch December 2024.pdf9 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Primo Arch Certificate March 2025.pdf9 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Primo Form 2 Eng Cert Dec 2024.pdf9 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eng Cert March 2025.pdf9 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Primo December 2024.pdf9 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Primo archiect certificate 30092024.pdf6 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA Primo Eng Form 2 30Sept24.pdf15 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Primo March 2023.pdf12 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Primo Arch March 2024.pdf30 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Primo Arch June 2024.pdf30 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Eng Quality March 2023.pdf30 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Primo Form 2 Eng Cert March 2024.pdf19 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Primo Form 2 Eng Cert June 2024.pdf19 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 23 Arch.pdf26 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 23 Arch.pdf26 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2, 30th September 2023 Eng.pdf26 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31st December Eng.pdf26 Mar 2024
Certificates of CA (Form 3)File: Form 3 30th Sept 2023 CA.pdf26 Mar 2024
Certificates of CA (Form 3)File: Form 3 30th Dec 2023 CA.pdf26 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1-30062023_Architect Certificate.pdf29 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2-30062023_Engineers Certificate.pdf29 Dec 2023
Certificates of CA (Form 3)File: Form_3-30062023_CA Certificate.pdf29 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Revised Form 5.pdf3 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Revised Form 5.pdf3 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form_2A-31032023_Engineers Certificate For Quality Assurance (UPLOADED).pdf27 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1-31032023_Architect Certificate (UPLOADED).pdf24 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2-31032023_Engineers Certificate (UPLOADED).pdf24 Apr 2023
Certificates of CA (Form 3)File: Form_3-31032023_CA Certificate (UPLOADED).pdf24 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1-31122022_Architect Certificate.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2-31122022_Engineers Certificate.pdf24 Jan 2023
Certificates of CA (Form 3)File: Form_3-31122022_CA Certificate.pdf24 Jan 2023
Declaration about Commencement CertificateFile: Form A.pdf10 Dec 2022
Disclosure of sold/ booked inventoryFile: Sold unsold data.pdf10 Dec 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf9 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf6 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf6 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: Full C C_PRIMO_signed.pdf3 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1-30092022_Architect Certificate.pdf2 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2-30092022_Engineers Certificate.pdf2 Dec 2022
Certificates of CA (Form 3)File: Form_3-30092022_CA Certificate.pdf2 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1-31032022_Architect Certificate_Signed.pdf30 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1-30062022_Architect Certificate_Signed.pdf30 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2-31032022_Engineers Certificate_Signed.pdf30 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2-30062022_Engineers Certificate_Signed.pdf30 Aug 2022
Certificates of CA (Form 3)File: Form_3-31032022_CA Certificate_Signed.pdf30 Aug 2022
Certificates of CA (Form 3)File: Form_3-30062022_CA Certificate_Signed.pdf30 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: 2337964_FurtherCC_signed.pdf29 Jul 2022
Declaration about Commencement CertificateFile: Declaration for FULL CC.pdf29 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form_1-31032022_Architect Certificate.pdf27 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2-31032022_Engineers Certificate.pdf27 Jun 2022
Certificates of CA (Form 3)File: Form_3-31032022_CA Certificate_.pdf27 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers certificate.pdf28 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect certificate.pdf27 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers certifi.pdf27 Apr 2022
Certificates of CA (Form 3)File: Form 3 31122021_.pdf27 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect certificate.pdf22 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers certificate.pdf22 Dec 2021
Certificates of CA (Form 3)File: form 3 certificate q2_.pdf22 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 certificate_.pdf18 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - ARCHITECT'S CERTIFICATE_.pdf20 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - ENGINEER'S CERTIFICATE_.pdf20 Oct 2021
Certificates of CA (Form 3)File: Form 3 - CHARTERED ACCOUNTANT JUN 2021__1.pdf20 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - ARCHITECT'S CERTIFICATE.pdf12 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineers Certficate.pdf12 Aug 2021
Certificates of CA (Form 3)File: Form 3 CA certificate Mar 21_.pdf12 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: Further CC upto15th floor.pdf13 May 2021
Details of encumbrancesFile: Encumbrance Primo (RERA).pdf6 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - ARCHITECT'S CERTIFICATE.pdf5 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - ENGINEER'S CERTIFICATE_.pdf5 Apr 2021
Certificates of CA (Form 3)File: Form 3 CA Certificate_.pdf5 Apr 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - ARCHITECT'S CERTIFICATE.pdf11 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - ENGINEER'S CERTIFICATE.pdf11 Nov 2020
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf11 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - ARCHITECT'S CERTIFICATE.pdf10 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - ENGINEER'S CERTIFICATE.pdf10 Nov 2020
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf10 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf27 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - ENGINEER’S CERTIFICATE.pdf27 Jul 2020
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf27 Jul 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationStatusPromisedDelivered
MELUHADindoshi Malad WestOngoingDec 2030Not due yet

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 63 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Primo on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Shangrilla Biscuit Factory6,700+ in Mumbai Suburban

2 kmPrimoCompleted 82Lapsed / revoked 59Other 98Dot size: filed unitsN

Filed coordinates, straight-line distance. 239 registered projects within 2 km.

Builder: Ceear Land Developers LLP

Ceear Land Developers LLP has 1 registration on MahaRERA, including Primo. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Primo is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Primo?

The registered promoter entity is Ceear Land Developers LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Primo?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Primo?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Primo?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Primo?

The professionals named in the filing: Architect: Tushar Bhor. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Primo?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Primo. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Primo to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.