ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Prestige Chambers Phase II

Registered No litigation declared Commercial project

Prestige Chambers Phase II

By SHAH PRATHAMESH CONSTRUCTIONS

RG-MH-31031 · RERA P52100079365 · Last updated on MahaRERA portal: 15 May 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Internal walls, 90%
43 of 46Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 98 documents Report an error

Prestige Chambers Phase II is a Commercial project by SHAH PRATHAMESH CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100079365 on 28 Feb 2025. Possession is promised by 31 Dec 2027. 3 of the 46 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePrestige Chambers Phase II
  • TypeCommercial
  • Location
    • Mundhawa Manjari Road
    • Keshav Nagar
    • Mundhawa
    • Haveli
    • Pune
    • 411036
  • Pincode411036
  • RERA no.P52100079365
  • ReraGenie IDRG-MH-31031

Builder

  • NameSHAH PRATHAMESH CONSTRUCTIONS
  • Entity typeOthers
  • Named personsMR. JAGADISH PRABHAKAR DESHPANDE, MR. SHIRISH GANGADHAR RISWADKAR, MR. SURESH INDULAL SHAH
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Feb 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed98 files

Current status

7%3 of 46 units booked
57.9%Work done, per cost certificate

Figures as on 15 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Prestige Chambers Phase IINA6004646

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

Prestige Chambers Phase II: 54% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed389

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots389
Closed/Covered216
Open Space173

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,640 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Aug 2025
LandownerVillageDistrict
Prtestige Panorama E (Amenity Sapce) Premises Soc.Keshavnagar-MundwaPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI7972.78
Proposed, not sanctioned6,392 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, GF-11&12, BASEMENT-UNIT-13, INDULAL COMMERCIAL COMPLEX, B WING, SURVEY NO.721/2A, PLOT NO-987-A, LBS ROAD, LOKMANYA NAGAR, NAVIPETH, SADASHIVPETH, PUNE,MAHARASHTRA-411030, PH-18002582000
Estimated costRs 21.16 cr
Cost incurredRs 12.26 cr
Work done57.93%
BuildingWingEstimatedIncurred
Prestige Chambers Phase IINARs 21.16 crRs 12.26 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVishal Jagdish Deshpande
EngineerBasavraj Amane
Chartered AccountantS D Medadkar and Co
Chartered AccountantVishram R Deshpande & Associates
PartnerRole in project
SHAH PRATHAMESH CONSTRUCTIONS-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12500130Ram GawaliSHAH PRATHAMESH CONSTRUCTIONS09/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Dec 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Feb 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Feb 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed98

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1- Architects Certificate- Prestige Chambers II.pdf15 May 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Prestige Chembers Phase II.pdf15 May 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate-29-04-2026.pdf15 May 2026
Form 2A (FY 2024-2025)File: Form 2A B A Amane.pdf27 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 V R Deshpande.pdf27 Mar 2026
Building plan approvalFile: prestige chamber mundhwa sanction plan 2.pdf17 Feb 2026
Building plan approvalFile: prestige chamber mundhwa sanction plan 3.pdf17 Feb 2026
Building plan approvalFile: prestige chamber mundhwa sanction plan 4.pdf17 Feb 2026
Building plan approvalFile: prestige chamber mundhwa sanction plan 6.pdf17 Feb 2026
Commencement certificateFile: CC 12112025.pdf17 Feb 2026
Building plan approvalFile: prestige chamber mundhwa sanction plan 5.pdf17 Feb 2026
Layout approvalFile: prestige chamber mundhwa sanction plan 1 Layout.pdf17 Feb 2026
Withdrawal Update Form 1File: Architect Certificate- Form-1.pdf17 Feb 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate.pdf17 Feb 2026
Withdrawal Update Form 3File: Form 3 Chartered Accountant Certificate.pdf17 Feb 2026
Withdrawal Update Form 1File: Form 1 Architectu0027s Certificate.pdf28 Oct 2025
Withdrawal Update Form 2File: Form 2 Engineers Certificate.pdf28 Oct 2025
Withdrawal Update Form 3File: Form 3 CA Certificate.pdf28 Oct 2025
Declaration about Commencement CertificateFile: Declaration about Commncemnt certificate Form D.pdf30 Apr 2025
Layout approvalFile: Scan_4783-01.pdf29 Apr 2025
Building plan approvalFile: Scan_4783-02.pdf29 Apr 2025
Building plan approvalFile: Scan_4783-03.pdf29 Apr 2025
Building plan approvalFile: Scan_4783-04.pdf29 Apr 2025
Building plan approvalFile: Scan_4783-05.pdf29 Apr 2025
Building plan approvalFile: Scan_4783-06.pdf29 Apr 2025
Copy of Layout Approval (in case of layout)File: Scan_4783-01.pdf29 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: 9TH SANCTION CC 4608 24 DT 29032025.pdf29 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Scan_4783-02.pdf29 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Scan_4783-03.pdf29 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Scan_4783-04.pdf29 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Scan_4783-05.pdf29 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Scan_4783-06.pdf29 Apr 2025
Other - LegalFile: Deed of Dissolution.pdf19 Feb 2025
Other - LegalFile: Supplementry Joint Venture Agreement.pdf19 Feb 2025
Other - LegalFile: JV Base agreement.pdf19 Feb 2025
Other - LegalFile: 10 Development Agreement.pdf19 Feb 2025
Other - LegalFile: 9 Development Agreement.pdf19 Feb 2025
Other - LegalFile: 8 Development Agreement.pdf19 Feb 2025
Other - LegalFile: 7 Development Agreement.pdf19 Feb 2025
Other - LegalFile: 6 Development Agreement.pdf19 Feb 2025
Other - LegalFile: 5 Development Agreement.pdf19 Feb 2025
Other - LegalFile: 4 Development Agreement.pdf19 Feb 2025
Other - LegalFile: 2 Development Agreement.pdf19 Feb 2025
Other - LegalFile: 1 Development Agreement.pdf19 Feb 2025
Other - LegalFile: SPC-Declaration dated-18-02-2025.pdf19 Feb 2025
Other - LegalFile: 3 Development Agreement.pdf19 Feb 2025
Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development (9).pdf5 Feb 2025
Building plan approvalFile: 4 Building Plan Approval _ NA Order for plotted development (2).pdf5 Feb 2025
Declaration in FORM BFile: 1 Declaration in FORM B.pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development (9).pdf5 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 4 Building Plan Approval _ NA Order for plotted development (2).pdf5 Feb 2025
Other - LegalFile: part 2 out of 2.pdf5 Feb 2025
Other - LegalFile: part 1 out of 2.pdf5 Feb 2025
Other - LegalFile: Flow Chart of Development Rights _compressed.pdf5 Feb 2025
Declaration about Commencement CertificateFile: Format D-CommencementPlan.pdf5 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest Letter-27-01-2025.pdf5 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Deed of Reconstitution of Partnership-15-7-2024_compressed.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 CA Certificate on Project Cost Fund withdrawal.pdf29 Jan 2025
Other - FinanceFile: CA-Certificate-16-1-2025.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration about Unit Allotment-16-1-25.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Note on Clarification of Nill Landcost-16-1-25.pdf18 Jan 2025
Other - LegalFile: Reconstitution of Partnership 15072024.pdf18 Jan 2025
Other - LegalFile: Flow Chart of Development Rights _compressed.pdf18 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: RERA Designated Bank Accout-16-1-25.pdf18 Jan 2025
Other - FinanceFile: Declaration about Unit Allotment-16-1-25.pdf18 Jan 2025
Other - FinanceFile: Note on Clarification of Nill Landcost-16-1-25.pdf18 Jan 2025
Other - FinanceFile: Reconstitution of Partnership 15072024.pdf18 Jan 2025
Other - LegalFile: Maha RERA Queries-11-1-25.pdf11 Jan 2025
Proforma of Agreement for saleFile: Annexure_A_-_Model_Agreement - 15-01-25.pdf11 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A-14-1-25.pdf10 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Disclosure-9-1-2025.pdf10 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B-9-1-2025.pdf10 Jan 2025
Other - TechnicalFile: 1 Other - Technical.pdf31 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-24-12-24.pdf28 Dec 2024
Details of encumbrances concerned to FinanceFile: Declaration- Finance Legal Encum- 21-12-24.pdf26 Dec 2024
CERSAI detailsFile: CERSAI-21-12-24.pdf26 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format-A RERA Designated Bank Ac-19-12-24.pdf26 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format-A Seprate Bank Ac-19-12-24.pdf26 Dec 2024
Details of encumbrances concerned to LegalFile: Declaration- Finance Legal Encum- 21-12-24.pdf26 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Fin availled for project-19-12-24.pdf26 Dec 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
PRESTIGE PANORAMASURVEY NO 36-1-1 AND 37-3B-2 MUNDHWA PUNE155CompletedJul 2007Jul 2007

How this compares with Pune

7%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Prestige Chambers Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Keshav Nagar13,700+ in Pune

Builder: SHAH PRATHAMESH CONSTRUCTIONS

SHAH PRATHAMESH CONSTRUCTIONS has 3 registrations on MahaRERA, including PRESTIGE GOLD and Prestige Chambers. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Prestige Chambers Phase II is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Prestige Chambers Phase II?

The registered promoter entity is SHAH PRATHAMESH CONSTRUCTIONS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Prestige Chambers Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Prestige Chambers Phase II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Prestige Chambers Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Prestige Chambers Phase II?

The professionals named in the filing: Architect: Vishal Jagdish Deshpande; Engineer: Basavraj Amane; Chartered Accountant: S D Medadkar and Co; Chartered Accountant: Vishram R Deshpande & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Prestige Chambers Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Prestige Chambers Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Prestige Chambers Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.