Home / Browse projects / Pune, Maharashtra / Presidia
Presidia
RG-MH-10910 · RERA P52100003128 · Last updated on MahaRERA portal: 15 Jun 2026
Source: official MahaRERA filing
Red flags
- 5 complaints at MahaRERA
- Completion date moved by 36 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Presidia is a Residential / Group Housing project by Kundan Buildcon in Pune, Maharashtra, registered with MahaRERA as P52100003128 on 4 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 36 months from the original filing. 81 of the 87 units on this registration are recorded sold or booked, and 22 of 22 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NamePresidia
- TypeResidential / Group Housing
- Location
- NIBM Undri Road
- Mohammed Wadi
- kondhwa khurd
- Haveli
- Pune
- 411048
- Pincode411048
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100003128
- ReraGenie IDRG-MH-10910
Builder
- NameKundan Buildcon
- Entity typePartnership
- PartnersAshish Bhawarlal Jain, Bhawarlal Kundanmal Jain, Saroj Pushparaj Khanna, Priyanka Shree Shambhu Singh, Dhanesh Dilip Mehta, Ashok Motiram Agarwal
- Other registrations1 more →
- Completed2 of 2
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on4 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2022)
- Buildings2 building records
- Documents filed163 files
Current status
Figures as on 15 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower A - Wing A | NA | 17 | 14 | 45 | 0 | 45 |
| Tower A - Wing B | NA | 17 | 14 | 42 | 0 | 42 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 15 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 22 construction stages are filed complete across 2 buildings.
Tower A - Wing A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Tower A - Wing B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 15 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed308
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Tower A - Wing A | 154 | 154 |
| Tower A - Wing B | 154 | 154 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Tirupati Developers | Swargate | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Tower A - Wing A | NA | Rs 42.00 cr | Rs 37.77 cr |
| Tower A - Wing B | NA | Rs 42.00 cr | Rs 37.77 cr |
| - | NA | Rs 8.00 cr | Rs 7.19 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NISHANT MENTA |
| Engineer | G. A. Bhilare Consultants Pvt. Ltd. |
| Engineer | SANTOSH BENDRE |
| Chartered Accountant | Patel and Sharma |
| Chartered Accountant | Agarwal Sarawgi and Associates |
| Partner | Role in project |
|---|---|
| Kundan Buildcon | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterCovid-19 Pandemic Declared by World Health Organization and consequent lockdown by the government further reverse migration of the labours to their native places and break in the supply chain of construction material. Construction of the project is under project we still require twenty four months to complete the project and get the occupancy certificate.
Reason as filed by the promoterDue to some unavoidable reasons we will not able to get completion certificate by that date.
Reason as filed by the promoterSupply chain disruptions and increased lead times for the delivery of essential construction materials, such as cement, steel, and other building components, have caused delays in the construction schedule. The scarcity of these materials in the local market and price volatility have further compounded the problem, leading to intermittent halts in construction activities. Additionally, there has been a marked shortage of both skilled and unskilled labour in the construction sector, adversely affecting the developer's capacity to sustain the required workforce levels necessary for the continuou
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000471480 | Nilofer Zubair | M/s Kundan Buildcon A Partnership Firm Through its Partner Mr. Ashish B. Jain | 07/08/2024 |
| CC12401228 | Santosh Suresh Patil | Kundan Buildcon | 25/12/2024 |
| CC12500515 | Rupen Bhattacharya | Kundan Buildcon | 15/02/2025 |
| CC12500659 | Kundan Buildcon | Huzefa Najmuddin Calcuttawala | 24/02/2025 |
| CC12501939 | Alok Ghosh | Kundan Buildcon | 13/06/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Jan 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Jan 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 8 Nov 2024
Documents filed163
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 163 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Full OC for Wing A and B.pdf | 15 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 _Presidia.pdf | 13 Feb 2026 |
| Withdrawal Update Form 2File: Presidia Form 2ok.pdf | 13 Feb 2026 |
| Withdrawal Update Form 3File: Form 3_0001 Signed.pdf | 13 Feb 2026 |
| Building plan approvalFile: PLAN-02-06.pdf | 22 Jan 2026 |
| Building plan approvalFile: PLAN-03-06.pdf | 22 Jan 2026 |
| Building plan approvalFile: PLAN-04-06.pdf | 22 Jan 2026 |
| Building plan approvalFile: PLAN-05-06.pdf | 22 Jan 2026 |
| Building plan approvalFile: PLAN-06-06.pdf | 22 Jan 2026 |
| Layout approvalFile: BP LAYOUT highlighted compressed.pdf | 22 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 - Presidia.pdf | 11 Dec 2025 |
| Withdrawal Update Form 2File: Presidia form 2.pdf | 11 Dec 2025 |
| Withdrawal Update Form 3File: Presidia Form 3 - sep 25 Copy_11zon.pdf | 11 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 - Presidia.pdf | 8 Dec 2025 |
| Withdrawal Update Form 2File: Presidia form 2.pdf | 8 Dec 2025 |
| Withdrawal Update Form 3File: Presidia Form 3 - sep 25.pdf | 8 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 - Presidia.pdf | 7 Nov 2025 |
| Withdrawal Update Form 2File: Presidia form 2.pdf | 7 Nov 2025 |
| Withdrawal Update Form 3File: Presidia - Form 3 - 30-06-2024_compressed.pdf | 7 Nov 2025 |
| Form 2A (FY 2024-2025)File: Presidia - Form 2A.pdf | 31 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 - Presidia.pdf | 29 Sep 2025 |
| Form 1File: Form 1.pdf | 26 Jul 2025 |
| Form 2File: Form 2.pdf | 26 Jul 2025 |
| Form 3File: Form 3 Presidia Final.pdf | 26 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: sold Unsold.pdf | 26 Jul 2025 |
| Other - TechnicalFile: Completion Certificate - 28-10-2024.pdf | 16 Jun 2025 |
| Other - TechnicalFile: Ack Presidia 18032025.pdf | 16 Jun 2025 |
| Certificates of CA (Form 3)File: Presidia Form 3.pdf | 11 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Presidia Sold - Unsold.pdf | 11 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Sold - Unsold - Presidia -.pdf | 8 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Presidia.pdf | 21 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 - Presidia.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold - Unsold - Presidia -.pdf | 19 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Presidia.pdf | 16 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold - Unsold Dec 24.pdf | 28 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Presidia Form 2A - 19-20.pdf | 24 Feb 2025 |
| Declaration in FORM BFile: 01 Form B As per original RERA format_rotated.pdf | 18 Feb 2025 |
| Certificates of CA (Form 3)File: Presidia Form 3 - 31 12 2024.pdf | 18 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Presidia Form 2 - 31 12 2024.pdf | 13 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Presidia Sold - Unsold - 31 12 2024.pdf | 13 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Presidia.pdf | 9 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Presidia 30-09-2024 - Sold - Unsold.pdf | 19 Dec 2024 |
| Certificates of CA (Form 3)File: To Upload Presidia Form 3 - 30-09-2024_compressed.pdf | 3 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: To Upload Presifdia - Form 2 - 30-09-2024.pdf | 3 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Presidia Form 1 - 30-09-2024.pdf | 27 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-3198-23 DT 12-03-2024.pdf | 8 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate - 28-10-2024.pdf | 8 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Presidia Sold - Unsold - 30-06-2024.pdf | 13 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Presidia Form 1 - 30-06-2024.pdf | 12 Aug 2024 |
| Certificates of CA (Form 3)File: Presidia - Form 3 - 30-06-2024_compressed.pdf | 12 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Presidia Form 2 - 30-06-2024.pdf | 3 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Presidia - Form 2A - 14-06-2024.pdf | 10 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Presidia - Sold - Unsold - 30-06-2024.pdf | 10 Jul 2024 |
| Certificates of CA (Form 3)File: Presidia form 3 -31-03-2024_11zon.pdf | 10 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Prsidia Form 5 - 04-06-2024.pdf | 10 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Presidia Form 2 31122023.pdf | 25 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Presidia Form 2 31032024.pdf | 25 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Presidia Sold Unsold 31122023.pdf | 25 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Presidia Sold Unsold 31032024.pdf | 25 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Presidia - Form 1 - 31032024.pdf | 14 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3 Signed.pdf | 14 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Presidia - Form 1 - 31122023.pdf | 8 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Kundan Buildcon (Presidia).pdf | 18 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 02 Form 2 Engineer Certificate Format_Sep 23.pdf | 15 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 Presidia Sep 23_Updated_Signed_15-12-2023_11zon.pdf | 15 Dec 2023 |
| Declaration in FORM BFile: Form B.pdf | 13 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Presidia - Form 1- 30-06-2023.pdf | 26 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Presidia - Form 1- 10-10-2023.pdf | 26 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Q3 31-03-2023_11zon.pdf | 26 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Q1 30-06-2023.pdf | 26 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Q2 30-09-2023.pdf | 26 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate-Dec22 - Final_compressed.pdf | 3 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate-Mar23 - Final_compressed.pdf | 3 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 Presidia June 2023_only promoter signed_11zon_Signed_compressed.pdf | 3 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Presidia Form 1 - 01-12-2022.pdf | 7 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Presidia Form 1 - 01-03-2023.pdf | 7 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 2022.pdf | 7 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 2023.pdf | 7 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q2 Presidia Form 2 - 30-09-2022.pdf | 26 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q3 Presidia Form 2 - 31-12-2022.pdf | 26 Sep 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 163 filed documents as one ZIP, foldered, with a manifest
Keep Presidia on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mohammed Wadi13,700+ in Pune
Filed coordinates, straight-line distance. 190 registered projects within 2 km.
Dwarikadham
Yashodhan Affordable Landmark LLP
UNITAS FASHION CENTER
UNITATIS DEVELOPMENTS PVT. LTD
Millennium Park
Xrbia Epoch Creations LLP
BABAR CLASSIC VISTA WING E, F, G
Classic Properties
JITO NAGAR
JAIN ASHAPURI DEVELOPER UNIT II
Wellwisher West Views
Bhansali Infrastructure LLP
Builder: Kundan Buildcon
Kundan Buildcon has 2 registrations on MahaRERA, including Presidia and The Peak. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Presidia is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Presidia?
The registered promoter entity is Kundan Buildcon, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Presidia?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Presidia?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Presidia?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Presidia?
The professionals named in the filing: Architect: NISHANT MENTA; Engineer: G. A. Bhilare Consultants Pvt. Ltd.; Engineer: SANTOSH BENDRE; Chartered Accountant: Patel and Sharma; Chartered Accountant: Agarwal Sarawgi and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Presidia?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.