Prarthana Grand
RG-MH-25403 · RERA P51900008215 · Last updated on MahaRERA portal: 22 Jul 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 72 months
- 4 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Prarthana Grand is a Residential / Group Housing project by OJUS DEVELOPERS in M.M.G.S MARG DADAR MUMBAI, 400012, registered with MahaRERA as P51900008215 on 18 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 72 months from the original filing. 0 of the 1 unit on this registration is recorded sold or booked, and 15 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NamePrarthana Grand
- TypeResidential / Group Housing
- Location
- B 101-103 NEW LOOK APARTMENT
- M.M.G.S MARG DADAR MUMBAI
- 400012
- Pincode400012
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900008215
- ReraGenie IDRG-MH-25403
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 Aug 2017
- Promised completion31 Dec 2024
- Revised completionRevised to 31 Dec 2024 (originally 31 Dec 2018)
- Buildings2 building records
- Documents filed85 files
Current status
Figures as on 22 Jul 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Prarthana Grand | NA | 32 | 27 | 1 | 0 | 1 |
| Sewree Azad Nagar SRA CHS Ltd | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 22 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 98%.
Prarthana Grand98%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 96% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 82% |
Sewree Azad Nagar SRA CHS Ltd82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 22 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 98% |
| Storm Water Drains | Yes | 98% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 70% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed61
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Chandrashekhar Architect |
| Engineer | JW Consultant |
| Engineer | Subhash Construction |
| Chartered Accountant | Sarawgi Shridhar & Associates |
| Chartered Accountant | RVS & Associates |
| Partner | Role in project |
|---|---|
| OJUS DEVELOPERS | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe construction work of the building is nearing completion. However, following works remain to be executed as of today: 1. Installation of lifts (order placed will take 7 months for installation) 2. Waterproofing of terrace 3. Finishing of parking floors 4. Finishing of flats from 25th to 30th floor 5. Site development 6. Handing over of D.P. road & other reservations 7. Obtaining O. C. This unexecuted work constitutes approximately 10% of the cost of construction. However we regret to state that the work is likely to be delayed for the following reasons: 1 Gloom in Real Estate market and hig
Reason as filed by the promoter1. The Managing Partner passed away during the year after prolonged hospitalization which resulted delays in decision making. 2. Non-payment of flat purchasers. (3) Pending litigation with B.E.S.T Undertaking.
Reason as filed by the promoterThe aforesaid project is registered with MahaRERA on 18/08/2017 under aforesaid registration number. An extension was granted to us upto 31st December 2020. The construction work of the building was nearing completion. However, following works remain to be executed as of today: 1. Installation of lifts (order placed) 2. Waterproofing of terrace 3. Finishing of lobbies and other common areas 5. Site development 6. Handing over of D.P. road & other reservations 7. Obtaining O. C. However we regret to state that the work is likely to be delayed for the following reasons: 1. Due to outbreak of COV
Reason as filed by the promoter•The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth •We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. •Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. •The geopolitical tension around the globe has led to rise
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000197541 | Gopal Ramprit Singh Thakur | Ojus Developers | 07/07/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Mar 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Mar 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed85
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Form 3 31-3-2024.pdf | 22 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3 30-6-2024.pdf | 22 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3 30-9-2024.pdf | 22 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3 31-12-2024.pdf | 22 Jul 2025 |
| Declaration in FORM BFile: form B_rotated.pdf | 2 Apr 2025 |
| Details of encumbrances concerned to FinanceFile: Non-Encumbrance concerned to Legal and Finance.pdf | 15 Mar 2025 |
| CERSAI detailsFile: Asset Based Report.pdf | 15 Mar 2025 |
| CERSAI detailsFile: Debtor Based Report.pdf | 15 Mar 2025 |
| Details of encumbrances concerned to LegalFile: Non-Encumbrance concerned to Legal and Finance.pdf | 15 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: Non Encumbrance Concered to legal.pdf | 22 Jul 2024 |
| Details of encumbrances concerned to LegalFile: Non Encumbrance Concered to legal.pdf | 22 Jul 2024 |
| CERSAI detailsFile: Asset Based Declaration.pdf | 22 Jul 2024 |
| CERSAI detailsFile: Debtor Based Declaration.pdf | 22 Jul 2024 |
| Declaration in FORM BFile: FORM_B-Affidavit_on_Stamp_Paper_of_Rs_100.pdf | 28 Mar 2024 |
| Layout approvalFile: Layout1_Part_1_compressed.pdf | 23 Mar 2024 |
| Layout approvalFile: Layout1_Part_2_compressed.pdf | 23 Mar 2024 |
| Layout approvalFile: Layout1_Part_3_compressed.pdf | 23 Mar 2024 |
| Layout approvalFile: Layout1_Part_4_compressed.pdf | 23 Mar 2024 |
| Building plan approvalFile: Layout1_Part_1_compressed.pdf | 23 Mar 2024 |
| Building plan approvalFile: Layout1_Part_2_compressed.pdf | 23 Mar 2024 |
| Building plan approvalFile: Layout1_Part_3_compressed.pdf | 23 Mar 2024 |
| Building plan approvalFile: Layout1_Part_4_compressed.pdf | 23 Mar 2024 |
| Building plan approvalFile: CC.pdf | 23 Mar 2024 |
| Copy of Layout Approval (in case of layout)File: Layout1_Part_1_compressed.pdf | 23 Mar 2024 |
| Copy of Layout Approval (in case of layout)File: Layout1_Part_2_compressed.pdf | 23 Mar 2024 |
| Copy of Layout Approval (in case of layout)File: Layout1_Part_3_compressed.pdf | 23 Mar 2024 |
| Copy of Layout Approval (in case of layout)File: Layout1_Part_4_compressed.pdf | 23 Mar 2024 |
| Building Plan Approval (IOD)File: Layout1_Part_1_compressed.pdf | 23 Mar 2024 |
| Building Plan Approval (IOD)File: Layout1_Part_2_compressed.pdf | 23 Mar 2024 |
| Building Plan Approval (IOD)File: Layout1_Part_3_compressed.pdf | 23 Mar 2024 |
| Building Plan Approval (IOD)File: Layout1_Part_4_compressed.pdf | 23 Mar 2024 |
| Building Plan Approval (IOD)File: CC.pdf | 23 Mar 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 23 Mar 2024 |
| Declaration about Commencement CertificateFile: Declaration of CC.pdf | 23 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_ 2018.pdf | 23 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_ 2019.pdf | 23 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_2020.pdf | 23 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_2021.pdf | 23 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_2022.pdf | 23 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_2023.pdf | 23 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_2017-18.pdf | 23 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_2018-19.pdf | 23 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_2019-20.pdf | 23 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_2020-21.pdf | 23 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_2021-22.pdf | 23 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_2022-23.pdf | 23 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_2023-24.pdf | 23 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SELF DECLARATION FOR FORM 2A.pdf | 23 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SELF DECLARATION FOR FORM 2A.pdf | 23 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SELF DECLARATION FOR FORM 2A.pdf | 23 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SELF DECLARATION FOR FORM 2A.pdf | 23 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Declaration of Sold Unsold.pdf | 23 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3_FY 2017-18_compressed.pdf | 23 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3_FY 2018-19_compressed.pdf | 23 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3_FY 2019-20_compressed.pdf | 23 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3_ FY 2020-21_compressed.pdf | 23 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3_FY 2021-22_compressed.pdf | 23 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3_FY 2022-23_compressed.pdf | 23 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3_April 23 To Dec 23_compressed.pdf | 23 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FY 2018-19.pdf | 23 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 2019-20.pdf | 23 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FY 2020-21.pdf | 23 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FY 2021-22.pdf | 23 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FY 2022-23.pdf | 23 Mar 2024 |
| Certificates of CA (Form 5)File: ojus form 5.pdf | 31 Dec 2018 |
| Copy of the legal title reportFile: Title_Certificaite_-_Gaykar.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: sewree_azadnagar_arch_cert.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: pr_grand_arch_cert.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: ojus_sale_agreement.pdf | 29 Jul 2017 |
| Building plan approvalFile: rehab1_iod.pdf | 28 Jul 2017 |
| Building plan approvalFile: sale_iod.pdf | 28 Jul 2017 |
| Layout approvalFile: layout_plan-1.pdf | 28 Jul 2017 |
| Layout approvalFile: layout_approval.pdf | 28 Jul 2017 |
| PAN CardFile: Ojus_Developers_PAN.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: legal_search_pg.pdf | 28 Jul 2017 |
| Details of encumbrancesFile: Declration_for_No_Encumbrance.pdf | 28 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: layout_approval.pdf | 28 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: layout_plan-1.pdf | 28 Jul 2017 |
| Building Plan Approval (IOD)File: rehab1_iod.pdf | 28 Jul 2017 |
| Building Plan Approval (IOD)File: sale_iod.pdf | 28 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 85 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Prarthana Grand on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near M.M.G.S MARG DADAR MUMBAI
Filed coordinates, straight-line distance. 53 registered projects within 2 km.
SATTVA SUMERA
ALPERTON DEVELOPERS AND CONTRACTORS PRIVAT
THE EDGE
TEJUKAYA CORP PRIVATE LIMITED
THE PINNACLE
RATNARAJ BLESSING MILESTONE LLP
Ruparel Millennia
Renuka Realtors
Ruparel Jewel
Renuka Realtors
Ruparel NOVA
SHREE SUKHAKARTA DEVELOPERS PVT.LTD.
Builder: OJUS DEVELOPERS
OJUS DEVELOPERS has 2 registrations on MahaRERA, including Prarthana Grand and SHANTI HARBOUR CREST. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record.
Frequently asked questions
What does it mean that Prarthana Grand shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Prarthana Grand is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Prarthana Grand?
The registered promoter entity is OJUS DEVELOPERS, a partnership as per the filing. Its GSTIN 27AANFM1794J1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Prarthana Grand?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Prarthana Grand?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Prarthana Grand?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Prarthana Grand?
The professionals named in the filing: Architect: Chandrashekhar Architect; Engineer: JW Consultant; Engineer: Subhash Construction; Chartered Accountant: Sarawgi Shridhar & Associates; Chartered Accountant: RVS & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Prarthana Grand?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback