ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Pranill Shree Ganesha

Registration lapsed No litigation declared Residential / Group Housing project

Pranill Shree Ganesha

By Pranill Constrobuild LLP

RG-MH-05162 · RERA P52000050237 · Last updated on MahaRERA portal: 3 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
7 of 11Construction stages donefurthest along: Internal walls, 95%
16 of 25Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

Pranill Shree Ganesha is a Residential / Group Housing project by Pranill Constrobuild LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000050237 on 27 Mar 2023. Possession was promised by 31 Mar 2026 and is now 7 months past that date. 9 of the 25 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NamePranill Shree Ganesha
  • TypeResidential / Group Housing
  • Location
    • Plot No 1 and 17
    • Bopele
    • Karjat
    • Raigarh
    • 410101
  • Pincode410101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000050237
  • ReraGenie IDRG-MH-05162

Builder

  • NamePranill Constrobuild LLP
  • Entity typePartnership
  • PartnerPriya Anil Patil

Key dates

7 months past promisethis monthRegisteredMar 2023PromisedMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on27 Mar 2023
  • Promised completion31 Mar 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed93 files

Current status

36%9 of 25 units booked
41.1%Work done, per cost certificate

Figures as on 3 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building Type ANA6525025

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

Building Type A: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes95%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed21

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots21
Closed/Covered6
Open Space15

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area443 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityDistrict Collector Raigad
Permissible FSI991.43
Proposed, not sanctioned991 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR SHOP NOS 2 3 4 5 VEERMA PARADISE PLOT NO 68 SECTOR 20 KAMOTHE
Estimated costRs 3.60 cr
Cost incurredRs 1.48 cr
Work done41.12%
BuildingWingEstimatedIncurred
Building Type ANARs 3.53 crRs 1.47 cr
-NARs 7.20 lakhRs 1.48 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDISHA ARCHITECTS
EngineerSK Consultants & Engineers
Chartered AccountantNB Sayed & Associates
PartnerRole in project
Pranill Constrobuild LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Pranill Shree Ganesha as on Sept 2025.pdf3 May 2026
Withdrawal Update Form 1File: Form 1 - Pranill Shree Ganesha as on March 2026.pdf3 May 2026
Withdrawal Update Form 1File: Form 1 - Pranill Shree Ganesha as on March 2026.pdf3 May 2026
Withdrawal Update Form 2File: Form 2 - Pranill Shree Ganesha as on March 2026.pdf3 May 2026
Withdrawal Update Form 2File: Form 2 - Pranill Shree Ganesha as on March 2026.pdf3 May 2026
Withdrawal Update Form 2File: Form 2 - Pranill Shree Ganesha as on March 2026.pdf3 May 2026
Withdrawal Update Form 3File: Form 3 Pranill Shree Ganesha as on 30th September 2025.pdf3 May 2026
Withdrawal Update Form 3File: Form 3- Pranill Shree Ganesha as on Dec 2025.pdf3 May 2026
Withdrawal Update Form 3File: Form 3 - Pranill Shree Ganesha as on March 2026.pdf3 May 2026
Withdrawal Update Form 1File: Form 1 - Pranill Shree Ganesha as on Sept 2025.pdf3 Jan 2026
Withdrawal Update Form 2File: Form 2 - Pranill Shree Ganesha as on June 2025 (SIGNED).pdf3 Jan 2026
Withdrawal Update Form 3File: Form 3 - Pranill Shree Ganesha as on June 2025 (SIGNED).pdf3 Jan 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Pranill Shree Ganesha as on Dec 2024.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Pranill Shree Ganesha as on March 2025.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Pranill Shree Ganesha as on Dec 2024.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Pranill Shree Ganesha as on March 2025.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Pranill Shree Ganesha as on March 2025.pdf8 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Pranill Shree Ganesha as on Sep 2024.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Pranill Shree Ganesha as on Sep 2024.pdf4 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24_compressed.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Pranill Shree Ganesha as on Sep 2024.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Pranill Shree Ganesha for FY 2023-24.pdf5 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - June 2024.pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - June 2024.pdf23 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - June 2024.pdf23 Oct 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf23 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: f.pdf20 Jul 2024
Declaration about Commencement CertificateFile: Format D.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 2024.pdf15 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2024.pdf15 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A FY 2022-23.pdf15 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY 2023-24.pdf15 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2024.pdf15 Jul 2024
Disclosure of sold/ booked inventoryFile: img09140.pdf13 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Pranill Shree Ganesha as on June 2024.pdf11 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Pranill Shree Ganesha as on March 2024.pdf21 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf21 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Pranill Shree Ganesha as on March 2024.pdf21 May 2024
Layout approvalFile: Layout - Pranill Shree Ganesha.pdf30 Apr 2024
Building plan approvalFile: Layout - Pranill Shree Ganesha.pdf30 Apr 2024
Copy of Layout Approval (in case of layout)File: Layout - Pranill Shree Ganesha.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Layout - Pranill Shree Ganesha.pdf30 Apr 2024
Disclosure of sold/ booked inventoryFile: Circular 29 - Pranill Shree Ganesha as on Dec 2023.pdf21 Mar 2024
Other - TechnicalFile: POA - Pranill Shree Ganesha.pdf13 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March.pdf2 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June.pdf2 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Spe.pdf2 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Dec.pdf2 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 march full.pdf2 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June form 2 full.pdf2 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sept form 2 full.pdf2 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf2 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pranill F3 - Mar 23.pdf2 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pranill F3 - June 23.pdf2 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pranill F3 - Sep 23.pdf2 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf2 Feb 2024
Other - TechnicalFile: Format A - Seperate Bank Account.pdf2 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Pranil Shree Ganesha FORM 2 As on December2023.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pranill Shree Ganesha FORM 3 As on December 2023.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf25 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Pranill Shree Ganesha as on Dec 2023.pdf4 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Pranill Shree Ganesha as on March 2023.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Pranill Shree Ganesha as on June 2023.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Pranill Shree Ganesha as on Sep 2023.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Pranill Shree Ganesha as on March 2023.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Pranill Shree Ganesha as on June 2023.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Pranill Shree Ganesha as on Sept 2023.pdf20 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Pranill Shree Ganesha as on march 23.pdf20 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Pranill Shree Ganesha as on 30th June 2023.pdf20 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Pranill Shree Ganesha as on Sept 23.pdf20 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_Pranill Shree Ganesha- FY 2022-23.pdf20 Dec 2023
Copy of the legal title reportFile: Pranil Title.pdf24 Mar 2023
CERSAI detailsFile: Cersai Pranill Shree Ganesha.pdf13 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: First Form 3 - Pranill Shree Ganesha final.pdf13 Mar 2023
Proforma of Agreement for saleFile: AFS_Pranill Shree Ganesha_Pranill Constrobuild LLP_11032023.pdf13 Mar 2023
Proforma of Allotment letterFile: Allotment Letter_Deviation_Pranill Shree Ganesha_Pranill Constrobuild LLP_11032023.pdf13 Mar 2023
Deviation Report with respect to Allotment letterFile: Allotment Letter.pdf13 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Agreement for sale.pdf13 Mar 2023
Layout approvalFile: Plan_11zon.pdf10 Mar 2023

How this compares with Raigarh

36%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Pranill Shree Ganesha on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bopele5,900+ in Raigarh

2 kmPranill Shree GaneshaCompleted 78Lapsed / revoked 46Other 53Dot size: filed unitsN

Filed coordinates, straight-line distance. 177 registered projects within 2 km.

Builder: Pranill Constrobuild LLP

Pranill Constrobuild LLP has 1 registration on MahaRERA, including Pranill Shree Ganesha. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Pranill Shree Ganesha shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Pranill Shree Ganesha is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Pranill Shree Ganesha?

The registered promoter entity is Pranill Constrobuild LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Pranill Shree Ganesha?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Pranill Shree Ganesha?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Pranill Shree Ganesha?

The professionals named in the filing: Architect: DISHA ARCHITECTS; Engineer: SK Consultants & Engineers; Chartered Accountant: NB Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pranill Shree Ganesha?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pranill Shree Ganesha. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pranill Shree Ganesha to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.