Home / Browse projects / Sangli, Maharashtra / Pranav Paradise
Pranav Paradise
RG-MH-24641 · RERA P53100009663 · Last updated on MahaRERA portal: 15 Apr 2019
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Pranav Paradise is a Residential / Group Housing project by Pranav Builders in Sangli, Maharashtra, registered with MahaRERA as P53100009663 on 22 Aug 2017. The registration is recorded completed; possession was promised by 15 Mar 2019.
At a glance
Project
- NamePranav Paradise
- TypeResidential / Group Housing
- Location
- Sangli
- Sangli Miraj Kupwad (M Corp.)
- Miraj
- 416325
- Pincode416325
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53100009663
- ReraGenie IDRG-MH-24641
Builder
- NamePranav Builders
- Entity typePartnership
- GSTIN27AANFP0882E1Z2
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersArvind Baburao Patil, Vinod Shamrao Patil
- Other registrations5 more →
- Completed4 of 6
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects9 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on22 Aug 2017
- Promised completion15 Mar 2019
- Revised completionNone
- Buildings1 building record
- Documents filed25 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Pranav Paradise | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Apr 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Pranav Paradise: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 15 Apr 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Appaso Bapu Patil | Sangli Miraj Kupwad (M Corp.) | Sangli |
| Annaso Bapu Patil | Sangli Miraj Kupwad (M Corp.) | Sangli |
| Rajgonda Bhauso Patil | Sangli Miraj Kupwad (M Corp.) | Sangli |
| Smt Akkatai Bhauso Patil | Sangli Miraj Kupwad (M Corp.) | Sangli |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar Ambernath M Shinde |
| Engineer | Dr Nandkumar K Patil |
| Partner | Role in project |
|---|---|
| Pranav Builders | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Mar 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed25
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 5)File: Form 5 Annual Report 1.pdf | 15 Apr 2019 |
| Certificates of CA (Form 5)File: Form 5 Annual Report-2.pdf | 15 Apr 2019 |
| Certificates of Architect (Form 4)File: Form 4 Architects Certificate.pdf | 15 Apr 2019 |
| OtherFile: Complition Certificate.pdf | 15 Apr 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates .pdf | 30 Mar 2018 |
| Building plan approvalFile: Building Plan Approval ( IOD ).pdf | 29 Mar 2018 |
| Building plan approvalFile: Building Plan Approval ( IOD ).pdf | 29 Mar 2018 |
| Building plan approvalFile: Building Plan Approval ( IOD ).pdf | 29 Mar 2018 |
| Building Plan Approval (IOD)File: Building Plan Approval ( IOD ).pdf | 29 Mar 2018 |
| Building Plan Approval (IOD)File: Building Plan Approval ( IOD ).pdf | 29 Mar 2018 |
| Building Plan Approval (IOD)File: Building Plan Approval ( IOD ).pdf | 29 Mar 2018 |
| Building plan approvalFile: Building Plan Approval (IOD).pdf | 4 Aug 2017 |
| Layout approvalFile: Copy of Layout Approval.pdf | 4 Aug 2017 |
| PAN CardFile: PAN card.pdf | 4 Aug 2017 |
| Copy of the legal title reportFile: Copy of the legal title report.pdf | 4 Aug 2017 |
| Details of encumbrancesFile: Details of encumbrances.pdf | 4 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: Copy of Layout Approval.pdf | 4 Aug 2017 |
| Building Plan Approval (IOD)File: Building Plan Approval (IOD).pdf | 4 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certifificats.pdf | 4 Aug 2017 |
| Declaration in FORM BFile: Declaration in form B.pdf | 4 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificates of Architect ( Form 1 ).pdf | 4 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificates of Engineer ( Form 2).pdf | 4 Aug 2017 |
| Certificates of CA (Form 3)File: Certificates of CA ( Form 3 ).pdf | 4 Aug 2017 |
| Proforma of Allotment letterFile: Proforma of the allotment letter and agreement for salel.pdf | 4 Aug 2017 |
| Proforma of Allotment letterFile: Proforma of the allotment letter and agreement for sale.pdf | 4 Aug 2017 |
Promoter's earlier projects9
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Pranav SkyP53100047235 | Shahu Nagar, Sangli | 15 | Oct 2022 | Ongoing | Mar 2025 | Not delivered |
| Pranav BreezeP53100046600 | 100' Road, Sangli | 24 | Aug 2022 | Ongoing | Mar 2025 | Not delivered |
| Pranav CornerP53100047076 | Tuljainagar, Sangli | 10 | Sep 2022 | Completed | Dec 2024 | Jan 1970 |
| Pranav Paradise | Tuljainagar Near Podar School Kupwad | 16 | - | Completed | Mar 2019 | Oct 2018 |
| Pranav Park | Revenue Colony Near Bapat Mala | 8 | - | Completed | Jan 2019 | Late, Feb 2019 |
| Pranav Square | Tuljai Nagar near Podar School | 6 | - | Completed | Aug 2018 | Jul 2018 |
| Pranav Pearl | Tulajainagar Kupwad | 12 | - | Completed | Feb 2017 | Jan 2017 |
| Pranav Pride | Tuljainagar kupwad | 6 | - | Completed | Apr 2015 | Late, May 2015 |
| Pranav Heights | Chinmay Park Road | 12 | - | Completed | Feb 2014 | Jan 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 25 filed documents as one ZIP, foldered, with a manifest
Keep Pranav Paradise on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Sangli790+ in Sangli
Filed coordinates, straight-line distance. 165 registered projects within 2 km.
SIDDHI VASTU Puram
SIDDHIVINAYAK PLATINUM
SEVEN HILLS
SHRI HARIPRIYA BUILDERS AND DEVELOPERS LLP
SHREE RAJLAXMI MALL
SHREE RAJLAXMI CONSTRUCTIONS AND BUILDERS
EVARA ESTATE
DSDB REALTY LLP
GOVIND ICON
G.K. ASSOCIATES
Fortune Business Hub
Fortune Enterprises
See every Sangli project, with the district possession charts
Builder: Pranav Builders
Pranav Builders has 6 registrations on MahaRERA, including Pranav Paradise and Pranav Flora. Its filings disclose 9 earlier MahaRERA projects: declares 5 of 7 past projects completed on time. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What are my rights if Pranav Paradise is delayed beyond 15 Mar 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Pranav Paradise?
The registered promoter entity is Pranav Builders, a partnership as per the filing. Its GSTIN 27AANFP0882E1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Pranav Paradise?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Pranav Paradise?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Pranav Paradise?
The professionals named in the filing: Architect: Ar Ambernath M Shinde; Engineer: Dr Nandkumar K Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Pranav Paradise?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback