Home / Browse projects / Sangli, Maharashtra / Pranav Sky
Pranav Sky
RG-MH-62218 · RERA P53100047235 · Last updated on MahaRERA portal: 27 Mar 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 19 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Pranav Sky is a Residential / Group Housing project by Pranav Builders in Sangli, Maharashtra, registered with MahaRERA as P53100047235 on 12 Oct 2022. Possession was promised by 25 Mar 2025 and is now 19 months past that date.
At a glance
Project
- NamePranav Sky
- TypeResidential / Group Housing
- Location
- Ahilyabai Holkar Smarak Road
- Shahu Nagar
- Sangli Miraj Kupwad (M Corp.)
- Miraj
- Sangli
- 416436
- Pincode416436
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53100047235
- ReraGenie IDRG-MH-62218
Builder
- NamePranav Builders
- Entity typePartnership
- GSTIN27AANFP0882E1Z2
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersArvind Baburao Patil, Vinod Shamrao Patil
- Other registrations5 more →
- Completed4 of 6
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects9 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on12 Oct 2022
- Promised completion25 Mar 2025
- Revised completionNone
- Buildings1 building record
- Documents filed37 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Pranav Sky | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.
Pranav Sky: 45% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Pranav Builders | Karnal | Sangli |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ambar M Shinde |
| Engineer | Sajan Baban Chavan |
| Chartered Accountant | Kumbhojkar Kulkarni deshpande & Associates |
| Partner | Role in project |
|---|---|
| Pranav Builders | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Jul 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Mar 2025
Documents filed37
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Sky OCCertificate.pdf | 27 Mar 2025 |
| Proforma of Agreement for saleFile: SKY AGREEMENT TO SALE IMP.pdf | 26 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT S CERTIFICATE 31-12-2023 SKY.pdf | 27 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 31-12-2023 SKY.pdf | 27 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 31-12-2023 SKY.pdf | 27 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG SKY 30-09-2023.pdf | 4 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA SKY 30-09-2023.pdf | 4 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate sky.pdf | 27 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 31-6-2023.pdf | 12 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 30-9-2023.pdf | 12 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SKY ENGINEER 31-6-2023.pdf | 12 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SKY ENGINEER 30-9-2023.pdf | 12 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SKY.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate sky.pdf | 17 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate sky.pdf | 17 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate sky.pdf | 17 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: pranav sky architects certificate form 1.pdf | 17 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: pranav sky engineers form 2.pdf | 17 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: pranav sky CA certificate form 3.pdf | 17 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate form 3 Sky .pdf | 3 Oct 2022 |
| Proforma of Allotment letterFile: Allotment letter SKY-U.pdf | 19 Sep 2022 |
| Proforma of Allotment letterFile: Model agreement as per RERA Sky-u.pdf | 19 Sep 2022 |
| Copy of the legal title reportFile: Legal search report Sky .pdf | 5 Sep 2022 |
| Declaration about Commencement CertificateFile: Declaration about commencement certificate Sky.pdf | 5 Sep 2022 |
| Details of encumbrances concerned to FinanceFile: Encumbrance letter finance Sky .pdf | 24 Aug 2022 |
| Details of encumbrances concerned to LegalFile: Encumbrance letter Legal.pdf | 24 Aug 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Acc details Sky.pdf | 24 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: Deviation report Allottment letter.pdf | 24 Aug 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation report Agreement.pdf | 24 Aug 2022 |
| PAN CardFile: Pranav Builders PAN card .pdf | 9 Aug 2022 |
| Declaration in FORM BFile: Form B Builder.pdf | 9 Aug 2022 |
| CERSAI detailsFile: Cersai Report Sky.pdf | 9 Aug 2022 |
| Layout approvalFile: NAKASHA.pdf | 6 Jul 2022 |
| Building plan approvalFile: DWG.pdf | 6 Jul 2022 |
| Copy of Layout Approval (in case of layout)File: NAKASHA.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: DWG.pdf | 6 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: BUILDING PERMISSION.pdf | 6 Jul 2022 |
Promoter's earlier projects8
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Pranav BreezeP53100046600 | 100' Road, Sangli | 24 | Aug 2022 | Ongoing | Mar 2025 | Not delivered |
| Pranav CornerP53100047076 | Tuljainagar, Sangli | 10 | Sep 2022 | Completed | Dec 2024 | Jan 1970 |
| Pranav Paradise | Tuljainagar Near Podar School Kupwad | 16 | - | Completed | Mar 2019 | Oct 2018 |
| Pranav Park | Revenue Colony Near Bapat Mala | 8 | - | Completed | Jan 2019 | Late, Feb 2019 |
| Pranav Square | Tuljai Nagar near Podar School | 6 | - | Completed | Aug 2018 | Jul 2018 |
| Pranav Pearl | Tulajainagar Kupwad | 12 | - | Completed | Feb 2017 | Jan 2017 |
| Pranav Pride | Tuljainagar kupwad | 6 | - | Completed | Apr 2015 | Late, May 2015 |
| Pranav Heights | Chinmay Park Road | 12 | - | Completed | Feb 2014 | Jan 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 37 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Pranav Sky on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shahu Nagar790+ in Sangli
Filed coordinates, straight-line distance. 158 registered projects within 2 km.
MANOMAY
YUVRAJ JAYSINGRAO PATIL
VAJE VATSALYAM
V D VAJE BUILDERS & DEVELOPERS
SHREE KRUPA CITY
TATYASAHEB SAMBHAJI KHOT
VASTU SIDDHI
VASTUSHRADDHA ASSOCIATES
MEGH MALHAR RESIDENCY
MALHAR BUILDCON
ARIHANT NANO PEARL
SURAJ ANNASAHEB UPADHYE
See every Sangli project, with the district possession charts
Builder: Pranav Builders
Pranav Builders has 6 registrations on MahaRERA, including Pranav Paradise and Pranav Flora. Its filings disclose 9 earlier MahaRERA projects: declares 5 of 7 past projects completed on time. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What does it mean that Pranav Sky shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Pranav Sky is delayed beyond 25 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Pranav Sky?
The registered promoter entity is Pranav Builders, a partnership as per the filing. Its GSTIN 27AANFP0882E1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Pranav Sky?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Pranav Sky?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Pranav Sky?
The professionals named in the filing: Architect: Ambar M Shinde; Engineer: Sajan Baban Chavan; Chartered Accountant: Kumbhojkar Kulkarni deshpande & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Pranav Sky?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback