Home / Developers / Pranav Builders

Pranav Builders: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

Pranav Builders has 6 registrations in this build, including Pranav Paradise and Pranav Flora. Its filings disclose 9 earlier MahaRERA projects: 5 of 7 past projects completed on time.

6Registrations in this build
9Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Pranav ParadiseSangli, Maharashtra--Completed
Pranav FloraSangli, Maharashtra--Completed
Pranav PushkaramSangli, Maharashtra--Completed
Pranav BreezeSangli, Maharashtra--Registration lapsed
Pranav SkySangli, Maharashtra--Registration lapsed
Pranav CornerSangli, Maharashtra--Completed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Pranav Heights
4 Feb 20141 Jan 2014On time
Pranav Pride
16 Apr 201530 May 2015+1 months
Pranav Pearl
1 Feb 201717 Jan 2017On time
Pranav Square
22 Aug 201817 Jul 2018On time
Pranav Park
16 Jan 201928 Feb 2019+1 months
Pranav Paradise
15 Mar 201912 Oct 2018On time
Pranav Corner
P53100047076
30 Dec 20241 Jan 1970On time
Pranav Sky
P53100047235
25 Mar 2025Not completed yetOngoing
Pranav Breeze
P53100046600
25 Mar 2025Not completed yetOngoing

Frequently asked questions

How do I verify Pranav Builders as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Pranav Builders?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.