PPRL Basera - Jaynagar
By Vinaykumar Uttamchand Parakh
RG-MH-36203 · RERA P49900050211 · Last updated on MahaRERA portal: 17 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Jalgaon registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PPRL Basera - Jaynagar is a Others project by Vinaykumar Uttamchand Parakh in Jalgaon, Maharashtra, registered with MahaRERA as P49900050211 on 27 Mar 2023. Possession is promised by 30 Dec 2026. The completion date has moved by 12 months from the original filing. 38 of the 214 units on this registration are recorded sold or booked, and 151 of 231 construction stages are filed complete.
At a glance
Project
- NamePPRL Basera - Jaynagar
- TypeOthers
- Location
- g no. 36/2/a
- Bodwad
- Bodvad
- Jalgaon
- 425310
- Pincode425310
- MapView location on Google Maps (as filed on RERA)
- RERA no.P49900050211
- ReraGenie IDRG-MH-36203
Builder
- NameVinaykumar Uttamchand Parakh
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on27 Mar 2023
- Promised completion30 Dec 2026
- Revised completionRevised to 30 Dec 2026 (originally 30 Dec 2025)
- Buildings21 building records
- Documents filed100 files
Current status
Figures as on 17 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CLUSTER 1 | NA | 2 | 0 | 10 | 0 | 10 |
| CLUSTER 2 | NA | 2 | 0 | 6 | 0 | 6 |
| CLUSTER 3 | NA | 2 | 0 | 4 | 0 | 4 |
| CLUSTER 4 | NA | 2 | 0 | 7 | 0 | 7 |
| CLUSTER 5 | NA | 2 | 0 | 6 | 0 | 6 |
| CLUSTER 6 | NA | 1 | 0 | 18 | 0 | 18 |
| CLUSTER 7 | NA | 1 | 0 | 14 | 0 | 14 |
| CLUSTER 8 | NA | 1 | 0 | 18 | 0 | 18 |
| CLUSTER 9 | NA | 1 | 0 | 20 | 0 | 20 |
| CLUSTER 10 | NA | 1 | 0 | 18 | 0 | 18 |
| CLUSTER 11 | NA | 1 | 0 | 20 | 0 | 20 |
| CLUSTER 12 | NA | 1 | 0 | 8 | 0 | 8 |
| CLUSTER 13 | NA | 1 | 0 | 7 | 0 | 7 |
| CLUSTER 14 | NA | 2 | 0 | 8 | 0 | 8 |
| CLUSTER 15 | NA | 1 | 0 | 9 | 0 | 9 |
| CLUSTER 16 | NA | 1 | 0 | 5 | 0 | 5 |
| CLUSTER 17 | NA | 1 | 0 | 4 | 0 | 4 |
| SHOPPING 1 | NA | 1 | 1 | 0 | 9 | 9 |
| SHOPPING 2 | NA | 1 | 1 | 0 | 9 | 9 |
| SHOPPING 3 | NA | 1 | 0 | 0 | 9 | 9 |
| SHOPPING 4 | NA | 1 | 0 | 0 | 5 | 5 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 21 buildings; the table lists the first 20.
151 of 231 construction stages are filed complete across 21 buildings. The stage furthest along is Staircases, at 80%.
CLUSTER 173%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | - |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 343%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | - |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 444%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 544%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 673%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 773%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 873%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 973%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 1073%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 1173%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 1268%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 1368%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 1451%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 76% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 1573%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 1673%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUSTER 1773%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SHOPPING 173%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SHOPPING 273%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SHOPPING 373%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 29% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed233
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| CLUSTER 1 | 13 | 13 |
| CLUSTER 2 | 8 | 8 |
| CLUSTER 3 | 5 | 5 |
| CLUSTER 4 | 9 | 9 |
| CLUSTER 5 | 8 | 8 |
| CLUSTER 6 | 18 | 18 |
| CLUSTER 7 | 14 | 14 |
| CLUSTER 8 | 18 | 18 |
| CLUSTER 9 | 27 | 27 |
| CLUSTER 10 | 18 | 18 |
| CLUSTER 11 | 20 | 20 |
| CLUSTER 12 | 8 | 8 |
| CLUSTER 13 | 7 | 7 |
| CLUSTER 14 | 10 | 10 |
| CLUSTER 15 | 9 | 9 |
| CLUSTER 16 | 5 | 5 |
| CLUSTER 17 | 4 | 4 |
| SHOPPING 1 | 9 | 9 |
| SHOPPING 2 | 9 | 9 |
| SHOPPING 3 | 9 | 9 |
| SHOPPING 4 | 5 | 5 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SATISH PUNDLIKRAO BAVISKAR | Aurangabad (M Corp.) | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 1.95 cr | Rs 1.77 cr |
| CLUSTER 1 | NA | Rs 55.75 lakh | Rs 55.75 lakh |
| CLUSTER 2 | NA | Rs 55.75 lakh | Rs 55.75 lakh |
| CLUSTER 3 | NA | Rs 55.75 lakh | Rs 37.45 lakh |
| CLUSTER 4 | NA | Rs 55.75 lakh | Rs 38.25 lakh |
| CLUSTER 5 | NA | Rs 55.75 lakh | Rs 38.25 lakh |
| CLUSTER 6 | NA | Rs 55.75 lakh | Rs 55.75 lakh |
| CLUSTER 7 | NA | Rs 55.75 lakh | Rs 55.75 lakh |
| CLUSTER 8 | NA | Rs 55.75 lakh | Rs 55.75 lakh |
| CLUSTER 9 | NA | Rs 55.75 lakh | Rs 55.75 lakh |
| CLUSTER 10 | NA | Rs 55.75 lakh | Rs 55.75 lakh |
| CLUSTER 11 | NA | Rs 55.75 lakh | Rs 55.75 lakh |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | UJWAL BHOLE |
| Engineer | MOHIT PATIL |
| Chartered Accountant | TEJAS KAWADIYA |
| Partner | Role in project |
|---|---|
| Vinaykumar Uttamchand Parakh | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRequest for Extension of Project Completion Period by One Year The AHP-PPP model project under PMAY at Bodwad, District Jalgaon was duly approved, and all requisite permissions were obtained in 2024. The project comprises a total of 214 units, including 141 EWS units, 41 LIG units, and 32 shops. Out of these, Part Occupation Certificates have already been granted for 88 EWS units and 27 shops. The remaining 74 units (53 EWS, 16 LIG, and 5 shops) are fully constructed, and only the Occupation Certificate is pending. Overall, approximately 88% of the project work has been completed, and the bala
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Mar 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Mar 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2026
Documents filed100
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: 15_Architects Certificate.pdf | 17 Jul 2026 |
| Withdrawal Update Form 1File: 14_Architects certificate.pdf | 17 Jul 2026 |
| Withdrawal Update Form 2File: 15_Engineer Certificate.pdf | 17 Jul 2026 |
| Withdrawal Update Form 2File: 14_Engineer Certificate.pdf | 17 Jul 2026 |
| Withdrawal Update Form 3File: 15_CA Certificate.pdf | 17 Jul 2026 |
| Withdrawal Update Form 3File: 15_CA Certificate.pdf | 17 Jul 2026 |
| Withdrawal Update Form 1File: 12_Architects Cetificate 081025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: 13_Engineers Certificate-150126.pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: 13_CA Certificate 260126.pdf | 29 Jan 2026 |
| Form 1File: 2_Architect Certificate 050823.pdf | 13 Dec 2025 |
| Form 2File: 2_Civil Engineer Certificate 050823.pdf | 13 Dec 2025 |
| Form 3File: 2_Kawadia CA Certificate 050823.pdf | 13 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 2_Kawadia CA Certificate 050823.pdf | 13 Dec 2025 |
| Form 1File: 4_Architect_311223.pdf | 13 Dec 2025 |
| Form 2File: 4_Engineer_311223.pdf | 13 Dec 2025 |
| Form 3File: 4_CA_311223_compressed.pdf | 13 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 4_CA_311223_compressed.pdf | 13 Dec 2025 |
| Form 1File: 5_Architects Certificate.pdf | 13 Dec 2025 |
| Form 2File: 5_Engineers Certificate.pdf | 13 Dec 2025 |
| Form 3File: 5_CA certificate.pdf | 13 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 5_CA certificate.pdf | 13 Dec 2025 |
| Form 1File: 3_Architure Certificate.pdf | 13 Dec 2025 |
| Form 2File: 3_EngineerCertificate.pdf | 13 Dec 2025 |
| Form 3File: 3_CA Certificate.pdf | 13 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 3_CA Certificate.pdf | 13 Dec 2025 |
| Form 1File: 6_Architect Certificate.pdf | 13 Dec 2025 |
| Form 2File: 6_Engineer Certificate.pdf | 13 Dec 2025 |
| Form 3File: 6_CA Certificate.pdf | 13 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 6_CA Certificate.pdf | 13 Dec 2025 |
| Form 1File: 7_Architect Certificate.pdf | 13 Dec 2025 |
| Form 2File: 7_Engineer Certificate_compressed.pdf | 13 Dec 2025 |
| Form 3File: 7_CA Certficate_compressed.pdf | 13 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 7_CA Certficate_compressed.pdf | 13 Dec 2025 |
| Form 1File: 9_Architect Certificate.pdf | 13 Dec 2025 |
| Form 2File: 10_Engineer Certificate.pdf | 13 Dec 2025 |
| Form 3File: 9_CA Certficate_compressed.pdf | 13 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 9_CA Certficate_compressed.pdf | 13 Dec 2025 |
| Withdrawal Update Form 1File: 11_Architect certificate 10072025.pdf | 13 Dec 2025 |
| Withdrawal Update Form 1File: 12_Architects Cetificate 081025.pdf | 13 Dec 2025 |
| Withdrawal Update Form 2File: 11_Engineer Certificate-120725.pdf | 13 Dec 2025 |
| Withdrawal Update Form 2File: 11_Engineer Certificate-120725.pdf | 13 Dec 2025 |
| Withdrawal Update Form 3File: Parakh Realties CA Certificate-010724 (1)_compressed.pdf | 13 Dec 2025 |
| Withdrawal Update Form 3File: 12_CA Certificate 221025.pdf | 13 Dec 2025 |
| Form 1File: 9_Architect Certificate.pdf | 3 Nov 2025 |
| Form 2File: 10_Engineer Certificate.pdf | 3 Nov 2025 |
| Form 3File: 10_CA Certificate.pdf | 3 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 10_CA Certificate.pdf | 3 Nov 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10_CA Certificate_compressed.pdf | 29 Apr 2025 |
| 10_Engineer Certificate | 29 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9_Architect Certificate_compressed.pdf | 3 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9_CA Certficate_compressed_compressed.pdf | 3 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7_Architect Certificate.pdf | 24 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7_CA Certficate_compressed.pdf | 24 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7_Engineer Certificate_compressed.pdf | 24 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6_Architect Certificate.pdf | 17 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6_Engineer Certificate.pdf | 17 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Parakh Realties CA Certificate-010724 (1)_compressed.pdf | 16 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5_Architects Certificate.pdf | 12 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5_Engineers Certificate.pdf | 12 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5_CA certificate_compressed.pdf | 12 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_2022-23.pdf | 12 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4_Architect_311223.pdf | 16 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4_Engineer_311223.pdf | 16 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4_CA_311223_compressed.pdf | 16 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2_Architect Certificate 050823.pdf | 18 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Civil Engineer Certificate 050823.pdf | 18 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3_EngineerCertificate.pdf | 18 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Citycon-Kawadia Certificate 131123.pdf | 18 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 050823.pdf | 3 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Civil Engineer Certificate 050823.pdf | 3 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: 1 Inventory disclosure.pdf | 3 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kawadia CA Certificate 050823_compressed.pdf | 3 Nov 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: self declaration new.pdf | 27 Jun 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format a new.pdf | 27 Jun 2023 |
| Declaration about Commencement CertificateFile: DocScanner Mar 22, 2023 11-59.pdf | 22 Mar 2023 |
| Building plan approvalFile: Page 1.pdf | 17 Mar 2023 |
| Building plan approvalFile: Page 2.pdf | 17 Mar 2023 |
| Building plan approvalFile: Page 3.pdf | 17 Mar 2023 |
| Building plan approvalFile: Page 4.pdf | 17 Mar 2023 |
| Layout approvalFile: PMAY_Bodwad_Approved Layout_compressed.pdf | 17 Mar 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Jalgaon
Computed across the 230+ Jalgaon projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 100 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PPRL Basera - Jaynagar on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bodwad230+ in Jalgaon
ADITYA GOLD CITY
ADITYA BUILDERS AND DEVELOPERS
Chhoriya Fortune City -Parola plotting
ANMOL CHHORIYA AND ASSOCIATES
KRUSHNAJI ARCADE
M/S. SHREYASH REALTIES
SSD Complex
Jay Narayan Developers
B M RAVAL PLAZA
DUSHYANT PRAVINSAGAR RAVAL
SUKRUTI SURATNA
SURATNA INFRA LLP
See every Jalgaon project, with the district possession charts
Builder: Vinaykumar Uttamchand Parakh
Vinaykumar Uttamchand Parakh has 1 registration on MahaRERA, including PPRL Basera - Jaynagar. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalgaon district page.
Frequently asked questions
What are my rights if PPRL Basera - Jaynagar is delayed beyond 30 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PPRL Basera - Jaynagar?
The registered promoter entity is Vinaykumar Uttamchand Parakh, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PPRL Basera - Jaynagar?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PPRL Basera - Jaynagar?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PPRL Basera - Jaynagar?
The professionals named in the filing: Architect: UJWAL BHOLE; Engineer: MOHIT PATIL; Chartered Accountant: TEJAS KAWADIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PPRL Basera - Jaynagar?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback