ReraGenieLog inGet a buyer report

Home / Browse projects / Jalgaon, Maharashtra / ADITYA GOLD CITY

Registered No litigation declared Others project

ADITYA GOLD CITY

By ADITYA BUILDERS AND DEVELOPERS

RG-MH-03875 · RERA P49900023478 · Last updated on MahaRERA portal: 21 May 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Jalgaon registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
7 of 33Construction stages doneacross 3 buildings; furthest along: Sanitary Fittings within the flats /..., 90%
124 of 206Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 176 documents Report an error

ADITYA GOLD CITY is a Others project by ADITYA BUILDERS AND DEVELOPERS in Jalgaon, Maharashtra, registered with MahaRERA as P49900023478 on 16 Dec 2019. Possession is promised by 30 Dec 2030. 82 of the 206 units on this registration are recorded sold or booked, and 7 of 33 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameADITYA GOLD CITY
  • TypeOthers
  • Location
    • SURVEY NO 38/2A/1
    • Near Godawari Engineering College
    • National Highway No. 6
    • Besides Usha Motors
    • MIDC Area
    • Jalgaon - 425003
    • SHIVAR KHEDI BUDRUK
    • MIDC...
  • Pincode425003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P49900023478
  • ReraGenie IDRG-MH-03875

Builder

  • NameADITYA BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersSUMEET PRAKASHCHAND MUTHA, AJAY SHANTILAL LALWANI
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2019PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Dec 2019
  • Promised completion30 Dec 2030
  • Revised completionNone
  • Buildings3 building records
  • Documents filed176 files

Current status

40%82 of 206 units booked

Figures as on 21 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DIAMONDNA14141290129
PLATINUMNA9976076
PEARLNA50011

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 21 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

DIAMOND78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.68%
PLATINUM0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PEARL0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 21 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes25%
Street LightingYes25%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes25%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes25%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes25%
CHILDREN PLAY AREAYes0%

Parking filed254

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots254
Closed/Covered254
BuildingClosed/CoveredTotal
DIAMOND153153
PLATINUM7676
PEARL2525

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,100 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
TARADEVI RATANLAL BAFNAJalgaonJalgaon
SUNIL KASTURCHAND BAFNAJalgaonJalgaon
VINIT SATISH OSWALJalgaonJalgaon

Approvals and building plan

Sanctioning authorityJalgaon Municipal Corporation
Permissible FSI18598.88
Proposed, not sanctioned13,568 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPlot No 02 Opposite JDCC Bank Ring Road Jalgaon 425001

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMILIND RATHI
ArchitectMAYURESH AGRAWAL
EngineerMILIND RATHI
Chartered AccountantNACHIKET JAKHETIYA
Chartered AccountantRAVINDRA CHHAJER
PartnerRole in project
ADITYA BUILDERS AND DEVELOPERS-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
SM12600013Ram GawaliADITYA BUILDERS AND DEVELOPERS06/01/2026
SM12600014Ram GawaliADITYA BUILDERS AND DEVELOPERS06/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2030

Documents filed176

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 176 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form131032026.pdf21 May 2026
Form 2File: Form231032026.pdf21 May 2026
Form 3File: Form331032026.pdf21 May 2026
Disclosure of Sold and Booked InventoryFile: UI31032026.pdf21 May 2026
Form 2A (FY 2019-2020)File: Form2A31032020.pdf30 Mar 2026
Form 2A (FY 2020-2021)File: Form2A31032021.pdf30 Mar 2026
Form 2A (FY 2021-2022)File: 3Form2A31032022.pdf30 Mar 2026
Form 2A (FY 2022-2023)File: 4Form2A31032023.pdf30 Mar 2026
Form 2A (FY 2023-2024)File: 5Form2A31032024.pdf30 Mar 2026
Form 2A (FY 2024-2025)File: 6Form2A31032025.pdf30 Mar 2026
Form 2A (FY 2025-2026)File: 7Form2A31032026.pdf30 Mar 2026
Form 5 (FY 2019-2020)File: AGC - Form 5_2020.pdf22 Mar 2026
Form 5 (FY 2020-2021)File: AGC - Form 5_2021.pdf22 Mar 2026
Form 5 (FY 2021-2022)File: AGC - Form 5_2022.pdf22 Mar 2026
Form 5 (FY 2022-2023)File: AGC - Form 5_2023.pdf22 Mar 2026
Form 5 (FY 2023-2024)File: AGC - Form 5_2024.pdf22 Mar 2026
Form 5 (FY 2024-2025)File: AGC - Form 5_2025.pdf22 Mar 2026
Form 1File: Form130062022.pdf5 Mar 2026
Form 2File: Form230062022.pdf5 Mar 2026
Form 3File: Form330062022.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI30062022.pdf5 Mar 2026
Form 1File: Form130092022.pdf5 Mar 2026
Form 2File: Form230092022.pdf5 Mar 2026
Form 3File: Form330092022.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI30092022.pdf5 Mar 2026
Form 1File: Form131122022.pdf5 Mar 2026
Form 2File: Form231122022.pdf5 Mar 2026
Form 3File: Form331122022.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI31122022.pdf5 Mar 2026
Form 1File: Form131032023.pdf5 Mar 2026
Form 2File: Form231032023.pdf5 Mar 2026
Form 3File: Form331032023.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI31032023.pdf5 Mar 2026
Form 1File: Form130062023.pdf5 Mar 2026
Form 2File: Form230062023.pdf5 Mar 2026
Form 3File: Form330062023.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI30062023.pdf5 Mar 2026
Form 1File: Form130092023.pdf5 Mar 2026
Form 2File: Form230092023.pdf5 Mar 2026
Form 3File: Form330092023.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI30092023.pdf5 Mar 2026
Form 1File: Form131122023.pdf5 Mar 2026
Form 2File: Form231122023.pdf5 Mar 2026
Form 3File: Form331122023.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI31122023.pdf5 Mar 2026
Form 1File: Form131032024.pdf5 Mar 2026
Form 2File: Form231032024.pdf5 Mar 2026
Form 3File: Form331032024.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI31032024.pdf5 Mar 2026
Form 1File: Form130062024.pdf5 Mar 2026
Form 2File: Form230062024.pdf5 Mar 2026
Form 3File: Form330062024.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI30062024.pdf5 Mar 2026
Form 1File: Form130092024.pdf5 Mar 2026
Form 2File: Form230092024.pdf5 Mar 2026
Form 3File: Form330092024.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI30092024.pdf5 Mar 2026
Form 1File: Form131122024.pdf5 Mar 2026
Form 2File: Form231122024.pdf5 Mar 2026
Form 3File: Form331122024.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI31122024.pdf5 Mar 2026
Form 1File: Form131032025.pdf5 Mar 2026
Form 2File: Form231032025.pdf5 Mar 2026
Form 3File: Form331032025.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI31032025.pdf5 Mar 2026
Form 1File: Form130062025.pdf5 Mar 2026
Form 2File: Form230062025.pdf5 Mar 2026
Form 3File: Form330062025.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI30062025.pdf5 Mar 2026
Form 1File: Form130092025.pdf5 Mar 2026
Form 2File: Form230092025.pdf5 Mar 2026
Form 3File: Form330092025.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI30092025.pdf5 Mar 2026
Form 1File: Form131122025Final.pdf5 Mar 2026
Form 2File: Form231122025.pdf5 Mar 2026
Form 3File: Form331122025.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: UI31122025.pdf5 Mar 2026
Form 1File: Form131122019.pdf4 Mar 2026
Form 2File: Form231122019.pdf4 Mar 2026
Form 3File: Form331122019.pdf4 Mar 2026

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
ADITYA BRIZE PARKNEAR ANURAG STATE BANK COLONY JALGAON55CompletedMar 2016Jan 2016

How this compares with Jalgaon

40%of this project is bookeddistrict median 21%
5%of Jalgaon projects moved their completion datethis one has not
32%of Jalgaon registrations have lapsed or been cancelledthis one is on the register

Computed across the 230+ Jalgaon projects on ReraGenie, from their own filings.

Keep ADITYA GOLD CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHIVAR KHEDI BUDRUK, MIDC AREA230+ in Jalgaon

Builder: ADITYA BUILDERS AND DEVELOPERS

ADITYA BUILDERS AND DEVELOPERS has 4 registrations on MahaRERA, including SAI DARSHAN APARTMENT and SUPRIYA RESIDENCY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Jalgaon district page.

Frequently asked questions

What are my rights if ADITYA GOLD CITY is delayed beyond 30 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ADITYA GOLD CITY?

The registered promoter entity is ADITYA BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ADITYA GOLD CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ADITYA GOLD CITY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ADITYA GOLD CITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ADITYA GOLD CITY?

The professionals named in the filing: Architect: MILIND RATHI; Architect: MAYURESH AGRAWAL; Engineer: MILIND RATHI; Chartered Accountant: NACHIKET JAKHETIYA; Chartered Accountant: RAVINDRA CHHAJER. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ADITYA GOLD CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ADITYA GOLD CITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ADITYA GOLD CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.