ReraGenieLog inGet a buyer report

Home / Browse projects / Jalgaon, Maharashtra / KRUSHNAJI ARCADE

Registered No litigation declared Commercial project

KRUSHNAJI ARCADE

By M/S. SHREYASH REALTIES

RG-MH-96421 · RERA P49900055715 · Last updated on MahaRERA portal: 26 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Jalgaon registration emailed to you, free during the pilot beta.
Jan 2028Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Staircases, 75%
190 of 190Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

KRUSHNAJI ARCADE is a Commercial project by M/S. SHREYASH REALTIES in Jalgaon, Maharashtra, registered with MahaRERA as P49900055715 on 15 Apr 2024. Possession is promised by 31 Jan 2028. 0 of the 190 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameKRUSHNAJI ARCADE
  • TypeCommercial
  • Location
    • BHADGAON ROAD
    • SAMBHAJI CHOWK
    • Pachora (Rural) (CT)
    • Pachora
    • Jalgaon
    • 424201
  • Pincode424201
  • RERA no.P49900055715
  • ReraGenie IDRG-MH-96421

Builder

  • NameM/S. SHREYASH REALTIES
  • Entity typePartnership
  • PartnersKAMALBAI HIRALAL KUMAVAT, KAVITA PARDEEP PATIL, SAPANA UMESH KUMAVAT, SANJAYKUMAR HIRALAL KUMAVAT
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2024PromisedJan 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Apr 2024
  • Promised completion31 Jan 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed104 files

Current status

0%0 of 190 units booked
95.9%Work done, per cost certificate

Figures as on 26 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KRUSHNAJI ARCADENA860190190

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 75%.

KRUSHNAJI ARCADE: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 26 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed277

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots277
Closed/Covered277

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,052 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
MADHUKAR PUROSHOTTAM WANIJalgaonJalgaon
SURESH LAXMAN WANIJalgaonJalgaon
HARICHANDRA LAXMAN WANIBhadgaon Jalgaon
RAMCHANDRA LAXMAN WANIBhadgaon Jalgaon
PRASHANT BALCHANDRA YEOLEJalna (M Cl)Jalna
PRADIP BHALCHANDRA VANIJalna (M Cl)Jalna

Approvals and building plan

Sanctioning authorityNagar Parishad, Pachora
Permissible FSI12389.2
Proposed, not sanctioned7,689 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAXMI PLAZA BHADGAON ROAD PACHORA MAHARASHTRA - 424201
Estimated costRs 11.22 cr
Cost incurredRs 10.76 cr
Work done95.9%
BuildingWingEstimatedIncurred
KRUSHNAJI ARCADENARs 10.72 crRs 10.44 cr
-NARs 49.50 lakhRs 31.75 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTHE DESIGNERS COLLECTIVE NASHIK
EngineerMR MILIND RATHI
EngineerBHUSHAN PHATE
Chartered AccountantANUJ A BAFNA
Chartered AccountantSHASHIKANT DHAMNE
PartnerRole in project
M/S. SHREYASH REALTIES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jan 2028

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architects Certificate (Form 1) 31 12 2025 SIGN.pdf26 May 2026
Withdrawal Update Form 1File: Architects Certificate (Form 1) 31 12 2025 SIGN.pdf26 May 2026
Withdrawal Update Form 2File: _Form_2_Dec_25__1_ SIGN.pdf26 May 2026
Withdrawal Update Form 2File: _Form_2_Dec_25__1_ SIGN.pdf26 May 2026
Withdrawal Update Form 3File: FORM 3 WITH UPDATED UDIN.pdf26 May 2026
Withdrawal Update Form 3File: FORM 3 FINAL Q3.pdf26 May 2026
Form 2A (FY 2024-2025)File: FORM 2A 2024-25- BHUSHAN PHATE SIR_0001.pdf6 Jan 2026
Withdrawal Update Form 1File: Draft Form 1 - 30-06-2025 Draft done.pdf17 Dec 2025
Withdrawal Update Form 1File: Draft Form 1 - 30-06-2025 Draft done.pdf17 Dec 2025
Withdrawal Update Form 1File: Draft Form 1 - 30-06-2025 Draft done.pdf17 Dec 2025
Withdrawal Update Form 1File: form 1_0001.pdf17 Dec 2025
Withdrawal Update Form 2File: Form - 2_Updated_KRUSHNAJI ARCADE.pdf17 Dec 2025
Withdrawal Update Form 2File: Form - 2_Updated_KRUSHNAJI ARCADE.pdf17 Dec 2025
Withdrawal Update Form 2File: FORM 2 Jun 25.pdf17 Dec 2025
Withdrawal Update Form 2File: Form 2 Sep 25.pdf17 Dec 2025
Withdrawal Update Form 3File: sign form 3 june 25.pdf17 Dec 2025
Withdrawal Update Form 3File: sign form 3 june 25.pdf17 Dec 2025
Withdrawal Update Form 3File: sign form 3 june 25.pdf17 Dec 2025
Withdrawal Update Form 3File: final form 3 sep 25_11zon.pdf17 Dec 2025
Form 5 (FY 2024-2025)File: SCANNED ANNEX F FORM 5.pdf25 Oct 2025
Form 1File: Draft Form 1 - 31-03-2025 Draft done.pdf13 Oct 2025
Form 2File: Form_-_2_March_25_KRUSHNAJI_ARCADE_.pdf13 Oct 2025
Form 3File: Uploaded Form 3.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold March 25.pdf13 Oct 2025
Form 1File: Draft Form 1 - 30-06-2024 Draft done.pdf9 Oct 2025
Form 2File: Form_-_2_June_24 (1).pdf9 Oct 2025
Form 3File: Form 3 Final.pdf9 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold jun 24.pdf9 Oct 2025
Form 1File: Draft Form 1 - 30-09-2024 Draft done.pdf9 Oct 2025
Form 2File: Form_-_2_Sept_24 (1).pdf9 Oct 2025
Form 3File: final form 3.pdf9 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Sept 24.pdf9 Oct 2025
Form 1File: Draft Form 1 - 31-12-2024 Draft done.pdf9 Oct 2025
Form 2File: Form_-_2_Dec_24 (1).pdf9 Oct 2025
Form 3File: form 3 final.pdf9 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 24.pdf9 Oct 2025
Declaration about Commencement CertificateFile: 5 Declaration About Commencement Certificate - Confirmation Final.pdf3 Apr 2024
Declaration about Commencement CertificateFile: Final Appendix F Ack_merged.pdf3 Apr 2024
Other - TechnicalFile: Final Appendix F Ack_merged.pdf3 Apr 2024
Declaration in FORM BFile: Form B Final.pdf12 Mar 2024
Other - TechnicalFile: 1 Annuxure A Delc cum Undertaking.pdf1 Mar 2024
Copy of the legal title reportFile: lEGAL TITLE_11zon.pdf21 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: fINAL fORM 3.pdf12 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Of interest SANJAY H KUMAVAT.pdf5 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest (SAPNA KUMAVAT).pdf5 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest (KAVITA PATILl).pdf5 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest (KAMALBAI H KUMAVAT).pdf5 Feb 2024
Proforma of Allotment letterFile: Allottment Letter as per rera.pdf5 Feb 2024
Proforma of Agreement for saleFile: Agreement to sale Draft_Uploaded.pdf5 Feb 2024
Other - LegalFile: Partnership Deed_Uploaded.pdf5 Feb 2024
Other - LegalFile: Partnership Certificate.pdf5 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate -Form 1- -29-01-2024-.pdf30 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2_Updated_KRUSHNAJI ARCADE.pdf30 Jan 2024
CERSAI detailsFile: CERSAI report declaration.pdf30 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Sperate Form A Bank Details-.pdf30 Jan 2024
Details of encumbrances concerned to FinanceFile: DECLARATION OF ENCUMBRANCES CONCERNED TO FINANCE.pdf29 Jan 2024
Details of encumbrances concerned to FinanceFile: Declaration of Encumbrances legal.pdf29 Jan 2024
Details of encumbrances concerned to LegalFile: DECLARATION OF ENCUMBRANCES CONCERNED TO FINANCE.pdf29 Jan 2024
Details of encumbrances concerned to LegalFile: Declaration of Encumbrances legal.pdf29 Jan 2024
Deviation Report with respect to Allotment letterFile: Decln allotment letter .pdf29 Jan 2024
Deviation Report with respect to model copy of AgreementFile: Declaration Of No Deviation Agreement for sale.pdf29 Jan 2024
CERSAI detailsFile: CERSAI_Search_Report_200294778245_For_Asset_Based_Search_26_01_2024_13_33_20_801.pdf26 Jan 2024
Layout approvalFile: 1-1.pdf25 Jan 2024
Layout approvalFile: 1-9.pdf25 Jan 2024
Layout approvalFile: 2-9.pdf25 Jan 2024
Layout approvalFile: 3-9.pdf25 Jan 2024
Layout approvalFile: 4-9.pdf25 Jan 2024
Layout approvalFile: 5-9.pdf25 Jan 2024
Layout approvalFile: 6-9.pdf25 Jan 2024
Layout approvalFile: 7-9.pdf25 Jan 2024
Layout approvalFile: 8-9.pdf25 Jan 2024
Layout approvalFile: 9-9.pdf25 Jan 2024
Building plan approvalFile: 1-1.pdf25 Jan 2024
Building plan approvalFile: 1-9.pdf25 Jan 2024
Building plan approvalFile: 2-9.pdf25 Jan 2024
Building plan approvalFile: 3-9.pdf25 Jan 2024
Building plan approvalFile: 4-9.pdf25 Jan 2024
Building plan approvalFile: 5-9.pdf25 Jan 2024
Building plan approvalFile: 6-9.pdf25 Jan 2024
Building plan approvalFile: 7-9.pdf25 Jan 2024

How this compares with Jalgaon

0%of this project is bookeddistrict median 21%
5%of Jalgaon projects moved their completion datethis one has not
32%of Jalgaon registrations have lapsed or been cancelledthis one is on the register

Computed across the 230+ Jalgaon projects on ReraGenie, from their own filings.

Keep KRUSHNAJI ARCADE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SAMBHAJI CHOWK230+ in Jalgaon

Builder: M/S. SHREYASH REALTIES

M/S. SHREYASH REALTIES has 2 registrations on MahaRERA, including RAMANAND NAGAR and KRUSHNAJI ARCADE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalgaon district page.

Frequently asked questions

What are my rights if KRUSHNAJI ARCADE is delayed beyond 31 Jan 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KRUSHNAJI ARCADE?

The registered promoter entity is M/S. SHREYASH REALTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KRUSHNAJI ARCADE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KRUSHNAJI ARCADE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KRUSHNAJI ARCADE?

The professionals named in the filing: Architect: THE DESIGNERS COLLECTIVE NASHIK; Engineer: MR MILIND RATHI; Engineer: BHUSHAN PHATE; Chartered Accountant: ANUJ A BAFNA; Chartered Accountant: SHASHIKANT DHAMNE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRUSHNAJI ARCADE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRUSHNAJI ARCADE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRUSHNAJI ARCADE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.