PITAMBARI INDRADHANU VILLAGE
RG-MH-28320 · RERA P52800027429 · Last updated on MahaRERA portal: 26 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves.
See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PITAMBARI INDRADHANU VILLAGE is a Residential / Group Housing project by PITAMBARI PRODUCTS PVT LTD in Ratnagiri, Maharashtra, registered with MahaRERA as P52800027429 on 10 Dec 2020. Possession is promised by 30 Jun 2027.
At a glance
Project
- NamePITAMBARI INDRADHANU VILLAGE
- TypeResidential / Group Housing
- Location
- Sakhroli Enaam Pangari Road
- Sakhroli
- Dapoli
- Ratnagiri
- 415712
- Pincode415712
- RERA no.P52800027429
- ReraGenie IDRG-MH-28320
Builder
- NamePITAMBARI PRODUCTS PVT LTD
- Entity typeCompany
- Managing DirectorRAVINDRA VAMAN PRABHUDESAI
- DirectorsVRUSHALI RAVINDRA PRABHUDESAI, PARIKSHIT RAVINDRA PRABHUDESAI, PRIYANKA RAVINDRA PRABHUDESAI, SANJAY DATTARAM PARAB
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Dec 2020
- Promised completion30 Jun 2027
- Revised completionNone
- Buildings98 building records
- Documents filed76 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| E-54 | NA | 1 | 0 | 0 | 0 | 0 |
| E-58 | NA | 1 | 0 | 0 | 0 | 0 |
| E-59 | NA | 1 | 0 | 0 | 0 | 0 |
| E-61 | NA | 1 | 0 | 0 | 0 | 0 |
| E-69 | NA | 1 | 0 | 0 | 0 | 0 |
| E-71 | NA | 1 | 0 | 0 | 0 | 0 |
| E-77 | NA | 1 | 0 | 0 | 0 | 0 |
| E-78 | NA | 1 | 0 | 0 | 0 | 0 |
| E-80 | NA | 1 | 0 | 0 | 0 | 0 |
| E-86 | NA | 1 | 0 | 0 | 0 | 0 |
| E-87 | NA | 1 | 0 | 0 | 0 | 0 |
| E-88 | NA | 1 | 0 | 0 | 0 | 0 |
| E-90 | NA | 1 | 0 | 0 | 0 | 0 |
| E-91 | NA | 1 | 0 | 0 | 0 | 0 |
| E-92 | NA | 1 | 0 | 0 | 0 | 0 |
| E-94 | NA | 1 | 0 | 0 | 0 | 0 |
| E-95 | NA | 1 | 0 | 0 | 0 | 0 |
| E-6 | NA | 1 | 0 | 0 | 0 | 0 |
| E-8 | NA | 1 | 0 | 0 | 0 | 0 |
| E-9 | NA | 1 | 0 | 0 | 0 | 0 |
| E-19 | NA | 1 | 0 | 0 | 0 | 0 |
| E-18 | NA | 1 | 0 | 0 | 0 | 0 |
| E-21 | NA | 1 | 0 | 0 | 0 | 0 |
| E-22 | NA | 1 | 0 | 0 | 0 | 0 |
| E-28 | NA | 1 | 0 | 0 | 0 | 0 |
| E-29 | NA | 1 | 0 | 0 | 0 | 0 |
| E-30 | NA | 1 | 0 | 0 | 0 | 0 |
| E-33 | NA | 1 | 0 | 0 | 0 | 0 |
| E-34 | NA | 1 | 0 | 0 | 0 | 0 |
| E-35 | NA | 1 | 0 | 0 | 0 | 0 |
| E-38 | NA | 1 | 0 | 0 | 0 | 0 |
| E-39 | NA | 1 | 0 | 0 | 0 | 0 |
| E-40 | NA | 1 | 0 | 0 | 0 | 0 |
| E-43 | NA | 1 | 0 | 0 | 0 | 0 |
| E-44 | NA | 1 | 0 | 0 | 0 | 0 |
| E-45 | NA | 1 | 0 | 0 | 0 | 0 |
| E-47 | NA | 1 | 0 | 0 | 0 | 0 |
| E-49 | NA | 1 | 0 | 0 | 0 | 0 |
| E-51 | NA | 1 | 0 | 0 | 0 | 0 |
| D-76 | NA | 0 | 0 | 0 | 0 | 0 |
| D-85 | NA | 1 | 0 | 0 | 0 | 0 |
| D-93 | NA | 1 | 0 | 0 | 0 | 0 |
| D-10 | NA | 1 | 0 | 0 | 0 | 0 |
| D-11 | NA | 1 | 0 | 0 | 0 | 0 |
| D-14 | NA | 1 | 0 | 0 | 0 | 0 |
| D-15 | NA | 1 | 0 | 0 | 0 | 0 |
| D-48 | NA | 1 | 0 | 0 | 0 | 0 |
| C-62 | NA | 1 | 0 | 0 | 0 | 0 |
| C-70 | NA | 1 | 0 | 0 | 0 | 0 |
| C-79 | NA | 1 | 0 | 0 | 0 | 0 |
| C-81 | NA | 1 | 0 | 0 | 0 | 0 |
| C-82 | NA | 1 | 0 | 0 | 0 | 0 |
| C-64 | NA | 0 | 0 | 0 | 0 | 0 |
| C-65 | NA | 0 | 0 | 0 | 0 | 0 |
| C-66 | NA | 0 | 0 | 0 | 0 | 0 |
| C-67 | NA | 0 | 0 | 0 | 0 | 0 |
| C-72 | NA | 0 | 0 | 0 | 0 | 0 |
| C-73 | NA | 2 | 0 | 0 | 0 | 0 |
| C-74 | NA | 2 | 0 | 0 | 0 | 0 |
| C-75 | NA | 2 | 0 | 0 | 0 | 0 |
| C-83 | NA | 0 | 0 | 0 | 0 | 0 |
| C-84 | NA | 0 | 0 | 0 | 0 | 0 |
| C-7 | NA | 0 | 0 | 0 | 0 | 0 |
| C-16 | NA | 0 | 0 | 0 | 0 | 0 |
| C-23 | NA | 0 | 0 | 0 | 0 | 0 |
| C-24 | NA | 0 | 0 | 0 | 0 | 0 |
| C-25 | NA | 0 | 0 | 0 | 0 | 0 |
| C-46 | NA | 0 | 0 | 0 | 0 | 0 |
| B-56 | NA | 3 | 0 | 0 | 0 | 0 |
| B-63 | NA | 2 | 0 | 0 | 0 | 0 |
| B-96 | NA | 2 | 0 | 0 | 0 | 0 |
| B-97 | NA | 2 | 0 | 0 | 0 | 0 |
| B-98 | NA | 3 | 0 | 0 | 0 | 0 |
| B-99 | NA | 2 | 0 | 0 | 0 | 0 |
| B-100 | NA | 2 | 0 | 0 | 0 | 0 |
| B-26 | NA | 3 | 0 | 0 | 0 | 0 |
| B-52 | NA | 3 | 0 | 0 | 0 | 0 |
| A-55 | NA | 2 | 0 | 0 | 0 | 0 |
| A-57 | NA | 3 | 0 | 0 | 0 | 0 |
| A-89 | NA | 2 | 0 | 0 | 0 | 0 |
| A-101 | NA | 3 | 0 | 0 | 0 | 0 |
| A-1 | NA | 3 | 0 | 0 | 0 | 0 |
| A-2 | NA | 3 | 0 | 0 | 0 | 0 |
| A-3 | NA | 2 | 0 | 0 | 0 | 0 |
| A-4 | NA | 2 | 0 | 0 | 0 | 0 |
| A-5 | NA | 0 | 0 | 0 | 0 | 0 |
| A-12 | NA | 3 | 0 | 0 | 0 | 0 |
| A-13 | NA | 3 | 0 | 0 | 0 | 0 |
| A-17 | NA | 3 | 0 | 0 | 0 | 0 |
| A-20 | NA | 3 | 0 | 0 | 0 | 0 |
| A-27 | NA | 3 | 0 | 0 | 0 | 0 |
| A-31 | NA | 3 | 0 | 0 | 0 | 0 |
| A-32 | NA | 0 | 0 | 0 | 0 | 0 |
| A-36 | NA | 0 | 0 | 0 | 0 | 0 |
| A-37 | NA | 0 | 0 | 0 | 0 | 0 |
| A-42 | NA | 2 | 0 | 0 | 0 | 0 |
| F-50/53 | NA | 4 | 0 | 0 | 0 | 0 |
| F-60/68 | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 26 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 98 buildings; the table lists the first 20.
0 of 1078 construction stages are filed complete across 98 buildings. The stage furthest along is Installation of Lifts, at 2%.
E-540%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-580%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-590%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-610%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-690%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-710%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-770%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-780%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-800%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-860%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-870%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-880%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-900%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-910%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-920%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-940%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-950%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 2% |
E-60%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E-80%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E-90%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 26 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed67
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| E-54 | 0 | 1 | 1 |
| E-58 | 0 | 1 | 1 |
| E-59 | 0 | 1 | 1 |
| E-61 | 0 | 1 | 1 |
| E-69 | 0 | 1 | 1 |
| E-71 | 0 | 1 | 1 |
| E-77 | 0 | 1 | 1 |
| E-78 | 0 | 1 | 1 |
| E-80 | 0 | 1 | 1 |
| E-86 | 0 | 1 | 1 |
| E-87 | 0 | 1 | 1 |
| E-88 | 0 | 1 | 1 |
| E-90 | 0 | 1 | 1 |
| E-91 | 0 | 1 | 1 |
| E-92 | 0 | 1 | 1 |
| E-94 | 0 | 1 | 1 |
| E-95 | 0 | 1 | 1 |
| E-6 | 0 | 1 | 1 |
| E-8 | 0 | 1 | 1 |
| E-9 | 0 | 1 | 1 |
| E-19 | 0 | 1 | 1 |
| E-18 | 0 | 1 | 1 |
| E-21 | 0 | 1 | 1 |
| E-22 | 0 | 1 | 1 |
| E-28 | 0 | 1 | 1 |
| E-29 | 0 | 1 | 1 |
| E-30 | 0 | 1 | 1 |
| E-33 | 0 | 1 | 1 |
| E-34 | 0 | 1 | 1 |
| E-35 | 0 | 1 | 1 |
| E-38 | 0 | 1 | 1 |
| E-39 | 0 | 1 | 1 |
| E-40 | 0 | 1 | 1 |
| E-43 | 0 | 1 | 1 |
| E-44 | 0 | 1 | 1 |
| E-45 | 0 | 1 | 1 |
| E-47 | 0 | 1 | 1 |
| E-49 | 0 | 1 | 1 |
| E-51 | 0 | 1 | 1 |
| D-85 | 0 | 1 | 1 |
| D-93 | 0 | 1 | 1 |
| D-14 | 0 | 1 | 1 |
| D-15 | 0 | 1 | 1 |
| D-48 | 0 | 1 | 1 |
| C-73 | 0 | 1 | 1 |
| C-74 | 0 | 1 | 1 |
| C-75 | 0 | 1 | 1 |
| B-56 | 1 | 0 | 1 |
| B-98 | 1 | 0 | 1 |
| B-26 | 1 | 0 | 1 |
| B-52 | 1 | 0 | 1 |
| A-57 | 1 | 0 | 1 |
| A-101 | 1 | 0 | 1 |
| A-1 | 1 | 0 | 1 |
| A-2 | 1 | 0 | 1 |
| A-12 | 1 | 0 | 1 |
| A-13 | 1 | 0 | 1 |
| A-17 | 1 | 0 | 1 |
| A-20 | 1 | 0 | 1 |
| A-27 | 1 | 0 | 1 |
| A-31 | 1 | 0 | 1 |
| F-50/53 | 2 | 1 | 3 |
| F-60/68 | 2 | 1 | 3 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| PPROM REALTORS | DOMBIVLI | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | JOSHI SAIGAONKAR ASSOCIATES |
| Engineer | MADHAV CHIKODI AND ASSOCIATES |
| Chartered Accountant | N S Gokhale And Company |
| Partner | Role in project |
|---|---|
| PITAMBARI PRODUCTS PVT LTD | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Jul 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Jul 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Jul 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Jul 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed76
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 July to Sep 2025.pdf | 26 May 2026 |
| Form 2File: Form 2 July to sep 2025.pdf | 26 May 2026 |
| Form 3File: Form 3 July to sept 2025.pdf | 26 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold.pdf | 26 May 2026 |
| Form 1File: Form 1 Oct to dec 2025.pdf | 26 May 2026 |
| Form 2File: Form 2 Oct to dec 2025.pdf | 26 May 2026 |
| Form 3File: Form 3 Oct to Dec 2025.pdf | 26 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold.pdf | 26 May 2026 |
| Form 1File: Form 1.pdf | 14 May 2026 |
| Form 2File: Form 2.pdf | 14 May 2026 |
| Form 3File: Form 3 Indradhanu.pdf | 14 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Indradhanu Sold Unsold inventory for Rera.pdf | 14 May 2026 |
| Form 1File: Form 1.pdf | 18 Feb 2026 |
| Form 2File: Form 2.pdf | 18 Feb 2026 |
| Form 3File: Form 3.pdf | 18 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: disclouser of sold bungalow.pdf | 18 Feb 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Q4-Indradhanu.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate-Rera-Indradhanu-Form 3 New-Mar25 (1).pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Indradhanu March 25.pdf | 5 May 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY -Q4-Indradhanu.pdf | 5 May 2025 |
| Other - TechnicalFile: Indradhanu OC 2 compressed.pdf | 5 May 2025 |
| Other - TechnicalFile: Indradhanu Bunglow OC_compressed.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate-Q3-Indradhanu.pdf | 21 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Indradhanu Form 3-Dec 24.pdf | 21 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Indradhanu 31-12-24 rera.pdf | 21 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: disclosure o sold inventory-Q3-Indradhanu.pdf | 21 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1.pdf | 28 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From 3.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2_compressed.pdf | 28 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of booked inventory.pdf | 28 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold inventory-Indradhanu-Q1 (1).pdf | 6 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf | 23 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_compressed.pdf | 23 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_compressed.pdf | 23 Jul 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: girveance cell draft-indradhanu.pdf | 23 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Point -1-Architect Certificate.pdf | 11 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Point -2 engineers certificate on cost incurred on project -form2_compressed.pdf | 11 May 2024 |
| Disclosure of sold/ booked inventoryFile: Point-6- Disclosure of sold-booked inventory.pdf | 11 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Pitambari.pdf | 11 May 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Point-8-Disclosure of interest in other Real Estate Organization.pdf | 11 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate DEC 2023 realtors.pdf | 31 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Realtors engineer certificate Dec 2023 1.pdf | 31 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pprom RealtorRera Indradhanu Dec23 CA Certificate.pdf | 31 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate SEP 2023.pdf | 26 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Realtors Sept 2023 (1).pdf | 26 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pprom Realtor CA CertificateSept23 (1).pdf | 26 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate June 2023.pdf | 7 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT JUNE 2023.pdf | 7 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificate.pdf | 7 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf | 7 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 7 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 signed.pdf | 7 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 signed.pdf | 7 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 signed.pdf | 7 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 7 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 7 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Form 5 PPPL - March 31 2022 signed print.pdf | 30 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1.pdf | 27 Sep 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 27 Sep 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 27 Sep 2022 |
| Proforma of Allotment letterFile: Draft Agreement for Sale and Allotment Letter-24 6 2022.pdf | 24 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD - UNSOLD INVENTORY.PDF | 16 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5-Signed-Final.pdf | 14 Mar 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate.pdf | 14 Aug 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate.pdf | 14 Aug 2021 |
| Proforma of Allotment letterFile: Agreement for Sale and Allotment Letter.pdf | 28 Nov 2020 |
| PAN CardFile: pppl pancard.pdf | 27 Nov 2020 |
| Details of encumbrancesFile: Letter - Encumbrance.pdf | 27 Nov 2020 |
| Declaration in FORM BFile: Form B.pdf | 27 Nov 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 27 Nov 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: pitambari prant office permission_compressed.pdf | 14 Jul 2020 |
| Layout approvalFile: Complete Project Structure - Bungalow Project - Dapoli.pdf | 13 Jul 2020 |
| Building plan approvalFile: combinepdf.pdf | 13 Jul 2020 |
| Copy of the legal title reportFile: pitambari sakhaloli search Marathi Consolidated.pdf | 13 Jul 2020 |
| Copy of Layout Approval (in case of layout)File: Complete Project Structure - Bungalow Project - Dapoli.pdf | 13 Jul 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: combinepdf.pdf | 13 Jul 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ratnagiri
Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- All 76 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PITAMBARI INDRADHANU VILLAGE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Sakhroli1,100+ in Ratnagiri
KONKAN TRAILS LIFESPACE
KONKANTRAILSLIFESPACELLP
Cape of Bliss Phase 1A
HOABL Management LLP
VIAA VISION
VIAA VISION
COASTAL BREEZE
UNIVERSAL PROPERTIES
VRUNDAVAN
EMPIRE REALTORS AND DEVELOPERS
Cape of Bliss Phase I
Lodha Management LLP
See every Ratnagiri project, with the district possession charts
Builder: PITAMBARI PRODUCTS PVT LTD
PITAMBARI PRODUCTS PVT LTD has 1 registration on MahaRERA, including PITAMBARI INDRADHANU VILLAGE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.
Frequently asked questions
What are my rights if PITAMBARI INDRADHANU VILLAGE is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PITAMBARI INDRADHANU VILLAGE?
The registered promoter entity is PITAMBARI PRODUCTS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PITAMBARI INDRADHANU VILLAGE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PITAMBARI INDRADHANU VILLAGE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PITAMBARI INDRADHANU VILLAGE?
The professionals named in the filing: Architect: JOSHI SAIGAONKAR ASSOCIATES; Engineer: MADHAV CHIKODI AND ASSOCIATES; Chartered Accountant: N S Gokhale And Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PITAMBARI INDRADHANU VILLAGE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback