Home / Browse projects / Jalna, Maharashtra / PC RESIDENCY PRIDE
PC RESIDENCY PRIDE
RG-MH-46077 · RERA P51400045717 · Last updated on MahaRERA portal: 15 Dec 2022
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Jalna registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PC RESIDENCY PRIDE is a Others project by SHUBHAM SURENDRA CHECHANI in Jalna, Maharashtra, registered with MahaRERA as P51400045717 on 6 Jun 2022. The registration is recorded completed; possession was promised by 1 May 2024.
At a glance
Project
- NamePC RESIDENCY PRIDE
- TypeOthers
- Location
- RAJUR ROAD
- JALNA
- Jalna (M Cl)
- 431203
- Pincode431203
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51400045717
- ReraGenie IDRG-MH-46077
Builder
- NameSHUBHAM SURENDRA CHECHANI
- Entity typeIndividual
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on6 Jun 2022
- Promised completion1 May 2024
- Revised completionNone
- Buildings1 building record
- Documents filed14 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PC RESIDENCY PRIDE | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Dec 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
PC RESIDENCY PRIDE: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 15 Dec 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MRS NEHA SHUBHAM CHECHANI | Jalna (M Cl) | Jalna |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRITAM KANDI |
| Architect | PRATAP GHAVANE |
| Architect | rupesh raiphale |
| Engineer | NEHA THAKUR |
| Engineer | VIJAYA PAWAR |
| Chartered Accountant | HARSHIT KABRA |
| Partner | Role in project |
|---|---|
| SHUBHAM SURENDRA CHECHANI | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 Dec 2022
Documents filed14
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: letter.pdf | 15 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca (1).pdf | 25 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 20220520173531-compressed.pdf | 20 May 2022 |
| Building plan approvalFile: 1 (1).pdf | 16 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 (1).pdf | 16 May 2022 |
| Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf | 9 May 2022 |
| Copy of the legal title reportFile: SHUBHAM CHECHANI.pdf | 9 May 2022 |
| Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf | 9 May 2022 |
| Declaration in FORM BFile: 1 Declaration in FORM B (1).pdf | 9 May 2022 |
| Declaration about Commencement CertificateFile: chechani certificate-converted.pdf | 31 Mar 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200235199364_For_Asset_Based_Search_15_04_2022_20_33_38_809_removed_r | 31 Mar 2022 |
| Proforma of Allotment letterFile: Registry Jalna.pdf | 31 Mar 2022 |
| PAN CardFile: PAN CARD.pdf | 25 Mar 2022 |
| Details of encumbrancesFile: ENCUMBRANCE.pdf | 25 Mar 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| RAJ PARK | NANDED | 5 | Completed | Jul 2014 | Late, Jan 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Jalna
Computed across the 100+ Jalna projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 14 filed documents as one ZIP, foldered, with a manifest
Keep PC RESIDENCY PRIDE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near JALNA100+ in Jalna
Filed coordinates, straight-line distance. 10 registered projects within 2 km.
VITTHALA TOWERS
TIRUPATI BUILDCON
SHREE SAI CITY PHASE-I
SHREE SAI CITY BUILDERS AND DEVELOPERS
JINDAL GOYAL SQUARE
JINDAL GOYAL REALITY LLP
Krishna Capital
Krishna Capital
Lalbag, Plotting
GO Developers LLP
RUKHMINI HEIGHTS
TIRUPATI INFRA JALNA
See every Jalna project, with the district possession charts
Builder: SHUBHAM SURENDRA CHECHANI
SHUBHAM SURENDRA CHECHANI has 1 registration on MahaRERA, including PC RESIDENCY PRIDE. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Jalna district page.
Frequently asked questions
What are my rights if PC RESIDENCY PRIDE is delayed beyond 1 May 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PC RESIDENCY PRIDE?
The registered promoter entity is SHUBHAM SURENDRA CHECHANI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PC RESIDENCY PRIDE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PC RESIDENCY PRIDE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PC RESIDENCY PRIDE?
The professionals named in the filing: Architect: PRITAM KANDI; Architect: PRATAP GHAVANE; Architect: rupesh raiphale; Engineer: NEHA THAKUR; Engineer: VIJAYA PAWAR; Chartered Accountant: HARSHIT KABRA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PC RESIDENCY PRIDE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.