Home / Browse projects / Pune, Maharashtra / PAWAR RISEONIC

Registered No litigation declared Others project

PAWAR RISEONIC

By PAWAR BUILDCON AND COMPANY

RG-MH-22432 · RERA P52100031525 · Last updated on MahaRERA portal: 9 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 33 months
  • 1 extension taken
  • Rs 39.00 crore secured on the land, in favour of Aditya Birla Capital Limited, Hero Fincorp Limited

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedmoved 33 months from the original
16 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 77%
62 of 128Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 142 documents Report an error

PAWAR RISEONIC is a Others project by PAWAR BUILDCON AND COMPANY in Pune, Maharashtra, registered with MahaRERA as P52100031525 on 25 Oct 2021. Possession is promised by 30 Jul 2027. The completion date has moved by 33 months from the original filing. 66 of the 128 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete.

At a glance

Project

  • NamePAWAR RISEONIC
  • TypeOthers
  • Location
    • magar patta road
    • kirtne baug
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411036
  • Pincode411036
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100031525
  • ReraGenie IDRG-MH-22432

Builder

  • NamePAWAR BUILDCON AND COMPANY
  • Entity typePartnership
  • GSTIN27AAVFP5071D1ZX
  • Partnershiva s teerth
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2021First promiseOct 2024Revised toJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Oct 2021
  • Promised completion30 Jul 2027
  • Revised completionRevised to 30 Jul 2027 (originally 31 Oct 2024)
  • Buildings2 building records
  • Documents filed142 files

Current status

52%66 of 128 units booked
67.7%Work done, per cost certificate

Figures as on 9 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA1715602080
B WINGNA171248048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 77%.

A WING62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure77%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed235

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots235
Closed/Covered235
BuildingClosed/CoveredTotal
A WING111111
B WING124124

Land and ownership14

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,986 sq m
Land owned byNot the promoter
Named landowners14
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Capital Limited, Hero Fincorp Limited
Secured amountRs 39.00 crore
Declared on21 Nov 2025
LandownerVillageDistrict
SHRI PAPANNA SAYANNA CONTROLLUMundhawaPune
ATUL PAPANNA CONTROLLUGhorpadiPune
SANJEEVANI DEEPAK KULASKARGhorpadiPune
VILAS KUSHABA RASKARMundhawaPune
KANTA VILAS RASKARMundhawaPune
YOGESH VILAS RASKARMundhawaPune
SNEHAL VILAS RASKARMundhawaPune
MS BHATI BROTHERSPune (M Corp.)Pune
ANIL NAMDEO DALVIFursungiPune
DHANASHREE ANNASAHEB TAPREPune (M Corp.)Pune
SONAL SHIVSHANT KHOSEJamkhed (CT)Ahmednagar
SMITA ULHAAS BODKEKeshavnagar-MundwaPune
BHAGYASHREE RAJENDRA BODKEKeshavnagar-MundwaPune
SUVARNA GULAAB BURADEMundhawaPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI12183.04
Proposed, not sanctioned12,183 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAXMI ARCADE,BT KAWADE ROAD, GHORPADI, PUNE - 411001
Estimated costRs 51.69 cr
Cost incurredRs 35.01 cr
Work done67.73%
BuildingWingEstimatedIncurred
A WINGNARs 27.60 crRs 13.22 cr
B WINGNARs 20.00 crRs 20.00 cr
-NARs 4.09 crRs 1.79 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPARVEJ JAMADAR & ASSOCIATES
EngineerRahul S Biradar
EngineerRohit
EngineerVaibhav Suresh Ghorpade
EngineerAmar Birajdar
Chartered AccountantRAMAWATAR S LADDAD & ASSOCIATES
Chartered AccountantBANGAD AND ASSOCIATES
Chartered AccountantCSSP & Associates
PartnerRole in project
PAWAR BUILDCON AND COMPANY-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024669Oct 2024 → Jul 2027

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, and coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress while taking all necessary steps to ensure timely completion. Please note that the previously kept completion date was for Building B, for which we had applied for part of the Occupancy Certificate (OC). The new completion date is for Building A, and

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jul 2027

Documents filed142

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 142 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A - Pawar Riseonic - FY 2025-26.pdf9 Jul 2026
Layout approvalFile: Page 1 - Highlighted (Parking) (Permissible and Sanctioned).pdf9 May 2026
Building plan approvalFile: Page 2 - Basement Plan.pdf9 May 2026
Building plan approvalFile: Page 3 - Lower Ground Plan.pdf9 May 2026
Building plan approvalFile: Page 4 - Upper Ground Plan.pdf9 May 2026
Building plan approvalFile: Page 5 - Mezz FLoor Plan.pdf9 May 2026
Building plan approvalFile: Page 6 - Podium Floor Plan.pdf9 May 2026
Building plan approvalFile: Page 7 - 1st and 2nd Floor Plans.pdf9 May 2026
Building plan approvalFile: Page 8 - 3rd and 4th Floors Plans.pdf9 May 2026
Building plan approvalFile: Page 9 - Typical and Refuge Floors Plans.pdf9 May 2026
Building plan approvalFile: Page 10.pdf9 May 2026
Building plan approvalFile: Page 11 - Elevation.pdf9 May 2026
Building plan approvalFile: Page 12 - Elevation.pdf9 May 2026
Building plan approvalFile: Page 13 - Elevation.pdf9 May 2026
Withdrawal Update Form 1File: Form 1 - Pawar Riseonic as on March 2026.pdf8 May 2026
Withdrawal Update Form 2File: Form 2 - Pawar Riseonic as on March 2026.pdf8 May 2026
Withdrawal Update Form 3File: Form 3 - Pawar Riseonic as on March 2026.pdf8 May 2026
Form 5 (FY 2024-2025)File: Form 5 - Pawar Riseonic fy 2024-25 (Signed).pdf9 Mar 2026
Withdrawal Update Form 1File: Form 1 - Pawar Riseonic as on Dec 2025.pdf21 Feb 2026
Withdrawal Update Form 2File: Form 2 - Pawar Riseonic as on Dec 2025.pdf21 Feb 2026
Withdrawal Update Form 3File: Form 3 - Pawar Riseonic as on Dec 2025.pdf21 Feb 2026
Withdrawal Update Form 1File: Form 1 - Pawar Riseonic as on Sep 2025.pdf26 Nov 2025
Withdrawal Update Form 2File: Form 2 - Pawar Riseonic as on Sep 2025.pdf26 Nov 2025
Withdrawal Update Form 3File: Form 3 - Pawar Riseonic as on Sep 2025-.pdf26 Nov 2025
Form 2A (FY 2024-2025)File: Form 2A - Pawar Riseonic - FY 2024-25.pdf10 Oct 2025
Withdrawal Update Form 1File: Form 1 - Pawar Riseonic as on June 2025.pdf22 Sep 2025
Withdrawal Update Form 2File: Form 2 - Pawar Riseonic as on June 2025.pdf22 Sep 2025
Withdrawal Update Form 3File: Form 3 - June 2025.pdf22 Sep 2025
Form 1File: Form 1 - Pawar Riseonic as on March 2025.pdf12 Sep 2025
Form 2File: Form 2 - Pawar Riseonic as on March 2025.pdf12 Sep 2025
Form 3File: Form 3 - Pawar Riseonic as on March 2025.pdf12 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Pawar Riseonic as on March 2025.pdf12 Sep 2025
Form 1File: Form 1-Pawar Riseonic as on June 2025.pdf8 Sep 2025
Form 2File: Form 2 -Pawar Riseonic as on June 2025.pdf8 Sep 2025
Form 3File: Form 3 -Pawar Riseonic as on June 2025.pdf8 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Pawar Riseonic as on June 2025.pdf8 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Pawar Riseonic as on December 2024.pdf9 Jan 2025
Layout approvalFile: 01_11zon.pdf8 Jan 2025
Building plan approvalFile: 02_11zon.pdf8 Jan 2025
Building plan approvalFile: 03_11zon.pdf8 Jan 2025
Building plan approvalFile: 04_11zon.pdf8 Jan 2025
Building plan approvalFile: 05_11zon.pdf8 Jan 2025
Building plan approvalFile: 06_11zon.pdf8 Jan 2025
Building plan approvalFile: 07_11zon.pdf8 Jan 2025
Building plan approvalFile: 08_11zon.pdf8 Jan 2025
Building plan approvalFile: 09_11zon.pdf8 Jan 2025
Building plan approvalFile: 10_11zon.pdf8 Jan 2025
Building plan approvalFile: 11_11zon.pdf8 Jan 2025
Building plan approvalFile: 12_11zon.pdf8 Jan 2025
Building plan approvalFile: 13_11zon.pdf8 Jan 2025
Building plan approvalFile: 14_11zon.pdf8 Jan 2025
Copy of Layout Approval (in case of layout)File: 01_11zon.pdf8 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Pawar Riseonic as on December 2024.pdf8 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Pawar Riseonic as on December 2024.pdf8 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 07_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 14_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 13_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 12_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 11_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 10_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 09_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 08_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 06_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 05_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 04_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 03_11zon.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 02_11zon.pdf8 Jan 2025
Disclosure of sold/ booked inventoryFile: Circular 29 - Pawar Riseonic as on Dec 2024.pdf6 Jan 2025
Declaration in FORM BFile: notarized formB .pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_CA Certificate_30092024_Signed (1)_11zon.pdf9 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 11nov2024.pdf9 Dec 2024
Disclosure of sold/ booked inventoryFile: sold_unsold 15nov2024.pdf9 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 11nov2024.pdf5 Dec 2024
CERSAI detailsFile: CERSAI_Search_Report_200321742633_For_Debtor_Based_Search_24_09_2024_14_10_35_618.pdf5 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf4 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sr44 form1 9oct 2024 revised.pdf8 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form5 22-23.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5 23-24 (1).pdf21 Oct 2024
Declaration in FORM BFile: form b for extension.pdf18 Oct 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
CAPRIVILLAB T KAWADE ROAD23CompletedJun 2015May 2015

How this compares with Pune

52%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 33 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PAWAR RISEONIC on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near kirtne baug13,700+ in Pune

2 kmPAWAR RISEONICCompleted 84Lapsed / revoked 23Other 98Dot size: filed unitsN

Filed coordinates, straight-line distance. 205 registered projects within 2 km.

Builder: PAWAR BUILDCON AND COMPANY

PAWAR BUILDCON AND COMPANY has 1 registration on MahaRERA, including PAWAR RISEONIC. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PAWAR RISEONIC is delayed beyond 30 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PAWAR RISEONIC?

The registered promoter entity is PAWAR BUILDCON AND COMPANY, a partnership as per the filing. Its GSTIN 27AAVFP5071D1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PAWAR RISEONIC?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PAWAR RISEONIC?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PAWAR RISEONIC?

The professionals named in the filing: Architect: PARVEJ JAMADAR & ASSOCIATES; Engineer: Rahul S Biradar; Engineer: Rohit; Engineer: Vaibhav Suresh Ghorpade; Engineer: Amar Birajdar; Chartered Accountant: RAMAWATAR S LADDAD & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PAWAR RISEONIC?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PAWAR RISEONIC. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PAWAR RISEONIC to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.