PAWAR RISEONIC
RG-MH-22432 · RERA P52100031525 · Last updated on MahaRERA portal: 9 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 33 months
- 1 extension taken
- Rs 39.00 crore secured on the land, in favour of Aditya Birla Capital Limited, Hero Fincorp Limited
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PAWAR RISEONIC is a Others project by PAWAR BUILDCON AND COMPANY in Pune, Maharashtra, registered with MahaRERA as P52100031525 on 25 Oct 2021. Possession is promised by 30 Jul 2027. The completion date has moved by 33 months from the original filing. 66 of the 128 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete.
At a glance
Project
- NamePAWAR RISEONIC
- TypeOthers
- Location
- magar patta road
- kirtne baug
- Pune (M Corp.)
- Pune City
- Pune
- 411036
- Pincode411036
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100031525
- ReraGenie IDRG-MH-22432
Builder
- NamePAWAR BUILDCON AND COMPANY
- Entity typePartnership
- GSTIN27AAVFP5071D1ZX
- Partnershiva s teerth
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Oct 2021
- Promised completion30 Jul 2027
- Revised completionRevised to 30 Jul 2027 (originally 31 Oct 2024)
- Buildings2 building records
- Documents filed142 files
Current status
Figures as on 9 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 17 | 15 | 60 | 20 | 80 |
| B WING | NA | 17 | 12 | 48 | 0 | 48 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 77%.
A WING62%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 77% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | Yes | 70% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed235
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A WING | 111 | 111 |
| B WING | 124 | 124 |
Land and ownership14
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| SHRI PAPANNA SAYANNA CONTROLLU | Mundhawa | Pune |
| ATUL PAPANNA CONTROLLU | Ghorpadi | Pune |
| SANJEEVANI DEEPAK KULASKAR | Ghorpadi | Pune |
| VILAS KUSHABA RASKAR | Mundhawa | Pune |
| KANTA VILAS RASKAR | Mundhawa | Pune |
| YOGESH VILAS RASKAR | Mundhawa | Pune |
| SNEHAL VILAS RASKAR | Mundhawa | Pune |
| MS BHATI BROTHERS | Pune (M Corp.) | Pune |
| ANIL NAMDEO DALVI | Fursungi | Pune |
| DHANASHREE ANNASAHEB TAPRE | Pune (M Corp.) | Pune |
| SONAL SHIVSHANT KHOSE | Jamkhed (CT) | Ahmednagar |
| SMITA ULHAAS BODKE | Keshavnagar-Mundwa | Pune |
| BHAGYASHREE RAJENDRA BODKE | Keshavnagar-Mundwa | Pune |
| SUVARNA GULAAB BURADE | Mundhawa | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A WING | NA | Rs 27.60 cr | Rs 13.22 cr |
| B WING | NA | Rs 20.00 cr | Rs 20.00 cr |
| - | NA | Rs 4.09 cr | Rs 1.79 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PARVEJ JAMADAR & ASSOCIATES |
| Engineer | Rahul S Biradar |
| Engineer | Rohit |
| Engineer | Vaibhav Suresh Ghorpade |
| Engineer | Amar Birajdar |
| Chartered Accountant | RAMAWATAR S LADDAD & ASSOCIATES |
| Chartered Accountant | BANGAD AND ASSOCIATES |
| Chartered Accountant | CSSP & Associates |
| Partner | Role in project |
|---|---|
| PAWAR BUILDCON AND COMPANY | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, and coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress while taking all necessary steps to ensure timely completion. Please note that the previously kept completion date was for Building B, for which we had applied for part of the Occupancy Certificate (OC). The new completion date is for Building A, and
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Oct 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 May 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 May 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jul 2027
Documents filed142
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 142 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A - Pawar Riseonic - FY 2025-26.pdf | 9 Jul 2026 |
| Layout approvalFile: Page 1 - Highlighted (Parking) (Permissible and Sanctioned).pdf | 9 May 2026 |
| Building plan approvalFile: Page 2 - Basement Plan.pdf | 9 May 2026 |
| Building plan approvalFile: Page 3 - Lower Ground Plan.pdf | 9 May 2026 |
| Building plan approvalFile: Page 4 - Upper Ground Plan.pdf | 9 May 2026 |
| Building plan approvalFile: Page 5 - Mezz FLoor Plan.pdf | 9 May 2026 |
| Building plan approvalFile: Page 6 - Podium Floor Plan.pdf | 9 May 2026 |
| Building plan approvalFile: Page 7 - 1st and 2nd Floor Plans.pdf | 9 May 2026 |
| Building plan approvalFile: Page 8 - 3rd and 4th Floors Plans.pdf | 9 May 2026 |
| Building plan approvalFile: Page 9 - Typical and Refuge Floors Plans.pdf | 9 May 2026 |
| Building plan approvalFile: Page 10.pdf | 9 May 2026 |
| Building plan approvalFile: Page 11 - Elevation.pdf | 9 May 2026 |
| Building plan approvalFile: Page 12 - Elevation.pdf | 9 May 2026 |
| Building plan approvalFile: Page 13 - Elevation.pdf | 9 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Pawar Riseonic as on March 2026.pdf | 8 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Pawar Riseonic as on March 2026.pdf | 8 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Pawar Riseonic as on March 2026.pdf | 8 May 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - Pawar Riseonic fy 2024-25 (Signed).pdf | 9 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 - Pawar Riseonic as on Dec 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 - Pawar Riseonic as on Dec 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 - Pawar Riseonic as on Dec 2025.pdf | 21 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 - Pawar Riseonic as on Sep 2025.pdf | 26 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 - Pawar Riseonic as on Sep 2025.pdf | 26 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 - Pawar Riseonic as on Sep 2025-.pdf | 26 Nov 2025 |
| Form 2A (FY 2024-2025)File: Form 2A - Pawar Riseonic - FY 2024-25.pdf | 10 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 - Pawar Riseonic as on June 2025.pdf | 22 Sep 2025 |
| Withdrawal Update Form 2File: Form 2 - Pawar Riseonic as on June 2025.pdf | 22 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 - June 2025.pdf | 22 Sep 2025 |
| Form 1File: Form 1 - Pawar Riseonic as on March 2025.pdf | 12 Sep 2025 |
| Form 2File: Form 2 - Pawar Riseonic as on March 2025.pdf | 12 Sep 2025 |
| Form 3File: Form 3 - Pawar Riseonic as on March 2025.pdf | 12 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Pawar Riseonic as on March 2025.pdf | 12 Sep 2025 |
| Form 1File: Form 1-Pawar Riseonic as on June 2025.pdf | 8 Sep 2025 |
| Form 2File: Form 2 -Pawar Riseonic as on June 2025.pdf | 8 Sep 2025 |
| Form 3File: Form 3 -Pawar Riseonic as on June 2025.pdf | 8 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - Pawar Riseonic as on June 2025.pdf | 8 Sep 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Pawar Riseonic as on December 2024.pdf | 9 Jan 2025 |
| Layout approvalFile: 01_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 02_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 03_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 04_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 05_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 06_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 07_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 08_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 09_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 10_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 11_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 12_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 13_11zon.pdf | 8 Jan 2025 |
| Building plan approvalFile: 14_11zon.pdf | 8 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: 01_11zon.pdf | 8 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Pawar Riseonic as on December 2024.pdf | 8 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Pawar Riseonic as on December 2024.pdf | 8 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 07_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 14_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 13_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 12_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 11_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 10_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 09_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 08_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 06_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 05_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 04_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 03_11zon.pdf | 8 Jan 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 02_11zon.pdf | 8 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29 - Pawar Riseonic as on Dec 2024.pdf | 6 Jan 2025 |
| Declaration in FORM BFile: notarized formB .pdf | 9 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_CA Certificate_30092024_Signed (1)_11zon.pdf | 9 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 11nov2024.pdf | 9 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: sold_unsold 15nov2024.pdf | 9 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 11nov2024.pdf | 5 Dec 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200321742633_For_Debtor_Based_Search_24_09_2024_14_10_35_618.pdf | 5 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 4 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sr44 form1 9oct 2024 revised.pdf | 8 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form5 22-23.pdf | 21 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5 23-24 (1).pdf | 21 Oct 2024 |
| Declaration in FORM BFile: form b for extension.pdf | 18 Oct 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| CAPRIVILLA | B T KAWADE ROAD | 23 | Completed | Jun 2015 | May 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 142 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PAWAR RISEONIC on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near kirtne baug13,700+ in Pune
Filed coordinates, straight-line distance. 205 registered projects within 2 km.
Godrej Aqua Vista
Oxford Realty LLP
Godrej Elaris
Godrej Properties Limited
Sukhwani Hermosa Casa
Sukhwani Associates
Basil Mondale
velx constructions llp
TREMONT D, E AND F WINGS
The Excellaa
ATELIER GREENS
ESTEEM CONSTRUCTIONS PRIVATE LIMITED (ADAN
Builder: PAWAR BUILDCON AND COMPANY
PAWAR BUILDCON AND COMPANY has 1 registration on MahaRERA, including PAWAR RISEONIC. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if PAWAR RISEONIC is delayed beyond 30 Jul 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PAWAR RISEONIC?
The registered promoter entity is PAWAR BUILDCON AND COMPANY, a partnership as per the filing. Its GSTIN 27AAVFP5071D1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PAWAR RISEONIC?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PAWAR RISEONIC?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PAWAR RISEONIC?
The professionals named in the filing: Architect: PARVEJ JAMADAR & ASSOCIATES; Engineer: Rahul S Biradar; Engineer: Rohit; Engineer: Vaibhav Suresh Ghorpade; Engineer: Amar Birajdar; Chartered Accountant: RAMAWATAR S LADDAD & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PAWAR RISEONIC?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback