ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / Patel palms

Registration lapsed No litigation declared Residential / Group Housing project

Patel palms

By ABDUL SAMI PATEL

RG-MH-01479 · RERA P51500008294 · Last updated on MahaRERA portal: 29 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Completion date moved by 57 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
30 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 0%
41 of 53Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

Patel palms is a Residential / Group Housing project by ABDUL SAMI PATEL in Aurangabad, Maharashtra, registered with MahaRERA as P51500008294 on 18 Aug 2017. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 57 months from the original filing. 12 of the 53 units on this registration are recorded sold or booked, and 30 of 44 construction stages are filed complete.

At a glance

Project

  • NamePatel palms
  • TypeResidential / Group Housing
  • Location
    • 306/02
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500008294
  • ReraGenie IDRG-MH-01479

Builder

  • NameABDUL SAMI PATEL
  • Entity typeIndividual

Key dates

13 months past promisethis monthRegisteredAug 2017First promiseDec 2020Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 30 Dec 2020)
  • Buildings4 building records
  • Documents filed77 files

Current status

23%12 of 53 units booked

Figures as on 29 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1-A8NA22808
A9-A13NA30505
Apartment ANA6020020
Apartment BNA6020020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 29 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.

A1-A891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A9-A130%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Apartment A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Apartment B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed53

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots53
Closed/Covered16
Open Space37
BuildingClosed/CoveredOpen SpaceTotal
A1-A8088
A9-A13055
Apartment A81220
Apartment B81220

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,900 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Sayyed Shahed Syed Abdul HameedAurangabad (M Corp.)Aurangabad
Syeda Sajeda Syed ShahedAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityAurangabad Municipal Corporation
Permissible FSI2917.2
Proposed, not sanctioned2,917 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchhimayat baugh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectlODHI Sajjad
EngineerICON Consultants
Chartered AccountantYASH NAGAR
PartnerRole in project
ABDUL SAMI PATEL-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500011700Dec 2020 → Mar 2025

Reason as filed by the promoterLack of Demand and Change by Authority Order.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 2025-26 Q2.pdf29 May 2026
Form 2File: Form 2 2025-26 Q2.pdf29 May 2026
Form 3File: Form 3 2025-26 Q2.pdf29 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory- Patel Palms.pdf29 May 2026
Form 1File: FORM 1-2025-26-Q1 Patel Palms.pdf11 Aug 2025
Form 2File: FORM 2 -2025-26-Q1 Patel Palms.pdf11 Aug 2025
Form 3File: FORM 3-2025-26-Q1 Patel Palms.pdf11 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory- Patel Palms.pdf11 Aug 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2024-25 Q4.pdf26 Apr 2025
Certificates of CA (Form 3)File: Form 3 2024-25 Q4.pdf26 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2024-25 Q7.pdf26 Apr 2025
Certificates of CA (Form 3)File: patel palm form 3 Q2.pdf22 Feb 2025
Certificates of CA (Form 3)File: patel palm form 3 q3.pdf22 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: patel palm 30-09 form 1.pdf21 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: patel palm form 1 31-12.pdf21 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: patel palm 30-09 form 2.pdf21 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: patel palms form 2 31-12.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: patel palm 30-09-24 Q2.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: patel palm 31-12-24 Q3.pdf21 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2024-25 Q1.pdf20 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2024-25 Q1.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold unsold 2024-25 Q1.pdf20 Jul 2024
Certificates of CA (Form 3)File: Form 3 2024-25 Q1_ (2).pdf20 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2023-24 Q4.pdf10 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2023-24 Q4.pdf10 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold - booked inventory.pdf10 Jul 2024
Certificates of CA (Form 3)File: Form 3 2023-24 Q4_.pdf10 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 22-23.pdf16 Mar 2024
Certificates of CA (Form 3)File: Form 3_31-12-2023.pdf7 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf6 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf6 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf6 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1.pdf10 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1.pdf10 Feb 2024
Disclosure of sold/ booked inventoryFile: 1.pdf10 Feb 2024
Certificates of CA (Form 3)File: Form 3 Patel Palms upload.pdf11 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf21 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_page-0001 (1).pdf21 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 22-23.pdf21 Dec 2023
Disclosure of sold/ booked inventoryFile: 1.pdf21 Dec 2023
Details of encumbrances concerned to FinanceFile: ilovepdf_merged.pdf10 Mar 2023
Details of encumbrances concerned to FinanceFile: ilovepdf_merged.pdf10 Mar 2023
Details of encumbrances concerned to LegalFile: ilovepdf_merged.pdf10 Mar 2023
Details of encumbrances concerned to LegalFile: ilovepdf_merged.pdf10 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert_compressed.pdf10 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Cert.pdf10 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY CERT .pdf10 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ilovepdf_merged (1).pdf10 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf10 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seprate Bank Declaration.pdf10 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation for allotment letter.pdf10 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement to sale.pdf10 Mar 2023
Declaration about Commencement CertificateFile: Declaration of Commencement Cert.pdf24 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A19-20.pdf24 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 20-21.pdf24 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert_compressed.pdf23 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cert_compressed.pdf23 Mar 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_compressed.pdf23 Mar 2022
CERSAI detailsFile: CERSAI REPORT.pdf23 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Audit Report 19-20.pdf23 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Audit Report 20-21_compressed.pdf23 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Audit Report 2017-18.pdf16 Oct 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Audit Report 2018-19.pdf16 Oct 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf7 Apr 2018
Building plan approvalFile: Patel Builders_Layout_Building Approval.pdf31 Jul 2017
Layout approvalFile: Patel Builders_Layout_Building Approval.pdf31 Jul 2017
Details of encumbrancesFile: Declaration_for_Encumbrances_format.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Patel Builders_Layout_Building Approval.pdf31 Jul 2017
Building Plan Approval (IOD)File: Patel Builders_Layout_Building Approval.pdf31 Jul 2017
Declaration in FORM BFile: Form B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate_opt.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CCI_000015.pdf31 Jul 2017
Certificates of CA (Form 3)File: Patel.pdf31 Jul 2017
Proforma of Allotment letterFile: proforma_allotment_letter.pdf31 Jul 2017
Proforma of Allotment letterFile: RERA_Agreement_for_Sale_Format.pdf31 Jul 2017
PAN CardFile: pan card.pdf30 Jul 2017
Copy of the legal title reportFile: title report.pdf30 Jul 2017

How this compares with Aurangabad

23%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 57 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Patel palms on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Aurangabad (M Corp.)1,400+ in Aurangabad

Builder: ABDUL SAMI PATEL

ABDUL SAMI PATEL has 1 registration on MahaRERA, including Patel palms. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that Patel palms shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Patel palms is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Patel palms?

The registered promoter entity is ABDUL SAMI PATEL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Patel palms?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Patel palms?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Patel palms?

The professionals named in the filing: Architect: lODHI Sajjad; Engineer: ICON Consultants; Chartered Accountant: YASH NAGAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Patel palms?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Patel palms. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Patel palms to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.