Home / Browse projects / Thane, Maharashtra / Patel Mount

Registered No litigation declared Others project

Patel Mount

By Patel Group & Co

RG-MH-85529 · RERA P51700048299 · Last updated on MahaRERA portal: 26 Jul 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 30 months from the original
0 of 11Construction stages donefurthest along: Excavation, 95%
55 of 81Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

Patel Mount is a Others project by Patel Group & Co in Thane, Maharashtra, registered with MahaRERA as P51700048299 on 26 Dec 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 30 months from the original filing. 26 of the 81 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePatel Mount
  • TypeOthers
  • Location
    • Opposite Birla College
    • Chikanghar
    • Kalyan West
    • Chikanghar
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700048299
  • ReraGenie IDRG-MH-85529

Builder

  • NamePatel Group & Co
  • Entity typePartnership
  • PartnersRittu Balkrishna Wasnik, Hasmukh Govindbhai Patel
  • Other registrations3 more →
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2022First promiseJun 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Dec 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed48 files

Current status

32%26 of 81 units booked

Figures as on 26 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building B1NA1111691281

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 95%.

Building B1: 49% average across the applicable activities

ActivityProgress
Excavation95%
Basement (if any)95%
Podiums (if any)0%
Plinth95%
Stilt Floor60%
Slabs of Super Structure62%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks62%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 26 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed120

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots120
Closed/Covered120

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area651 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jun 2025
LandownerVillageDistrict
LIG-1 Kokan Vasahat CHS LTDChikangharThane

Approvals and building plan

Sanctioning authorityKalyan Dombivali Municipal Corporation
Permissible FSI10101.12
Proposed, not sanctioned4,699 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKalyan West

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDesign Consortium
EngineerNadeem Shaikh
EngineerAkash Kumar Singh
Chartered AccountantSTP & Associates
Chartered AccountantPratiksha Tulshyan &Associates
Chartered AccountantCA Rutuja Narsingh & Associates
PartnerRole in project
Patel Group & Co-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700024054Jun 2024 → Jun 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

EA02072501927Jun 2024 → Dec 2026

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2026

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12503513Pritesh BuradPatel Group & Co01/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1) (7).pdf26 Jul 2025
Form 2File: Revised Form 2 - Patel Mount as on March 2025.pdf26 Jul 2025
Form 3File: Revised Form 3 - Patel Mount as on March, 25-Final_11zon.pdf26 Jul 2025
Disclosure of Sold and Booked InventoryFile: CIRCULAR 29 (13) (1).pdf26 Jul 2025
Declaration in FORM BFile: FORM -B Affidavit Cum Declaration 02-07-2024.pdf6 Jul 2024
Declaration about Commencement CertificateFile: FORMAT D (32).pdf5 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 02 ARCHITECTS CERTFICATE FORM I.pdf5 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTFICATE FORM I.pdf5 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Patel Mount- March24.pdf5 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf5 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf5 Jul 2024
Disclosure of sold/ booked inventoryFile: CIRCULAR 29- Patel Mount.pdf5 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Patel Mount- March24_11zon.pdf5 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Format N.pdf5 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Patel Mount FY 22-23.pdf5 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Patel Mount FY 23-24.pdf5 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: GetUserDocumentFileContent (1).pdf20 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Patel MOunt.pdf8 Dec 2022
Other - TechnicalFile: 1 Other - Legal (3).pdf8 Dec 2022
Other - TechnicalFile: Site Photos Patel Mount.pdf8 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Patel Mount (1).pdf5 Dec 2022
Other - LegalFile: CC - Patel.pdf3 Dec 2022
Layout approvalFile: copy Layout - Patel_11zon.pdf1 Dec 2022
Building plan approvalFile: Plan Page 1 B1 - Patel Mount_11zon.pdf1 Dec 2022
Building plan approvalFile: Plan Page 2 B1 - Patel Mount_11zon.pdf1 Dec 2022
Building plan approvalFile: Plan Page-3 B1 - Patel Mount_11zon.pdf1 Dec 2022
Copy of Layout Approval (in case of layout)File: copy Layout - Patel_11zon.pdf1 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan Page 1 B1 - Patel Mount_11zon.pdf1 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan Page 2 B1 - Patel Mount_11zon.pdf1 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: Plan Page-3 B1 - Patel Mount_11zon.pdf1 Dec 2022
Other - TechnicalFile: Declaration Verification -Patel Mount.pdf1 Dec 2022
Declaration in FORM BFile: Form B Affidavit (1).pdf30 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: CC Letter (1)_11zon.pdf29 Nov 2022
Copy of the legal title reportFile: Title Certificate and Search Report - Patel Mount.pdf24 Nov 2022
CERSAI detailsFile: CERSAI Report - Patel Mount.pdf24 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: organized (27).pdf21 Nov 2022
Proforma of Agreement for saleFile: AFS_Patel Group_Patel Mount_04_11_2022.pdf7 Nov 2022
Proforma of Allotment letterFile: Allotment Letter_Patel Group_Patel Mount_04_11_2022.pdf7 Nov 2022
Deviation Report with respect to Allotment letterFile: deviation report allotment letter.pdf5 Nov 2022
Deviation Report with respect to model copy of AgreementFile: deviation report AOS.pdf5 Nov 2022
Details of encumbrances concerned to FinanceFile: encumbrance letter finance.pdf3 Nov 2022
Details of encumbrances concerned to FinanceFile: encumbrance letter legal.pdf3 Nov 2022
Details of encumbrances concerned to LegalFile: encumbrance letter finance.pdf3 Nov 2022
Details of encumbrances concerned to LegalFile: encumbrance letter legal.pdf3 Nov 2022
Declaration about Commencement CertificateFile: declaration (1).pdf3 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format a.pdf3 Nov 2022
PAN CardFile: Patel Group and Co Pancard.pdf2 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf2 Nov 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
Patel Colossus Phase 1P51700010242Kalyan, ThaneAug 2017Certificate SignedDec 2022Dec 2022

How this compares with Thane

32%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 30 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Patel Mount on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chikanghar, Kalyan West7,600+ in Thane

2 kmPatel MountCompleted 86Lapsed / revoked 52Other 130Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: Patel Group & Co

Patel Group & Co has 4 registrations on MahaRERA, including Patel Colossus Phase 1 and Patel Colossus Phase II. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Patel Mount is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Patel Mount?

The registered promoter entity is Patel Group & Co, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Patel Mount?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Patel Mount?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Patel Mount?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Patel Mount?

The professionals named in the filing: Architect: Design Consortium; Engineer: Nadeem Shaikh; Engineer: Akash Kumar Singh; Chartered Accountant: STP & Associates; Chartered Accountant: Pratiksha Tulshyan &Associates; Chartered Accountant: CA Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Patel Mount?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Patel Mount. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Patel Mount to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.