Home / Browse projects / Thane, Maharashtra / PARTH SKYONE

Registration lapsed No litigation declared Residential / Group Housing project

PARTH SKYONE

By Parth Parikh

RG-MH-73922 · RERA P51700015994 · Last updated on MahaRERA portal: 17 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 30 months
  • 1 extension taken
  • Rs 15.00 crore secured on the land, in favour of PUNJAB NATIONAL BANK

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
4 of 11Construction stages donefurthest along: Internal walls, 95%
88 of 185Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

PARTH SKYONE is a Residential / Group Housing project by Parth Parikh in Thane, Maharashtra, registered with MahaRERA as P51700015994 on 11 Apr 2018. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 30 months from the original filing. 97 of the 185 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NamePARTH SKYONE
  • TypeResidential / Group Housing
  • Location
    • GYMKHANA ROAD
    • MIDC
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700015994
  • ReraGenie IDRG-MH-73922

Builder

  • NameParth Parikh
  • Entity typeIndividual
  • Declared earlier projects2 →

Key dates

4 months past promisethis monthRegisteredApr 2018First promiseDec 2023Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Apr 2018
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed89 files

Current status

52%97 of 185 units booked
95.8%Work done, per cost certificate

Figures as on 17 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARTH SKY ONENA242216025185

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

PARTH SKY ONE: 70% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed73

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots73
Open Space73

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,200 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofPUNJAB NATIONAL BANK
Secured amountRs 15.00 crore
CERSAI search filedYes
Declared on18 Sep 2025
LandownerVillageDistrict
DHARMNDRA M PARIKHGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authority:- MIDC, Dombivli Industrial Area...,
Permissible FSI4799.58
Proposed, not sanctioned4,800 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJAY APATMENTS LINKING ROAD SANTACRUZ WEST MUMBAI - 54
Estimated costRs 45.65 cr
Cost incurredRs 43.73 cr
Work done95.8%
BuildingWingEstimatedIncurred
PARTH SKY ONENARs 35.30 crRs 34.16 cr
-NARs 10.35 crRs 9.58 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHOMEWORK
Engineerstructural concepts designs pvt ltd
Chartered AccountantASHOK K LOHIYA AND ASSOCIATES
PartnerRole in project
Parth Parikh-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700025529Dec 2023 → Jun 2026

Reason as filed by the promoterWe have recently obtained a new Commencement Certificate (CC) dated 17/10/2024 from the competent authority, which is valid until period of one Year commencing from date of it issue. We are confident that with the new CC, we will be able to complete the project within the extended timeframe. We request you to consider our application for extension of registration and grant us the necessary extension to complete the project. We are committed to complying with all the provisions of the RERA Act and rules made there under.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Nov 2024

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 17 Architect Certificate form1 dombivli 300626.pdf17 Jul 2026
Withdrawal Update Form 2File: Form 2 3062026-DSC.pdf17 Jul 2026
Withdrawal Update Form 3File: Form-3 30062026 PArth Sky one.pdf17 Jul 2026
Withdrawal Update Form 1File: 16 form1 dombivli 310326dsc.pdf1 Jul 2026
Withdrawal Update Form 2File: Form 2 March 26.pdf1 Jul 2026
Withdrawal Update Form 3File: Skyone From-331032026-final_compressed.pdf1 Jul 2026
Withdrawal Update Form 1File: Architect Certificate form1 dombivli 31 12 25.pdf30 Mar 2026
Withdrawal Update Form 2File: Form 2 Dec 2025 .pdf30 Mar 2026
Withdrawal Update Form 3File: FORM 3 SKYONE 31 12 2025.pdf30 Mar 2026
Withdrawal Update Form 1File: 14 Architect Certificate form1 dombivli 30 09 25 dsc.pdf21 Mar 2026
Withdrawal Update Form 2File: Parth Skyone Form 2 30 09 2025 dsc.pdf21 Mar 2026
Withdrawal Update Form 3File: FORM 3 SKYONE 30 09 2025.pdf21 Mar 2026
Withdrawal Update Form 1File: Architect Certificate form1 dombivli.pdf20 Mar 2026
Withdrawal Update Form 2File: Parth SkyoneForm 2 3062025 dsc.pdf20 Mar 2026
Withdrawal Update Form 3File: Parth Skyone Form 3 30 06 2025.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: inventory disclosure 31032025.pdf7 Jan 2026
Form 3File: FORM-3 SKYONE 31032025.pdf7 Jan 2026
Form 2File: form2Parth Skyone31032025.pdf7 Jan 2026
Form 1File: 12form1 dombivli 31032025.pdf7 Jan 2026
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form-5 sign 23-24.pdf6 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: from 2A Sign 22-23.pdf21 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf16 Jan 2025
Declaration in FORM BFile: form B revised.pdf13 Jan 2025
Certificates of CA (Form 3)File: Form -3 Sign.pdf13 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 july to sep 24.pdf4 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf19 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 10Architect Certificate -form1 dombivli 300624.pdf10 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate -form1 dombivli 300924.pdf10 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate -form1 dombivli 310324.pdf10 Dec 2024
Certificates of CA (Form 3)File: form-3 30062024.pdf10 Dec 2024
Certificates of CA (Form 3)File: form-3 30092024.pdf10 Dec 2024
Disclosure of sold/ booked inventoryFile: inventory.pdf10 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032024.pdf7 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Parth Skyone_Form 2 30092024.pdf7 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Parth Skyone FOM 2 30062024.pdf7 Dec 2024
Declaration about Commencement CertificateFile: cc declaration.pdf5 Dec 2024
CERSAI detailsFile: cersai.pdf5 Dec 2024
Certificates of CA (Form 3)File: FORM 3 MARCH 24.pdf4 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: MAHARERA FORM 5 SKYONE2223.pdf4 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 MARCH 24.pdf4 Dec 2024
Certificates of CA (Form 3)File: Form 3 revised Skyone 31032023.pdf28 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: part oc 13092024.pdf28 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PARTH SKY ONE MARCH 23.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate -form1 dombivli 311223.pdf1 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: part oc 21112023.pdf15 Jan 2024
Certificates of CA (Form 3)File: FORM 3 SKY ONE 2019.pdf13 Apr 2023
Certificates of CA (Form 3)File: FORM 3 SKY ONE 2020.pdf13 Apr 2023
Certificates of CA (Form 3)File: FORM 3 SKY ONE 2021.pdf13 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Sign FY 2018-19.pdf8 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Sign FY 2019-20.pdf8 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Sign FY 2020-21.pdf8 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Parth SkyoneForm 2.pdf7 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Parth SkyoneForm 2A.pdf7 Apr 2023
Certificates of CA (Form 3)File: Form 3 skyone dec22.pdf11 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Parth Skyone march 22.pdf11 Mar 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC - 29052019 parth skyone.pdf11 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form1 dombivli 31032022.pdf16 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 dombivli 31122022.pdf16 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 5 Parth Skyone march 22.pdf16 Feb 2023
Certificates of CA (Form 3)File: Form 3 Parth Skyone March 22.pdf16 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 16th slab certificate skyone.pdf24 May 2021
Layout approvalFile: LAYOUT PLAN 30JUN21.pdf20 Apr 2021
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN 30JUN21.pdf20 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: PARTH SKYONE NEW CC.pdf20 Apr 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 15TH SLAB COMPLETION CERTIFICATE.pdf20 Apr 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 3103.pdf17 Jan 2020
Details of encumbrancesFile: declaration of encrubnaces.pdf20 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2ND SLAB.pdf1 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 SLAB COMPLETION.pdf1 Feb 2019
Proforma of Allotment letterFile: dRAFT aGREEMENT nnnnnn.pdf19 Dec 2018
Certificates of CA (Form 3)File: ca certificate 201018.pdf20 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PLINTH COMPLETION CERTIFICATE.pdf17 Oct 2018
Proforma of Allotment letterFile: Download File.pdf6 Jun 2018
Proforma of Allotment letterFile: Allotment Letter -new (5).pdf31 May 2018
Proforma of Allotment letterFile: Draft Agreement - new (3).pdf31 May 2018
Commencement Certificates / NA Order for plotted developmentFile: 12 COMMENCEMENT CERTIFICATE.pdf9 Apr 2018
Declaration in FORM BFile: FORM B NOTARY.pdf9 Apr 2018
Proforma of Allotment letterFile: DRAFT AGREEMENT PDF RERA.pdf9 Apr 2018
Building plan approvalFile: PLAN.pdf6 Apr 2018
Layout approvalFile: PLAN.pdf6 Apr 2018

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Parth MagnusSanpada46CompletedJul 2017Jul 2017
Parth SolitaireKalamboli68CompletedNov 2012Nov 2012

How this compares with Thane

52%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 30 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARTH SKYONE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MIDC7,600+ in Thane

2 kmPARTH SKYONECompleted 87Lapsed / revoked 81Other 138Dot size: filed unitsN

Filed coordinates, straight-line distance. 306 registered projects within 2 km.

Builder: Parth Parikh

Parth Parikh has 1 registration on MahaRERA, including PARTH SKYONE. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that PARTH SKYONE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARTH SKYONE is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARTH SKYONE?

The registered promoter entity is Parth Parikh, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARTH SKYONE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARTH SKYONE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARTH SKYONE?

The professionals named in the filing: Architect: HOMEWORK; Engineer: structural concepts designs pvt ltd; Chartered Accountant: ASHOK K LOHIYA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARTH SKYONE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARTH SKYONE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARTH SKYONE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.