Home / Browse projects / PARKLANE LIFESEASONS

Registration lapsed No litigation declared Residential / Group Housing project

PARKLANE LIFESEASONS

By Life Seasons Development LLP

RG-MH-15401 · RERA P52100025586 · Last updated on MahaRERA portal: 13 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 9 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Jan 2026Possession promised9 months past this date
33 of 33Construction stages doneacross 3 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

PARKLANE LIFESEASONS is a Residential / Group Housing project by Life Seasons Development LLP in DHANORI, 411015, registered with MahaRERA as P52100025586 on 1 Jul 2020. Possession was promised by 31 Jan 2026 and is now 9 months past that date.

At a glance

Project

  • NamePARKLANE LIFESEASONS
  • TypeResidential / Group Housing
  • Location
    • DM PARANDE PARK MARG
    • DHANORI
    • 411015
  • Pincode411015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100025586
  • ReraGenie IDRG-MH-15401

Builder

  • NameLife Seasons Development LLP
  • Entity typePartnership
  • PartnersSagar Prakash Gandhi, Karan Vijay Porwal, Kunal Vijay Porwal, Swapnil Dilip Bafna, Jitendrakumar Mohanlal Jain, Mamik Rajendra Jain

Key dates

9 months past promisethis monthRegisteredJul 2020PromisedJan 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Jul 2020
  • Promised completion31 Jan 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed79 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A3NA170000
A2NA170000
A1NA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 13 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

33 of 33 construction stages are filed complete across 3 buildings.

A3100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed182

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots182
Closed/Covered161
Open Space21
BuildingClosed/CoveredOpen SpaceTotal
A3707
A280080
A1742195

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,209 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI24869.98
Proposed, not sanctioned24,657 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchS N 39 3 SIDDHESHWARNAGAR TINGRENAGAR ROAD PUNE 15

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSuraj Abhang
EngineerPravin Gaikwad
Chartered AccountantSA Buchha & Co
PartnerRole in project
Life Seasons Development LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Feb 2025

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Q3.pdf13 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Q4.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A.pdf17 Apr 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: Certificate.pdf19 Feb 2025
Deviation Report with respect to model copy of AgreementFile: FULL OC.pdf19 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4.pdf12 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FULL OC.pdf8 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf5 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_C_compressed.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_c_compressed (1).pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf5 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC LSD PART_merged.pdf5 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf2 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf1 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a.pdf1 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 r.pdf1 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A Q3 2023-24.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.PDF9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LSD RERA.pdf1 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19 20.pdf23 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20 21.pdf23 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 19 20.pdf23 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21 22.pdf23 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate for Quality Assurance.pdf23 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19 20.pdf23 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20 21.pdf23 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21 22.pdf23 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22 23.pdf23 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers certificate RERA.pdf7 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LSD 31-3-23 RERA form 3.pdf7 Jun 2023
Details of encumbrances concerned to FinanceFile: DECLARATION ABOUT LITIGATION 25-3-23.pdf25 Mar 2023
Details of encumbrances concerned to LegalFile: DECLARATION ABOUT LITIGATION 25-3-23.pdf25 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Past Project details LSD.pdf25 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORM A Declaration about Separate Bank Account.pdf25 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form no 02 Engineer Certificate.pdf1 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate-compressed.pdf21 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2 Engineers certificate.pdf15 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf8 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2 Engineer Certificate.pdf8 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From 3 CA Certificate.pdf8 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Annx to Certificate.pdf9 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate.pdf8 Nov 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3CA Certificate.pdf8 Nov 2021
Layout approvalFile: Plan 21-08-21 2.pdf1 Nov 2021
Layout approvalFile: Plan 21-08-21 3.pdf1 Nov 2021
Layout approvalFile: Plan 21-08-21 4.pdf1 Nov 2021
Layout approvalFile: Plan 21-08-21 5.pdf1 Nov 2021
Layout approvalFile: Plan 21-08-21 6.pdf1 Nov 2021
Layout approvalFile: Plan 28-8-21 1.pdf1 Nov 2021
Building plan approvalFile: Dhanori Sr No 7 NA ORDER.pdf1 Nov 2021
Copy of Layout Approval (in case of layout)File: Plan 28-8-21 1.pdf1 Nov 2021
Copy of Layout Approval (in case of layout)File: Plan 21-08-21 2.pdf1 Nov 2021
Copy of Layout Approval (in case of layout)File: Plan 21-08-21 3.pdf1 Nov 2021
Copy of Layout Approval (in case of layout)File: Plan 21-08-21 4.pdf1 Nov 2021
Copy of Layout Approval (in case of layout)File: Plan 21-08-21 5.pdf1 Nov 2021
Copy of Layout Approval (in case of layout)File: Plan 21-08-21 6.pdf1 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: Dhanori Sr No 7 NA ORDER.pdf1 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 27-8-21.pdf1 Nov 2021
Declaration about Commencement CertificateFile: CC Declaration.pdf1 Nov 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers certificate.pdf23 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LSD CA Certificate.pdf23 Jul 2021
Proforma of Allotment letterFile: RERA Agreement.pdf18 Nov 2020
Details of encumbrancesFile: Search Title Dhanori sr7.pdf4 Jun 2020
Proforma of Allotment letterFile: ARTICLES OF AGREEMENT draft .pdf4 Jun 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Life Seasons CA Certificate.pdf23 Jan 2020
Declaration in FORM BFile: Rera Declaration in FORM B.pdf6 Jan 2020
Layout approvalFile: PMC Sanction layout SrNo7 Jayraman.pdf1 Jan 2020
Building plan approvalFile: PMC Sanction layout SrNo7 PMC Rupesh.pdf1 Jan 2020
Copy of the legal title reportFile: Search Title Dhanori sr7.pdf1 Jan 2020
Copy of Layout Approval (in case of layout)File: PMC Sanction layout SrNo7 Jayraman.pdf1 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: PMC Sanction layout SrNo7 PMC Rupesh.pdf1 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: Dhanori PMC CC.pdf1 Jan 2020
PAN CardFile: PANCARD LIFE SEASONS DEVELOPMENTS LLP AAHFL4445R.pdf26 Dec 2019

Keep PARKLANE LIFESEASONS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DHANORI

2 kmPARKLANE LIFESEASONSCompleted 31Lapsed / revoked 6Other 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 58 registered projects within 2 km.

Builder: Life Seasons Development LLP

Life Seasons Development LLP has 1 registration on MahaRERA, including PARKLANE LIFESEASONS. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What does it mean that PARKLANE LIFESEASONS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARKLANE LIFESEASONS is delayed beyond 31 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARKLANE LIFESEASONS?

The registered promoter entity is Life Seasons Development LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARKLANE LIFESEASONS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARKLANE LIFESEASONS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARKLANE LIFESEASONS?

The professionals named in the filing: Architect: Suraj Abhang; Engineer: Pravin Gaikwad; Chartered Accountant: SA Buchha & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARKLANE LIFESEASONS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARKLANE LIFESEASONS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARKLANE LIFESEASONS to a free account