Home / Browse projects / Thane, Maharashtra / PARK ENCLAVE

Registered No litigation declared Residential / Group Housing project

PARK ENCLAVE

By NAYANTARA NXT

RG-MH-06249 · RERA P51700053121 · Last updated on MahaRERA portal: 6 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 24 months from the original
4 of 11Construction stages donefurthest along: Internal walls, 95%
5 of 21Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 68 documents Report an error

PARK ENCLAVE is a Residential / Group Housing project by NAYANTARA NXT in Thane, Maharashtra, registered with MahaRERA as P51700053121 on 16 Oct 2023. Possession is promised by 30 Jun 2027. The completion date has moved by 24 months from the original filing. 16 of the 21 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NamePARK ENCLAVE
  • TypeResidential / Group Housing
  • Location
    • CTS NO 6230 6231 AND 6232 AYRE GAON DOMBIVLI EAST 421201
    • AYRE ROAD NEAR KOPAR STATION DOMBIVLI EAST 421201
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700053121
  • ReraGenie IDRG-MH-06249

Builder

  • NameNAYANTARA NXT
  • Entity typePartnership
  • GSTIN27AAOFN9534G1ZS
  • PartnersVINOD BALIRAM PISE, AVINASH VITTHAL MHATRE, SHARAD VISHNU PATIL, ANIL AMARNATH SINGH, VINIT SHANKAR TENDULKAR

Key dates

this monthRegisteredOct 2023First promiseJun 2025Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Oct 2023
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed68 files

Current status

76%16 of 21 units booked
97.0%Work done, per cost certificate

Figures as on 6 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARK ENCLAVENA5721021

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

PARK ENCLAVE: 78% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 6 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes60%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes60%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Open Space12

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area402 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Sep 2024
LandownerVillageDistrict
MATU SHANTARAM KENEDOMBIVLIThane
CAPTAIN MATU KENEDOMBIVLIThane
KIRAN MATU KENEDOMBIVLIThane
SHRAVAN MATU KENEDOMBIVLIThane
AVINASH MATU KENEDOMBIVLIThane

Approvals and building plan

Sanctioning authorityKalyan Dombivali Municipal Corporation, Kalyan
Permissible FSI1204.4
Proposed, not sanctioned659 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAMNAGAR DOMBIVLI EAST
Estimated costRs 4.60 cr
Cost incurredRs 4.46 cr
Work done97.0%
BuildingWingEstimatedIncurred
PARK ENCLAVENARs 4.60 crRs 4.46 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSTHAPATYA NIRMAAN
ArchitectSHIRISH GAJANAN NACHANE
EngineerBAHUBALI DHAMANE
EngineerBAHUBALI T DHAMANE
Chartered AccountantDHIRAJ WAGHMARE
Chartered AccountantDHIRAJ SUDHIR WAGHMARE
Chartered AccountantSIDDHI SANJAY MANE
Chartered AccountantPooja Prasad Sawant & Company
PartnerRole in project
NAYANTARA NXT-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA11092502557Jun 2025 → Jun 2026

Reason as filed by the promoterDue to certain circumstances, we are unable to complete our project. Therefore, we request an extension until 30th June 2026.

EA06082622035Jun 2025 → Jun 2027

Reason as filed by the promoterThere were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed68

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A FY 2025-26.pdf6 Aug 2026
Withdrawal Update Form 1File: Form 1_Jun 26.pdf22 Jul 2026
Withdrawal Update Form 2File: Form 2_Jun 26.pdf22 Jul 2026
Withdrawal Update Form 3File: Form 3_Jun 26.pdf22 Jul 2026
Withdrawal Update Form 1File: Form 1_Mar 26.pdf25 Apr 2026
Withdrawal Update Form 2File: Form 2_Mar 26.pdf25 Apr 2026
Withdrawal Update Form 3File: Form 3_Mar 26.pdf25 Apr 2026
Withdrawal Update Form 1File: Form 1 Dec 25.pdf19 Jan 2026
Withdrawal Update Form 2File: Form 2 Dec 25.pdf19 Jan 2026
Withdrawal Update Form 3File: Form 3 Dec 25.pdf19 Jan 2026
Withdrawal Update Form 1File: Form 1_Sep 25.pdf18 Oct 2025
Withdrawal Update Form 1File: Form 1_Sep 25.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2_Sep 25.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2_Sep 25.pdf18 Oct 2025
Withdrawal Update Form 3File: Form 3_Sep 25.pdf18 Oct 2025
Withdrawal Update Form 3File: Form 3_Sep 25.pdf18 Oct 2025
Form 2A (FY 2023-2024)File: FORM 2A MARCH 2024.pdf30 Sep 2025
Form 2A (FY 2024-2025)File: FORM 2A MARCH 2025.pdf30 Sep 2025
Form 5 (FY 2023-2024)File: Form -5 FY-23-24.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: Form -5 FY-24-25.pdf30 Sep 2025
Form 1File: FORM 1 31-03-2025 NAYANTARA.pdf18 Jul 2025
Form 2File: FORM 2 NAYANTARA 31 MARCH 25.pdf18 Jul 2025
Form 3File: FORM 3 NAYANTARA 31-03-2025.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 31-03-2025.pdf18 Jul 2025
Form 1File: FORM 1 31-03-2025 NAYANTARA.pdf18 Jul 2025
Form 2File: FORM 2 NAYANTARA 30 JUNE 25.pdf18 Jul 2025
Form 3File: FORM 3 NAYANTARA 31-03-2025.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 31-03-2025.pdf18 Jul 2025
Form 1File: FORM 1 30-06-2025 NAYANTARA.pdf18 Jul 2025
Form 2File: FORM 2 NAYANTARA 30 JUNE 25.pdf18 Jul 2025
Form 3File: FORM 3 NAYANTARA 30-06-2025.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 30-06-2025.pdf18 Jul 2025
Other - LegalFile: SN 59-2 (1).pdf19 Jun 2025
Other - TechnicalFile: Nayantara NXT Declaration cum undertaking Annexure A (1).pdf11 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Nayantara NXT Form No5.pdf29 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Nayantara NXT Form 2A.pdf23 Mar 2024
Disclosure of sold/ booked inventoryFile: Nayantara NXT Disclosure sold booked inventory.pdf23 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nayantara NXT Form 3 CA certificate - converted.pdf23 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Nayantara NXT declaration about Saperate Bank account.pdf23 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nayantara NXT Form 1 Architect Certificate - converted.pdf2 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nayantara NXT Form 2 Engineers certificate - converted.pdf2 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Form 3 Nayantara NXT (2).pdf2 Oct 2023
Copy of the legal title reportFile: TITLE REPORT NEW.pdf4 Sep 2023
Proforma of Agreement for saleFile: REVISED DRAFT RERA AGREEMENT AYRE.pdf4 Sep 2023
Other - LegalFile: Screenshot (310) (1).pdf4 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nayantara NXT Architect Certificate Form 1_0001.pdf8 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nayantara NXT Engineer Certificate Form 2_0001.pdf8 Aug 2023
CERSAI detailsFile: popo_1 (2 files merged).pdf8 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: OTHER RERA _1.pdf8 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: OTHER RERA _2.pdf8 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: OTHER RERA _3.pdf8 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: OTHER RERA _4.pdf8 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Nayantara NXT Annexure A Prashant Shukla_0001.pdf8 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Nayantara NXT Annexure A_0001 Vinod Pise.pdf8 Aug 2023
Layout approvalFile: scan029 (1).pdf7 Aug 2023
Building plan approvalFile: scan029 (1).pdf7 Aug 2023
PAN CardFile: Screenshot (289).pdf7 Aug 2023
Details of encumbrances concerned to FinanceFile: Nayantara NXT ENCUMBARANCE TO FINANCE_0001 (2 files merged).pdf7 Aug 2023
Details of encumbrances concerned to LegalFile: Nayantara NXT ENCUMBARANCE TO FINANCE_0001 (2 files merged).pdf7 Aug 2023
Copy of Layout Approval (in case of layout)File: scan029 (1).pdf7 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: scan029 (1).pdf7 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: S041000390_2304191330000 (1) (1).pdf7 Aug 2023
Declaration about Commencement CertificateFile: Nayantara NXT DECLARATION ABOUT COMMENCEMNT CERTIFICATE format D_0001.pdf7 Aug 2023
Declaration in FORM BFile: Nayantara NXT Form B Declaration _0001.pdf7 Aug 2023
Proforma of Allotment letterFile: Nayantara NXT Model Allotment letter_0001.pdf7 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Nayantara NXT Declaration about Separate Bank Account for real e_20230807_0001.pdf7 Aug 2023
Deviation Report with respect to Allotment letterFile: Nayantara NXT Deviation Report Allotment letter_0001.pdf7 Aug 2023
Deviation Report with respect to model copy of AgreementFile: Nayantara NXT Deviation Report Agreement_0001.pdf7 Aug 2023

How this compares with Thane

76%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARK ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AYRE ROAD NEAR KOPAR STATION DOMBIVLI EAST 4212017,600+ in Thane

2 kmPARK ENCLAVECompleted 79Lapsed / revoked 72Other 115Dot size: filed unitsN

Filed coordinates, straight-line distance. 266 registered projects within 2 km.

Builder: NAYANTARA NXT

NAYANTARA NXT has 1 registration on MahaRERA, including PARK ENCLAVE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if PARK ENCLAVE is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARK ENCLAVE?

The registered promoter entity is NAYANTARA NXT, a partnership as per the filing. Its GSTIN 27AAOFN9534G1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARK ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARK ENCLAVE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARK ENCLAVE?

The professionals named in the filing: Architect: STHAPATYA NIRMAAN; Architect: SHIRISH GAJANAN NACHANE; Engineer: BAHUBALI DHAMANE; Engineer: BAHUBALI T DHAMANE; Chartered Accountant: DHIRAJ WAGHMARE; Chartered Accountant: DHIRAJ SUDHIR WAGHMARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARK ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARK ENCLAVE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARK ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.