ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Parinee i

Registered No litigation declared Commercial project

Parinee i

By PARINEE REALTY PRIVATE LIMITED

RG-MH-19662 · RERA P51800001904 · Last updated on MahaRERA portal: 3 Sep 2026

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 90 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 90 months from the original
10 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 0%
40 of 286Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 138 documents Report an error

Parinee i is a Commercial project by PARINEE REALTY PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001904 on 29 Jul 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 90 months from the original filing. 246 of the 286 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameParinee i
  • TypeCommercial
  • Location
    • Off Link Road
    • Andheri west
    • Andheri
    • Mumbai Suburban
    • 400053
  • Pincode400053
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800001904
  • ReraGenie IDRG-MH-19662

Builder

  • NamePARINEE REALTY PRIVATE LIMITED
  • Entity typeCompany
  • DireDhaval Dilip Shah
  • DirectorVipul Dilip Shah
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects3 →

Key dates

this monthRegisteredJul 2017First promiseJun 2021Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jul 2017
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed138 files

Current status

86%246 of 286 units booked
116.5%Work done, per cost certificate

Figures as on 3 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Parinee iNA34310286286

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 0%.

Parinee i: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed304

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots304
Closed/Covered304

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,997 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI17454.13
Proposed, not sanctioned16,751 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchANDHERI KURLA ROAD, ANDHERI EAST, MUMBAI
Estimated costRs 257.90 cr
Cost incurredRs 300.54 cr
Work done116.53%
BuildingWingEstimatedIncurred
Parinee iNARs 229.73 crRs 276.82 cr
-NARs 28.17 crRs 23.72 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDharmesh Chevli
EngineerVinayak Bowlekar
Chartered AccountantBarin Trivedi & Co.
Chartered AccountantB B Jain and Associates
PartnerRole in project
PARINEE REALTY PRIVATE LIMITED-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009968Jun 2021 → Jun 2022

Reason as filed by the promoter“Parinee i” is a Commercial Project being undertaken under the SRA. The RCC structure is already completed way back in 2019, but due to current pandemic situation and non-disbursal of funds by the lending institution due to their internal issues, the further work couldn’t be completed within the stipulated time. The reasons/circumstances, which were beyond the control of Promoter are enlisted below:- Delay in grant of various approvals: Due to changes in the regulations, the project plans are amended in April 2017. Post that there is delay in granting various approvals like Further CC, High Ri

EXT51800013127Jun 2021 → Mar 2024

Reason as filed by the promoter“Parinee I” is a Commercial Project undertaken under the SRA. The RCC structure of the entire building is already completed way back in 2019. Due to past pandemic situation, non-disbursal of funds by the lending institution and various delay in approvals from the competent authorities, the further work couldn’t be completed within the stipulated time and the reasons were beyond the control of Promoter 1) On 31st December 2020 SRA had issued stop work on project on baseless grounds. We had filed Writ Petition (L) 8601 in High Court, whilst the same was pending SRA withdrew the Stop Work Notice

EXT51800019725Jun 2021 → Dec 2024

Reason as filed by the promoter“Parinee I” is a 30 storey Commercial Project undertaken under the SRA. The RCC structure of the entire building is already completed way back in 2019. Due to past pandemic situation, non-disbursal of funds by the lending institution and various delay in approvals from the competent authorities, the further work couldn’t be completed within the stipulated time and the reasons were beyond the control of Promoter 1) The finishing work uptill 23rd floor is already completed and no inventory is sold beyond 23rd Floor. 2) We have obtained Part Occupation Certificate uptill 12th Floor on 02/11/223,

EA21082622304Jun 2021 → Dec 2028

Reason as filed by the promoterWe, Parinee Realty Private Limited, the promoter of the project Parinee i (Registration No. P51800001904) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We wish to clarify that the construction of the project has been completed and we have also received Part Occupancy Certificate for a major portion of the project from the Planning Authority Slum Rehabilitation Authority. However, the Full Occupancy Certificate is yet to be received. Certain SRA compliances are pending from our side, which are required to be completed before the Planning A

Litigation declared1

CaseCourtStatus
258/2017HIGH COURT BOMBAYNOTICE OF MOTION FOR HEARING

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000044303RADHAKRISHNA SHETTYPARINEE REALTY PVT LTD27/04/2018
CC006000000193953Aman Sachdeva & Sejal SachdevaShri Vipul Dilip Shah10/09/2020
CC006000000395566NARENDRA POPATPARINEE REALTY PRIVATE LTD08/05/2023
CC006000000395567CHANDRAVADAN TRIVEDIPARINEE REALTY PRIVATE LTD08/05/2023
CC006000000540768SAHIL SIKANDER SHAIKHPARINEE REALITY PVT. LTD.13/06/2024
CC12604555Tarun RathiParinee Realty Private Limited20/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Mar 2024

Documents filed138

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 138 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: VINAYAK J BOWLEKAR.pdf3 Sep 2026
Withdrawal Update Form 1File: Form 1 Parinee I June 2026.pdf27 Aug 2026
Withdrawal Update Form 1File: Form 1 Parinee I June 2026.pdf27 Aug 2026
Withdrawal Update Form 1File: Form 1 Parinee I June 2026.pdf27 Aug 2026
Withdrawal Update Form 1File: Form 1 Parinee I June 2026.pdf27 Aug 2026
Withdrawal Update Form 1File: Form 1 Parinee I June 2026.pdf27 Aug 2026
Withdrawal Update Form 1File: Form 1 Parinee I June 2026.pdf27 Aug 2026
Withdrawal Update Form 2File: Form 2 Parinee I Jun 26.pdf27 Aug 2026
Withdrawal Update Form 2File: Form 2 Parinee I Jun 26.pdf27 Aug 2026
Withdrawal Update Form 2File: Form 2 Parinee I Jun 26.pdf27 Aug 2026
Withdrawal Update Form 2File: Form 2 Parinee I Jun 26.pdf27 Aug 2026
Withdrawal Update Form 2File: Form 2 Parinee I Jun 26.pdf27 Aug 2026
Withdrawal Update Form 2File: Form 2 Parinee I Jun 26.pdf27 Aug 2026
Withdrawal Update Form 3File: Form 3 Parinee I June 2026_compressed.pdf27 Aug 2026
Withdrawal Update Form 3File: Form 3 Parinee I June 2026_compressed.pdf27 Aug 2026
Withdrawal Update Form 3File: Form 3 Parinee I June 2026_compressed.pdf27 Aug 2026
Withdrawal Update Form 3File: Form 3 Parinee I June 2026_compressed.pdf27 Aug 2026
Withdrawal Update Form 3File: Form 3 Parinee I June 2026_compressed.pdf27 Aug 2026
Withdrawal Update Form 3File: Form 3 Parinee I June 2026_compressed.pdf27 Aug 2026
Withdrawal Update Form 1File: Form 1 Parinee I June 2026.pdf21 Aug 2026
Withdrawal Update Form 1File: Form 1 Parinee I June 2026.pdf21 Aug 2026
Withdrawal Update Form 1File: Form 1 Parinee I June 2026.pdf21 Aug 2026
Withdrawal Update Form 2File: Form 2 Parinee I Jun 26.pdf21 Aug 2026
Withdrawal Update Form 2File: Form 2 Parinee I Jun 26.pdf21 Aug 2026
Withdrawal Update Form 2File: Form 2 Parinee I Jun 26.pdf21 Aug 2026
Withdrawal Update Form 3File: Form 3 Parinee I June 2026_compressed.pdf21 Aug 2026
Withdrawal Update Form 3File: Form 3 Parinee I June 2026_compressed.pdf21 Aug 2026
Withdrawal Update Form 3File: Form 3 Parinee I June 2026_compressed.pdf21 Aug 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Parinee - I Form - I March 2025.pdf4 May 2025
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 March 2025 pt 1.pdf4 May 2025
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 March 2025 pt 2.pdf4 May 2025
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 March 2025 pt 3.pdf4 May 2025
Certificates of CA (Form 5)File: Form 5 - Parinee I - FY 2024-25.pdf4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Parinee I March 2025.pdf4 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Parinee I FORM 1 JUNE 2024.pdf22 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Parinee I FORM 1 SEPTEMBER 2024.pdf22 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Parinee I FORM 1 DECEMBER 2024.pdf22 Feb 2025
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 30th June 2024.pdf9 Feb 2025
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 Sep 2024.pdf9 Feb 2025
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 Dec 2024.pdf9 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Parinee I June 2024.pdf9 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Parinee I Sep 2024.pdf9 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Parinee I Dec 2024.pdf9 Feb 2025
Disclosure of sold/ booked inventoryFile: Parinee I _RERA _Sold, Unsold and Booked.pdf9 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A-Parinee I-Engneer Certificate.pdf22 Jan 2025
Certificates of CA (Form 5)File: Form 5 - Parinee I - FY 2023-24.pdf26 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Parinee I - FY 2023-24.pdf26 Dec 2024
Declaration in FORM BFile: Form B Parinee I Rera Extension.pdf17 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Parinee I Form 1 March 2024.pdf17 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Parinee I Form 2 March 2024.pdf17 May 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 31st March 2024_1.pdf17 May 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 31st March 2024_2.pdf17 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Further CC 05032024.pdf4 May 2024
Declaration about Commencement CertificateFile: CC Declaration.pdf4 May 2024
Details of encumbrancesFile: JCF New Loan.pdf30 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Parinee I June 2023.pdf30 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Parinee I Sep 2023.pdf30 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Parinee I Dec 2023.pdf30 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Parinee I March 2023.pdf30 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Parinee I June 2023.pdf30 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 parinee i Sep 2023.pdf30 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Parinee I Dec 2023.pdf30 Mar 2024
Disclosure of sold/ booked inventoryFile: Parinee I _Sold, Unsold, Booked Inventory 29022024.pdf30 Mar 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 30th June 2023_1.pdf30 Mar 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 30th June 2023_2.pdf30 Mar 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 30th June 2023_3.pdf30 Mar 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 30th September 2023_1.pdf30 Mar 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 30th September 2023_2.pdf30 Mar 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 30th September 2023_3.pdf30 Mar 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 31st December 2023_1.pdf30 Mar 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 31st December 2023_2.pdf30 Mar 2024
Certificates of CA (Form 3)File: Parinee I - Rera Form 3 - 31st December 2023_3.pdf30 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Parinee I Part OC till 12th Floor.pdf30 Mar 2024
Certificates of CA (Form 3)File: Form 3 Parinee I Jun 2022.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Parinee i Sep 2022.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Parinee I Dec 2022.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Parinee i Mar 2023.pdf5 Mar 2024
Certificates of CA (Form 3)File: Parinee i form 3 fy 18.pdf29 Sep 2023
Certificates of CA (Form 5)File: Form 5- Parinee I_FY 2022-23.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Parinee I_FY 2022-23.pdf29 Sep 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
ANANDVILLAPLOT NO. 65 Z LINKING ROAD SANTACRUZ WEST VILLAGE BANDRA TALUKA ANDHERI MUMBAI.17CompletedSep 2012Late, Dec 2012
SUDEEPPLOT NO 61 NUTAN LAXMI CHSL NS ROAD NO 8 JVPD VILLE PARLE WEST MUMBAI10CompletedMar 2012Late, May 2012
KRISHLINSUB PLOT NO 13 NUTAN LAXMI CHSL NS ROAD NO 10 JVPD VILLE PARLE WEST MUMBAI10CompletedMar 2010Late, Apr 2010

How this compares with Mumbai Suburban

86%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 90 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Parinee i on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri west6,700+ in Mumbai Suburban

2 kmParinee iCompleted 105Lapsed / revoked 78Abeyance 1Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 336 registered projects within 2 km.

Builder: PARINEE REALTY PRIVATE LIMITED

PARINEE REALTY PRIVATE LIMITED has 3 registrations on MahaRERA, including Parinee Adney and Parinee i. Its filings disclose 3 earlier MahaRERA projects: declares 0 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Parinee i is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Parinee i?

The registered promoter entity is PARINEE REALTY PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Parinee i?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Parinee i?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Parinee i?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Parinee i?

The professionals named in the filing: Architect: Dharmesh Chevli; Engineer: Vinayak Bowlekar; Chartered Accountant: Barin Trivedi & Co.; Chartered Accountant: B B Jain and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Parinee i?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Parinee i. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Parinee i to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.