Home / Browse projects / Palghar, Maharashtra / PARASNATH NAGARI BUILDING NO. 2

Registration lapsed No litigation declared Others project

PARASNATH NAGARI BUILDING NO. 2

By SHREE PARASNATH BUILDERS

RG-MH-53762 · RERA P99000009350 · Last updated on MahaRERA portal: 18 Apr 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date
  • 7 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
15 of 55Construction stages doneacross 5 buildings; furthest along: Podiums (if any), 0%
7Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

PARASNATH NAGARI BUILDING NO. 2 is a Others project by SHREE PARASNATH BUILDERS in Palghar, Maharashtra, registered with MahaRERA as P99000009350 on 22 Aug 2017. Possession was promised by 13 Dec 2022 and is now 46 months past that date. The completion date has moved by 12 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NamePARASNATH NAGARI BUILDING NO. 2
  • TypeOthers
  • Location
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401209
  • Pincode401209
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000009350
  • ReraGenie IDRG-MH-53762

Builder

  • NameSHREE PARASNATH BUILDERS
  • Entity typePartnership
  • PartnersMEHUL M CHAPLOT, DAYANAND D PATIL, ROHIT B MOTAWAT, SNEHA PATIL, NARESH S JAIN
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

46 months past promisethis monthRegisteredAug 2017First promiseDec 2021Revised toDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion13 Dec 2022
  • Revised completionRevised to 13 Dec 2022 (originally 13 Dec 2021)
  • Buildings5 building records
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARASNATH NAGARI BUILDING NO 2 ANA90000
PARASNATH NAGARI BUILDING NO 2 BNA90000
PARASNATH NAGARI BUILDING NO 2 CNA90000
PARASNATH NAGARI BUILDING NO 2 DNA90000
PARASNATH NAGARI BUILDING NO 2 ENA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 18 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 0%.

PARASNATH NAGARI BUILDING NO 2 A27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PARASNATH NAGARI BUILDING NO 2 B27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PARASNATH NAGARI BUILDING NO 2 C27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PARASNATH NAGARI BUILDING NO 2 D27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PARASNATH NAGARI BUILDING NO 2 E27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered5
Open Space10
BuildingClosed/CoveredOpen SpaceTotal
PARASNATH NAGARI BUILDING NO 2 A123
PARASNATH NAGARI BUILDING NO 2 B123
PARASNATH NAGARI BUILDING NO 2 C123
PARASNATH NAGARI BUILDING NO 2 D123
PARASNATH NAGARI BUILDING NO 2 E123

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,260 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
NELSON SIMONS REBELLOVasai-Virar City (M Corp)Palghar
HARDIK DAYANAND PATILVasai-Virar City (M Corp)Palghar

Approvals and building plan

Permissible FSI12350.0
Proposed, not sanctioned3,405 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch100FT, VASAI NALASOPARA LINK ROAD

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbhay Raut
EngineerHaresh L Patel
PartnerRole in project
SHREE PARASNATH BUILDERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000012860Dec 2021 → Dec 2022

Reason as filed by the promoterWe have Commencement Certificate of Building No 2 Wing A to E Received on Dated 27/01/2015 till Ground + 3 Floors. Our Building No 2 Proposed for Ground + 23 Floors. But Our Building Requirement of Environment Clearance from Authority. This Permission Not Received Till Date. So We Request You Please Extend Time for Project Competition.

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000194377Udaiprakash P Chawhan andNeelam ChawhanShree Parasnath Builders01/01/2021
CC006000000397302Shelton John ColasoShri Parasnath Builders02/09/2023
CC006000000397303Shelton John ColasoShri Parasnath Builders02/09/2023
CC006000000397306Gurminderjit Singh ValotraShri Parasnath Builders05/09/2023
CC006000000397308Sushil ChoudharyShri Parasnath Builders06/09/2023
CC006000000397529Sudarshan MishraShri Parasnath Builders04/10/2023
CC006000000408133Shivanath MishraShri Parasnath Builders21/11/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about Commencement CertificateFile: Declaration about CC.pdf18 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form - 2A - Q1 - 30-06-2020.pdf14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form - 2A - Q2 - 30-09-2020.pdf14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form - 2A - Q3 - 31-12-2020.pdf14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form - 2A - Q4 - 31-03-2021.pdf14 Apr 2023
CERSAI detailsFile: Self Declaration Regarding Cersai.pdf14 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold as on 23-03-2023.pdf14 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 - 01-04-2017 to 31-03-2018.pdf14 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - 01-04-2018 to 31-03-2019.pdf14 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - 01-04-2019 to 31-03-2020.pdf14 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 01-04-2020 to 31-03-2021.pdf14 Apr 2023
Layout approvalFile: lay out plan.pdf1 Aug 2017
Layout approvalFile: building 2 plan.pdf1 Aug 2017
Building plan approvalFile: lay out plan.pdf1 Aug 2017
Building plan approvalFile: building 2 plan.pdf1 Aug 2017
PAN CardFile: Company PAN.pdf1 Aug 2017
Copy of the legal title reportFile: Title Report BUILDING 1,2,5.pdf1 Aug 2017
Details of encumbrancesFile: No Encumbrances Letter Building No2.pdf1 Aug 2017
Copy of Layout Approval (in case of layout)File: lay out plan.pdf1 Aug 2017
Copy of Layout Approval (in case of layout)File: building 2 plan.pdf1 Aug 2017
Building Plan Approval (IOD)File: lay out plan.pdf1 Aug 2017
Building Plan Approval (IOD)File: building 2 plan.pdf1 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: cc09-11-11 building 1,2,5.pdf1 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: vvmcm 27-1-15 building 1,2,5.pdf1 Aug 2017
Declaration in FORM BFile: Bldg 2 Form B declaration.pdf1 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect building 2.pdf1 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 engineer certificate building2.pdf1 Aug 2017
Certificates of CA (Form 3)File: Form No3 Building No2.pdf1 Aug 2017
Proforma of Allotment letterFile: Building No 1 2 5.pdf1 Aug 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 12 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARASNATH NAGARI BUILDING NO. 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

2 kmPARASNATH NAGARI BUILDINCompleted 50Lapsed / revoked 38Other 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: SHREE PARASNATH BUILDERS

SHREE PARASNATH BUILDERS has 3 registrations on MahaRERA, including PARASNATH NAGARI BUILDING NO. 1 and PARASNATH NAGARI BUILDING NO 5. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that PARASNATH NAGARI BUILDING NO. 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARASNATH NAGARI BUILDING NO. 2 is delayed beyond 13 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARASNATH NAGARI BUILDING NO. 2?

The registered promoter entity is SHREE PARASNATH BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARASNATH NAGARI BUILDING NO. 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PARASNATH NAGARI BUILDING NO. 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PARASNATH NAGARI BUILDING NO. 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARASNATH NAGARI BUILDING NO. 2?

The professionals named in the filing: Architect: Abhay Raut; Engineer: Haresh L Patel. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARASNATH NAGARI BUILDING NO. 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARASNATH NAGARI BUILDING NO. 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARASNATH NAGARI BUILDING NO. 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.