Home / Browse projects / Palghar, Maharashtra / Paramount Heights

Completed No litigation declared Residential / Group Housing project

Paramount Heights

By M/s Zion Constructions

RG-MH-41462 · RERA P99000010275 · Last updated on MahaRERA portal: 22 Jan 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
6 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 90%
1Complaints at MahaRERAon this registration
Jump to the 127 documents Report an error

Paramount Heights is a Residential / Group Housing project by M/s Zion Constructions in Palghar, Maharashtra, registered with MahaRERA as P99000010275 on 24 Aug 2017. The registration is recorded completed; possession was promised by 29 Jun 2023. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameParamount Heights
  • TypeResidential / Group Housing
  • Location
    • Chulane Road
    • Vasai (W)
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401202
  • Pincode401202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000010275
  • ReraGenie IDRG-MH-41462

Builder

  • NameM/s Zion Constructions
  • Entity typePartnership
  • PartnerBarthol Lawrence Dias

Key dates

this monthRegisteredAug 2017First promiseJun 2021Revised toJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Aug 2017
  • Promised completion29 Jun 2023
  • Revised completionRevised to 29 Jun 2023 (originally 30 Jun 2021)
  • Buildings2 building records
  • Documents filed127 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bldg No 1NA210000
Bldg No 2NA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

Bldg No 186%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)50%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Bldg No 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes30%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes35%
Landscaping & Tree PlantingYes30%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes30%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes35%
Electrical meter room, sub-station, receiving stationYes35%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed92

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots92
Closed/Covered60
Open Space32
BuildingClosed/CoveredOpen SpaceTotal
Bldg No 1593291
Bldg No 2101

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,510 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6023.18
Proposed, not sanctioned1,961 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhabola Vasai West

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMs Encon
EngineerEPICONS CONSULTANTS PVT LTD
PartnerRole in project
M/s Zion Constructions-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000009644Jun 2021 → Jun 2022

Reason as filed by the promoterTo The respected MAHARERA Authority, Maharashtra State. Sir, We humbly submit as under: 1. The RERA Registration Certificate bearing registration Number P99000010275 dated 18 May 2020, commencing from 24 August 2017 in respect of our project- Paramount Heights is getting over/expired on 30 June 2021. 2. Owing to the delay caused by the competent authority in approving our revised development plan, the construction was stopped for some time. Thereafter, because of the Covid 19 Pandemic, during the Lockdown imposed by the Central Government we could carry on with the construction with only limit

EXT99000013444Jun 2021 → Jun 2023

Reason as filed by the promoterTo Tha MAHARERA Authority, Mumbai Maharashtra, Kindly allow our application for Second extension of our above project from 31st December, 2022 to 29th June, 2023. Although we tried completing our above project by the date of completion as was permitted by Maharera vide the extension application granted by Maharera vide its Certificate dated 09/09/2021, we have not yet received Occupation Certificate from the Municipal Corporation. Vide Application dated 30th November, 2022, on our behalf, Mr. Sanjay Narang has submitted application to VVCMC for grant of Occupation Certificate. Further, vide ou

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000055752Mr. Randolf NettoMs. Zion Constructions through its Partner Mr.Bronson Dias14/08/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Dec 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Jan 2025

Documents filed127

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Zion Constructions Annexure-E Form-4 29-11-2024 (1).pdf22 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 building no 1 zion.pdf22 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Bldg No 2 OC Date 29122023.pdf22 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Zion Constructions Annexure -A Form 1, 29-11-2024.pdf27 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: Zion Constructions Annexure-E Form-4, 12-04-2023.pdf27 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Zion Constructions Annexure-A Form 2, 12-04-2023.pdf27 Dec 2024
Other - LegalFile: Zion Constructions Annexure-E Form-4, 12-04-2023.pdf27 Dec 2024
Other - LegalFile: Zion Constructions Annexure-E Form-4, 12-04-2023_1.pdf27 Dec 2024
Other - LegalFile: Zion Constructions Annexure-E Form-4, 29-11-2024.pdf27 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Date 09032023.pdf27 Dec 2024
Certificates of CA (Form 3)File: Annexure A Qtr3.pdf1 Mar 2024
Certificates of CA (Form 3)File: Annexure A Qtr 2.pdf10 Oct 2023
Certificates of CA (Form 3)File: Annexure A Qtr 4.pdf25 Sep 2023
Certificates of CA (Form 3)File: Annexure A Qtr 1.pdf25 Sep 2023
Certificates of CA (Form 3)File: CA Form3 Q3 .pdf14 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Certificate .pdf14 Apr 2023
Certificates of CA (Form 3)File: CA Q2 Zion Construction.pdf13 Apr 2023
Certificates of CA (Form 5)File: CA Q2 Zion Construction.pdf13 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 En con.pdf5 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SS Associates.pdf5 Apr 2023
Certificates of CA (Form 3)File: Q2 Zion Construction.pdf5 Apr 2023
Certificates of CA (Form 3)File: Q3 Zion Construction.pdf5 Apr 2023
Deviation Report with respect to Allotment letterFile: additonal Deviation report of allotment letter.pdf22 Feb 2023
CERSAI detailsFile: CERSAI report Paramount Hieghts.pdf21 Feb 2023
Details of encumbrances concerned to FinanceFile: Encumbrances Concerned .pdf20 Feb 2023
Details of encumbrances concerned to LegalFile: Encumbrances Concerned .pdf20 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate.pdf20 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest in other real estate.pdf20 Feb 2023
Proforma of Allotment letterFile: Annexure 1 Allotement Letter.pdf20 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Bank Account.pdf20 Feb 2023
Deviation Report with respect to Allotment letterFile: Deviation of Allotment Letter.pdf20 Feb 2023
Deviation Report with respect to model copy of AgreementFile: Details of Deviation of Agreement.pdf20 Feb 2023
Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory.pdf17 Jan 2023
Proforma of Agreement for saleFile: Agreement for Sale.pdf14 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Encon Form 1.pdf28 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SS Associates Form 2.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Form 3.pdf28 Dec 2022
Certificates of CA (Form 3)File: Inventory.pdf28 Dec 2022
Certificates of CA (Form 5)File: Rera Certificate (From 5) Zion Constructions (1).pdf14 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf14 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Zion- RERA certificate form 5.pdf14 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Rera Certificate (From 5) Zion Constructions (1).pdf14 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ENCon Form 1 Zion.pdf13 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SS Associates Fom 2 Zion.pdf13 Oct 2022
Certificates of CA (Form 3)File: From 3 Zion .pdf13 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Encon.pdf13 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SS Associates.pdf13 May 2022
Certificates of CA (Form 3)File: Form 3 CA.pdf13 May 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf19 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Encon.pdf27 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2nSS Associate.pdf27 Jan 2022
Certificates of CA (Form 3)File: Form 3 CA.pdf27 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Encon.pdf31 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SS Associate.pdf31 Aug 2021
Certificates of CA (Form 3)File: Form 3 CA Kishor.pdf31 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Encon.pdf15 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SS Associates.pdf15 Jul 2021
Certificates of CA (Form 3)File: Form 3 CA.pdf15 Jul 2021
Certificates of CA (Form 5)File: Zion- RERA certificate form 5.pdf15 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 Encon.pdf28 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 Encon.pdf28 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Encon.pdf28 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 SS Associate.pdf28 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 SS Associate.pdf28 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate SS Associates.pdf28 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate SS Associates.pdf28 May 2021
Disclosure of sold/ booked inventoryFile: Scan Discolsure of Sold Book InventoryZion.pdf28 May 2021
Certificates of CA (Form 3)File: Form 3 CA.pdf28 May 2021
Certificates of CA (Form 3)File: Form 3 CA.pdf28 May 2021
Certificates of CA (Form 5)File: Form 3 CA.pdf28 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 Encon.pdf4 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 SS Associate.pdf4 Mar 2021
Certificates of CA (Form 3)File: Form 3.pdf4 Mar 2021
Certificates of CA (Form 5)File: Form 5.pdf4 Mar 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 Encon.pdf27 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certifcate Form 2 SS Asociates.pdf27 Jul 2020
Certificates of CA (Form 3)File: CA Certificate Form 3.pdf27 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Certificate.pdf8 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Certifcate -encon.pdf8 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers CertifcateZION.pdf8 Feb 2020

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 24 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Paramount Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai (W)3,200+ in Palghar

2 kmParamount HeightsCompleted 45Lapsed / revoked 27Other 55Dot size: filed unitsN

Filed coordinates, straight-line distance. 127 registered projects within 2 km.

Builder: M/s Zion Constructions

M/s Zion Constructions has 1 registration on MahaRERA, including Paramount Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Paramount Heights is delayed beyond 29 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Paramount Heights?

The registered promoter entity is M/s Zion Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Paramount Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Paramount Heights?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Paramount Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Paramount Heights?

The professionals named in the filing: Architect: Ms Encon; Engineer: EPICONS CONSULTANTS PVT LTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Paramount Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Paramount Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Paramount Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.