Home / Browse projects / Thane, Maharashtra / Panvelkar Nisarg Phase II Building A2

Registered No litigation declared Residential / Group Housing project

Panvelkar Nisarg Phase II Building A2

By Panvelkar Realty Pvt Ltd

RG-MH-06633 · RERA P51700054034 · Last updated on MahaRERA portal: 21 May 2026

Source: official MahaRERA filing

Red flags

  • Rs 10.00 crore secured on the land, in favour of Shriram Housing Finance Limited

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
2 of 11Construction stages donefurthest along: Basement (if any), 0%
56 of 57Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

Panvelkar Nisarg Phase II Building A2 is a Residential / Group Housing project by Panvelkar Realty Pvt Ltd in Thane, Maharashtra, registered with MahaRERA as P51700054034 on 27 Dec 2023. Possession is promised by 31 Dec 2026. 1 of the 57 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NamePanvelkar Nisarg Phase II Building A2
  • TypeResidential / Group Housing
  • Location
    • Joveli
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700054034
  • ReraGenie IDRG-MH-06633

Builder

  • NamePanvelkar Realty Pvt Ltd
  • Entity typeCompany
  • DirectorsVijay Ramchandra Panvelkar, Rahul Vijay Panvelkar
  • Declared earlier projects4 →

Key dates

this monthRegisteredDec 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Dec 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed66 files

Current status

2%1 of 57 units booked
16.4%Work done, per cost certificate

Figures as on 21 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building A2NA121254357

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

Building A2: 18% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes70%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,125 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofShriram Housing Finance Limited
Secured amountRs 10.00 crore
Declared on24 May 2025

Approvals and building plan

Sanctioning authorityKulgaon Badlapur Municipal Council
Permissible FSI2646.1
Proposed, not sanctioned2,646 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPanvelkar Plaza,Station Road,Ambernath East
Estimated costRs 7.38 cr
Cost incurredRs 1.21 cr
Work done16.36%
BuildingWingEstimatedIncurred
Building A2NARs 6.71 crRs 1.11 cr
-NARs 67.10 lakhRs 10.06 lakh

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSamarthy Engineers
EngineerAtul Kudtarkar & Associates
Chartered AccountantMangesh Ghanekar
Chartered AccountantVyanktesh Joshi
Chartered AccountantMonisha Kuperkar
Chartered AccountantASKA & Co
Chartered AccountantJoshi Kale & Associates
Chartered AccountantKirtane &Pandit
Chartered AccountantNikhil Pakhle
PartnerRole in project
Panvelkar Realty Pvt Ltd-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 A2 as on March 2026.pdf21 May 2026
Withdrawal Update Form 2File: Form 2 Nisarg A2 as on March 2026.pdf21 May 2026
Withdrawal Update Form 3File: Signed Form 3 of PRPL Nisarg Phase II A2__March 2026.pdf21 May 2026
Withdrawal Update Form 1File: Form 1 Nisarg A2 Oct25 to Dec25.pdf19 May 2026
Withdrawal Update Form 2File: Form 2 Nisarg A2 Q3 2025.pdf19 May 2026
Withdrawal Update Form 3File: Signed Form 3 of Panvelkar Nisarg A2 Bldg__December 2025.pdf19 May 2026
Withdrawal Update Form 1File: Form 1 Nisarg A2 Jul25 to Sept25.pdf11 May 2026
Withdrawal Update Form 2File: Form 2 Nisarg A2 as on September.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 Nisarg A2 as on September 2025.pdf11 May 2026
Withdrawal Update Form 1File: Form 1 Nisarg A2 Apr To June 25.pdf5 Feb 2026
Withdrawal Update Form 2File: Form 2 Nisarg A2 June-2025.pdf5 Feb 2026
Withdrawal Update Form 3File: Form 3 Nisarg A2 June-2025.pdf5 Feb 2026
Form 5 (FY 2024-2025)File: Signed Form 5 Nisarg for FY 2024-25.pdf22 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nisarg A2 Form 2 Jan To March 25 Sign.pdf22 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nisarg A2 Form 2 Jan To March 25 Sign.pdf22 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nisarg Building A2 Form 1 Jan To March 25.pdf13 May 2025
Disclosure of sold/ booked inventoryFile: Nisarg A2 Bldg Sold Unsold.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nisarg Building A2 Form 1 Oct To Dec 24.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: Nisarg A2 Bldg Sold Unsold (31 12 24).pdf21 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Nisarg Building A2 23-24.pdf21 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nisarg A2 Form 2 July To Sept 24.pdf16 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nisarg A2 Form 2 July To Sept 24.pdf16 Nov 2024
Disclosure of sold/ booked inventoryFile: Nisarg A2 Sold Unsold July To Sept 24.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nisarg Building A2 Form 1 July To Sept 24.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Panvelkar Nisarg Phase II A2 (Signed).pdf19 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nisarg Building A2 Form 1 Apr To June 24.pdf22 Jul 2024
Disclosure of sold/ booked inventoryFile: Nisarg Bldg A2 Sold Unsold Apr To June 24.pdf8 Jul 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seprate Bank Account RERA Nisarg A2 (Rev).pdf25 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nisarg Bldg A2 Form 2 (Jan To March 24).pdf22 May 2024
Details of encumbrances concerned to FinanceFile: prpl A2 shfl encumbrance certificate.pdf26 Apr 2024
Details of encumbrances concerned to LegalFile: prpl A2 shfl encumbrance certificate.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nisarg Building A2 Form 1 Jan To March 24.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Nisarg A2 Bldg Sold Unsold Jan To March 24.pdf17 Apr 2024
Proforma of Agreement for saleFile: Draft of Agreement For Sale.pdf26 Dec 2023
Deviation Report with respect to model copy of AgreementFile: Deviation report Agreememt(Rev).pdf20 Dec 2023
Details of encumbrances concerned to FinanceFile: Details of No Encumbrances.pdf18 Dec 2023
Details of encumbrances concerned to LegalFile: Details of No Encumbrances.pdf18 Dec 2023
Copy of the legal title reportFile: Title Report.pdf4 Dec 2023
Other - LegalFile: Supplementry Agreement (Land Purchase).pdf29 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A2 Form 1 (1).pdf18 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: A2 Form 2 (1).pdf18 Nov 2023
Layout approvalFile: A2 Sheet 1.pdf17 Nov 2023
Layout approvalFile: A2 Sheet 2.pdf17 Nov 2023
Copy of Layout Approval (in case of layout)File: A2 Sheet 1.pdf17 Nov 2023
Copy of Layout Approval (in case of layout)File: A2 Sheet 2.pdf17 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: Revised CC A1 A2.pdf17 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: Nisarg A2 Declaration for CC Validation.pdf17 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: APPENDIX-F FOR PLINTH COMPLETION BLDG NO A1.pdf17 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A2 Form 1.pdf17 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: A2 Form 2.pdf17 Nov 2023
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate.pdf2 Nov 2023
CERSAI detailsFile: 1 CERSAI details.pdf2 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf2 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow2 Nov 2023
Details of encumbrances concerned to FinanceFile: Details of No Encumbrances.pdf21 Oct 2023
Details of encumbrances concerned to LegalFile: Details of No Encumbrances.pdf21 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations.pdf20 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 2 Disclosure of Interest in Other Real Estate Organizations.pdf20 Oct 2023
Declaration in FORM BFile: Form B declaration_compressed.pdf13 Sep 2023
Proforma of Allotment letterFile: Model Form of Allotment Letter.pdf13 Sep 2023
Deviation Report with respect to Allotment letterFile: No Deviation letter ( Allotment letter).pdf5 Sep 2023
Building plan approvalFile: Sheet 1 of 4_compressed.pdf31 Aug 2023
Building plan approvalFile: Sheet 4 of 4_compressed.pdf31 Aug 2023
PAN CardFile: PRPL PAN CARD.pdf31 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Sheet 1 of 4_compressed.pdf31 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: Sheet 4 of 4_compressed.pdf31 Aug 2023

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Panvelkar Estate Stanford Phase IMankivali Badlapur E285CompletedDec 2018Late, Dec 2019
Panvelkar AquamarineGut No 3 Morivali Ambernath E262CompletedOct 2016May 2016
Panvelkar VelloziaS No 79 H No 2 Bhosale Nagar Badlapur E159CompletedDec 2014Jun 2014
Panvelkar Royal SquareS No 64 H No 12 Near Bharat College Hendre Pada Badlapur W122CompletedDec 2013May 2012

How this compares with Thane

2%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Panvelkar Nisarg Phase II Building A2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Joveli7,600+ in Thane

2 kmPanvelkar Nisarg Phase ICompleted 53Lapsed / revoked 14Other 31Dot size: filed unitsN

Filed coordinates, straight-line distance. 98 registered projects within 2 km.

Builder: Panvelkar Realty Pvt Ltd

Panvelkar Realty Pvt Ltd has 1 registration on MahaRERA, including Panvelkar Nisarg Phase II Building A2. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Panvelkar Nisarg Phase II Building A2 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Panvelkar Nisarg Phase II Building A2?

The registered promoter entity is Panvelkar Realty Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Panvelkar Nisarg Phase II Building A2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Panvelkar Nisarg Phase II Building A2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Panvelkar Nisarg Phase II Building A2?

The professionals named in the filing: Architect: Samarthy Engineers; Engineer: Atul Kudtarkar & Associates; Chartered Accountant: Mangesh Ghanekar; Chartered Accountant: Vyanktesh Joshi; Chartered Accountant: Monisha Kuperkar; Chartered Accountant: ASKA & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Panvelkar Nisarg Phase II Building A2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Panvelkar Nisarg Phase II Building A2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Panvelkar Nisarg Phase II Building A2 to a free account