Panvelkar Realty Pvt Ltd: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

Panvelkar Realty Pvt Ltd has 1 registration in this build, including Panvelkar Nisarg Phase II Building A2. Its filings disclose 4 earlier MahaRERA projects: 3 of 4 past projects completed on time.

1Registrations in this build
4Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Panvelkar Nisarg Phase II Building A2Thane, Maharashtra572%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Panvelkar Royal Square
31 Dec 201320 May 2012On time
Panvelkar Vellozia
31 Dec 201412 Jun 2014On time
Panvelkar Aquamarine
31 Oct 20162 May 2016On time
Panvelkar Estate Stanford Phase I
31 Dec 201831 Dec 2019+12 months

Frequently asked questions

How do I verify Panvelkar Realty Pvt Ltd as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Panvelkar Realty Pvt Ltd?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.