ReraGenieLog inGet a buyer report

Home / Browse projects / Dadra & Nagar Haveli / PALLADIUM ALCOVE

Registered No litigation declared Mixed project

PALLADIUM ALCOVE

By SEVEN - 9 DEVCON LLP

RG-MH-51660 · RERA P49600000157 · Last updated on MahaRERA portal: 8 May 2026

Source: official MahaRERA filing

Red flags

  • Rs 7.50 crore secured on the land, in favour of Bank of India

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Dadra & Nagar Haveli registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
11 of 33Construction stages doneacross 3 buildings; furthest along: Sanitary Fittings within the flats /..., 80%
135 of 162Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

PALLADIUM ALCOVE is a Mixed project by SEVEN - 9 DEVCON LLP in Dadra & Nagar Haveli, registered with MahaRERA as P49600000157 on 13 Jul 2023. Possession is promised by 31 Dec 2027. 27 of the 162 units on this registration are recorded sold or booked, and 11 of 33 construction stages are filed complete.

At a glance

Project

  • NamePALLADIUM ALCOVE
  • TypeMixed
  • Location
    • SILVASSA
    • Others
    • Dadra & Nagar Haveli
    • 396230
  • Pincode396230
  • RERA no.P49600000157
  • ReraGenie IDRG-MH-51660

Builder

  • NameSEVEN - 9 DEVCON LLP
  • Entity typePartnership
  • GSTIN26AEMFS8069P1ZW
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersVISHAL KISHORBHAI PANCHAL, HARDIK KISHORBHAI PANCHAL
  • Other registrations4 more →
  • Completed1 of 5
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on13 Jul 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed85 files

Current status

17%27 of 162 units booked
44.3%Work done, per cost certificate

Figures as on 8 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA1614682593
B WINGNA99442367

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 8 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 80%.

A WING36%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure29%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises2%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks34%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
B WING80%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
NA Plot Without Structure0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes30%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed156

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots156
Closed/Covered138
Open Space18
BuildingClosed/CoveredOpen SpaceTotal
A WING70070
B WING681886

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,618 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBank of India
Secured amountRs 7.50 crore
CERSAI search filedYes
Declared on20 May 2026

Approvals and building plan

Sanctioning authoritySILVASSA MUNICIPAL COUNCIL
Permissible FSI11500.62
Proposed, not sanctioned11,501 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOORSHRI DIXIT FALIA ANAVIL PANCH WADI
Estimated costRs 25.63 cr
Cost incurredRs 11.35 cr
Work done44.27%
BuildingWingEstimatedIncurred
A WINGNARs 16.87 crRs 3.07 cr
B WINGNARs 8.01 crRs 7.89 cr
-NARs 75.00 lakhRs 39.15 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARDIK PANCHAL
EngineerCHETAN H SAPARIYA
Chartered AccountantIshwarlal Chaplot
Chartered AccountantYOGESH KOTHARI
PartnerRole in project
SEVEN - 9 DEVCON LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Feb 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 01 FORM-1.PDF8 May 2026
Withdrawal Update Form 2File: 02 FORM-2.PDF8 May 2026
Withdrawal Update Form 3File: ALCOVE FORM 3 MARCH 2026 Signed.pdf8 May 2026
Form 2A (FY 2025-2026)File: ALCOVE FORM 2A 2026- signed.pdf8 May 2026
Layout approvalFile: Wing B - Plans.pdf21 Feb 2026
Layout approvalFile: Wing A - Plans - Highlighted.pdf21 Feb 2026
Withdrawal Update Form 1File: ALCOVE Form -1 OCT TO DEC 2025.pdf23 Jan 2026
Withdrawal Update Form 2File: ALCOVE Form 2 OCT TO DEC 2025.pdf23 Jan 2026
Withdrawal Update Form 3File: RERA form 3 FY 25-26 Q3 Signed.pdf23 Jan 2026
Withdrawal Update Form 1File: July to sep 2025 Form -1.pdf17 Jan 2026
Withdrawal Update Form 2File: July To Sep 2025 Form -2.pdf17 Jan 2026
Withdrawal Update Form 3File: Alcove Form 3 2025 form -3 Q2.pdf17 Jan 2026
Form 5 (FY 2024-2025)File: FORM-5 ALCOVE 2024-25 Signed.pdf12 Nov 2025
Form 1File: FORM-1 DEC 2024.PDF8 Jul 2025
Form 2File: 02 ALCOVE DEC 2024.pdf8 Jul 2025
Form 3File: Alcove Signed form 3 Dec 2024 Final Signed.pdf8 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and Booked Inventory.pdf8 Jul 2025
Form 1File: Form 1 PA.pdf7 Jul 2025
Form 2File: Form 2 PA.pdf7 Jul 2025
Form 3File: FORM-3(30-9-2023).pdf7 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Booked Inventory.pdf7 Jul 2025
Form 1File: oct to dec 2023 form -01.PDF7 Jul 2025
Form 2File: oct to dec 2023 form -2.PDF7 Jul 2025
Form 3File: FORM-3(30-12-2023).pdf7 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold bookes inventory.pdf7 Jul 2025
Form 2A (FY 2023-2024)File: Form 2A PA mar 2024.pdf7 Jul 2025
Form 2A (FY 2024-2025)File: Form 2A Alcove March-2025.pdf7 Jul 2025
Form 5 (FY 2023-2024)File: Alcove from 5 2023-24 Signed.pdf7 Jul 2025
Form 1File: 01 KISHAN BHAI KHARPADIYA FORM 1 (31 03 2024) (R01) form 1.PDF23 Jun 2025
Form 2File: 02 KISHAN BHAI KHARPADIYA FORM 2 (31 03 2024) (R01).pdf23 Jun 2025
Form 3File: FORM - 3.pdf23 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and Booked Inventory.pdf23 Jun 2025
Form 1File: Form 1 june 2024 seven 9 Devcon LLP (1).pdf23 Jun 2025
Form 2File: Form 2 June 2024 seven 9 Devcon LLP (1).pdf23 Jun 2025
Form 3File: FORM -3 jun 2024_Signed.pdf23 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and Booked Inventory.pdf23 Jun 2025
Form 1File: FORM -1 SEP 2024.PDF23 Jun 2025
Form 2File: FORM -2 SEP 2024.PDF23 Jun 2025
Form 3File: FORM 3 SEP 2024_Signed.pdf23 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and Booked Inventory.pdf23 Jun 2025
Form 1File: Form 1 Alcove March-2025.pdf23 Jun 2025
Form 2File: Form 2 Alcove March 2025.pdf23 Jun 2025
Form 3File: Form 3 Alcove March-2025 Q4 signed.pdf23 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and Booked Inventory.pdf23 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3 Alcove March-2025.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Form 2 Alcove March 2025.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Form 1 Alcove March-2025.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A Alcove March-2025.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Alcove Signed form 3 Dec 2024 Final Signed_compressed.pdf31 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Alcove from 5 2023-24 Signed.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM -3 jun 2024 Signed.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 SEP 2024 Signed_compressed.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: Form 1 PA.pdf11 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: 01 KISHAN BHAI KHARPADIYA FORM 1 (31 12 2023) (R01).pdf11 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: 01 KISHAN BHAI KHARPADIYA FORM 1 (31 03 2024) (R01).pdf11 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Form 2 PA.pdf11 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: 02 KISHAN BHAI KHARPADIYA FORM 2 (31 12 2023).pdf11 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: 02 KISHAN BHAI KHARPADIYA FORM 2 (31 03 2024).pdf11 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3 Palladium Alcove 30 Sep 2023 Seven 9 Devcon LLP.pdf11 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3 Palladium Alcove 31 Dec 2023 Seven 9 Devcon LLP.pdf11 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: Form 3 Palladium Alcove 31 March 2024 Seven 9 Devcon LLP.pdf11 May 2024
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A PA.pdf11 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 REG.pdf29 Jun 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE.pdf20 May 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCE.pdf20 May 2023
CERSAI detailsFile: CERSAI PALLADIUM ALCOVE.pdf20 May 2023
Details of encumbrances concerned to FinanceFile: NO ENCUMBERANCE.pdf10 May 2023
Details of encumbrances concerned to LegalFile: NO ENCUMBERANCE.pdf10 May 2023
Layout approvalFile: 8 APPROVED LAYOUT PLAN_compressed.pdf3 May 2023
Building plan approval or NA orderFile: 9 APPROVED BUILDING PLAN_compressed.pdf3 May 2023
PAN CardFile: PAN CARD.pdf3 May 2023
Copy of the legal title reportFile: TITLE SEARCH REPORT COMPRESSED.pdf3 May 2023
Copy of Layout Approval (in case of layout)File: 8 APPROVED LAYOUT PLAN_compressed.pdf3 May 2023
Building Plan Approval (IOD)File: 9 APPROVED BUILDING PLAN_compressed.pdf3 May 2023
Commencement CertificatesFile: CP.PDF3 May 2023
Declaration in FORM BFile: FORM B PROMOTER_compressed.pdf3 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1.PDF3 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Palladium Alcove Revised form 2_compressed.pdf3 May 2023
Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: ITR NOT APPLICABLE.pdf3 May 2023
Proforma of Agreement for saleFile: 13 PROFORMA OF AGREEMENT FOR SALE.pdf3 May 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
PALLADIUM SQUAREP49600000125SILVASSA, Dadra & Nagar Haveli2Feb 2022CompletedDec 2026Apr 2025

How this compares with Dadra & Nagar Haveli

17%of this project is bookeddistrict median 30%
10%of Dadra & Nagar Haveli projects moved their completion datethis one has not
28%of Dadra & Nagar Haveli registrations have lapsed or been cancelledthis one is on the register

Computed across the 210+ Dadra & Nagar Haveli projects on ReraGenie, from their own filings.

Keep PALLADIUM ALCOVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SILVASSA210+ in Dadra & Nagar Haveli

Builder: SEVEN - 9 DEVCON LLP

SEVEN - 9 DEVCON LLP has 5 registrations on MahaRERA, including PALLADIUM SQUARE and PALLADIUM ALCOVE. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Dadra & Nagar Haveli district page.

Frequently asked questions

What are my rights if PALLADIUM ALCOVE is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PALLADIUM ALCOVE?

The registered promoter entity is SEVEN - 9 DEVCON LLP, a partnership as per the filing. Its GSTIN 26AEMFS8069P1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PALLADIUM ALCOVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PALLADIUM ALCOVE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PALLADIUM ALCOVE?

The professionals named in the filing: Architect: HARDIK PANCHAL; Engineer: CHETAN H SAPARIYA; Chartered Accountant: Ishwarlal Chaplot; Chartered Accountant: YOGESH KOTHARI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PALLADIUM ALCOVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PALLADIUM ALCOVE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PALLADIUM ALCOVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.