Home / Browse projects / Dadra & Nagar Haveli / PARADISE ONE

Registered No litigation declared Mixed project

PARADISE ONE

By JMB REALTY

RG-MH-00991 · RERA P49600000141 · Last updated on MahaRERA portal: 18 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Dadra & Nagar Haveli registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 12 months from the original
34 of 55Construction stages doneacross 6 buildings; furthest along: Basement (if any), 90%
118 of 258Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

PARADISE ONE is a Mixed project by JMB REALTY in Dadra & Nagar Haveli, registered with MahaRERA as P49600000141 on 26 Sep 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 140 of the 258 units on this registration are recorded sold or booked, and 34 of 55 construction stages are filed complete.

At a glance

Project

  • NamePARADISE ONE
  • TypeMixed
  • Location
    • SURVEY NO. 30/1/2P
    • VILLAGE - SAMARVARNI
    • Others
    • Dadra & Nagar Haveli
    • 396230
  • Pincode396230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P49600000141
  • ReraGenie IDRG-MH-00991

Builder

  • NameJMB REALTY
  • Entity typePartnership
  • PartnersMUKUND KABABHAI GAJERA, DINESHBHAI PARSOTTAMBHAI AVAIYA, HITESH B MANGUKIYA, KHANJAN HIMANSHUBHAI KAVANI, JITENDRA DAYABHAI DHOLA, KISHORBHAI DAYABHAI DHOLA, MAYUR KUMAR VEKARIYA, HARDIK MADHAVJIBHAI PATEL

Key dates

this monthRegisteredSep 2022First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Sep 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings5 building records
  • Documents filed79 files

Current status

54%140 of 258 units booked
77.5%Work done, per cost certificate

Figures as on 18 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA111134539
WING BNA111168876
WING CNA111168876
WING DNA111154054
WING ENA6612012

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

34 of 55 construction stages are filed complete across 6 buildings. The stage furthest along is Basement (if any), at 90%.

WING A19%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks8%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B65%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.73%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
WING C82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING E86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed245

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots245
Closed/Covered215
Open Space30
BuildingClosed/CoveredOpen SpaceTotal
WING A41647
WING B54660
WING C68674
WING D28634
WING E24630

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,550 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jul 2025

Approvals and building plan

Sanctioning authorityDADRA AND NAGAR HAVELI PLANNING & DEVELOPMENT AUTHORITY
Permissible FSI12473.38
Proposed, not sanctioned12,473 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSILVASSA
Estimated costRs 22.21 cr
Cost incurredRs 17.20 cr
Work done77.47%
BuildingWingEstimatedIncurred
WING BNARs 5.73 crRs 5.22 cr
WING CNARs 5.65 crRs 5.65 cr
WING DNARs 4.43 crRs 4.43 cr
WING ANARs 4.00 crRs 39.39 lakh
WING ENARs 1.51 crRs 1.51 cr
-NARs 88.98 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCity Architect
ArchitectHARDIK PANCHAL
EngineerCHETAN H SAPARIYA
Chartered AccountantKUNAL B SHAH
Chartered AccountantPRATIKA CHAWLA
PartnerRole in project
JMB REALTY-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA23032620337Mar 2026 → Mar 2027

Reason as filed by the promoterProject is not completed need further time for development

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 MAR 2026.pdf18 Apr 2026
Withdrawal Update Form 2File: FORM 2 MAR 2026.pdf18 Apr 2026
Withdrawal Update Form 3File: FORM 3 MAR 2026_compressed.pdf18 Apr 2026
Form 2A (FY 2025-2026)File: FORM 2A MAR 2026.pdf18 Apr 2026
Form 2A (FY 2024-2025)File: FORM 2A MAR 2025.pdf18 Apr 2026
Form 5 (FY 2024-2025)File: FORM 5 MAR 2025.pdf20 Jan 2026
Withdrawal Update Form 1File: FORM 1 DEC 2025_compressed.pdf17 Jan 2026
Withdrawal Update Form 2File: FORM 2 DEC 2025.pdf17 Jan 2026
Withdrawal Update Form 3File: FORM 3 DEC 2025_compressed.pdf17 Jan 2026
Withdrawal Update Form 1File: rera 1 sept 2025_compressed.pdf18 Oct 2025
Withdrawal Update Form 2File: rera 2 sept 2025.pdf18 Oct 2025
Withdrawal Update Form 3File: Rera form 3 sept 2025_compressed.pdf18 Oct 2025
Withdrawal Update Form 1File: FORM 1 JUNE 2025_compressed.pdf20 Jul 2025
Withdrawal Update Form 2File: FORM 2 JUNE 2025.pdf20 Jul 2025
Withdrawal Update Form 3File: FORM 3 JUNE 2025.pdf20 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 MAR 2025.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 MAR 2025_compressed.pdf17 Apr 2025
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: FORM 2 MAR 2025.pdf17 Apr 2025
Form 2AFile: FORM 2A MAR 2025.pdf17 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 MAR 23.pdf21 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 MAR 24.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: rera 1 mach 2023.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: rera 1 june 2023.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 SEPT 2023.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: rera 1 dec 2023.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: rera 1 march 2024.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: rera 1 june 2024_compressed.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: 01 PARADISE-1 FORM 1 (30 09 2024) (R01)_compressed.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: 01 FORM-1_compressed.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: rera 1 dec-2022.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 JUNE 2024.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: rera 3 dec 2024 SIGN.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: rera 3 sept 2024_compressed.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: rera 3 march 2024_compressed.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: rera form 3 sept 2023_compressed.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3 JUNE 2023 SIGN_compressed.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: JMB REALTY FORM 3 MAR 2023.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: JMB REALTY FORM 3 DEC 22_compressed.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: rera 3 dec 2023.pdf28 Jan 2025
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: rera 2 dec 2023.pdf28 Jan 2025
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: 02 PARADISE-1 FORM 2 (31 12 2024) (R01).pdf28 Jan 2025
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: 02 PARADISE-1 FORM 2 (30 09 2024) (R01).pdf28 Jan 2025
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: rera 2 june 2024.pdf28 Jan 2025
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: rera 2 march 2024.pdf28 Jan 2025
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: FORM 2 SEPT 2023.pdf28 Jan 2025
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: rera 2 june 2023.pdf28 Jan 2025
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: rera 2 march 2023.pdf28 Jan 2025
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: rera 2 dec 2022.pdf28 Jan 2025
Form 2AFile: rera 2a march 2023.pdf28 Jan 2025
Form 2AFile: rera 2a dec 2023.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: rera 1 30-9-22.pdf12 Mar 2024
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: rera 2 30-9 22.pdf12 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: JMB REALTY FORM 1 NEW.pdf13 Sep 2022
Layout approvalFile: LAYOUT PLAN.pdf2 Sep 2022
Building plan approval or NA orderFile: BUILDING 1.pdf2 Sep 2022
Building plan approval or NA orderFile: BUILDING 2.pdf2 Sep 2022
Building plan approval or NA orderFile: BUILDING 3.pdf2 Sep 2022
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf2 Sep 2022
Building Plan Approval (IOD)File: BUILDING 1.pdf2 Sep 2022
Building Plan Approval (IOD)File: BUILDING 2.pdf2 Sep 2022
Building Plan Approval (IOD)File: BUILDING 3.pdf2 Sep 2022
Commencement CertificatesFile: DECLARATION_JMB CP.pdf18 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: FORM 3.pdf20 Jul 2022
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE CERTIFICATE.pdf7 Jul 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SELF- DECLARATION ABOUT SEPARATE BANK ACCOUNT.pdf7 Jul 2022
Details of encumbrances concerned to LegalFile: NOT APPLICABLE.pdf29 Jun 2022
Deviation Report with respect to Allotment letterFile: NOT APPLICABLE.pdf29 Jun 2022
Deviation Report with respect to model copy of AgreementFile: NOT APPLICABLE.pdf29 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19) (UT)File: NOT APPLICABLE.pdf11 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20) (UT)File: NOT APPLICABLE.pdf11 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) (UT)File: NOT APPLICABLE.pdf11 Jun 2022
CERSAI detailsFile: CERSAI REPORT.pdf10 Mar 2022
Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: ITR AND NOT APPLICABLE.pdf10 Mar 2022
PAN CardFile: PAN OF THE FIRM.pdf9 Mar 2022
Copy of the legal title reportFile: TITLE SEARCH REPORT CERTIFICATE.pdf9 Mar 2022
Declaration in FORM BFile: FORM B.pdf9 Mar 2022
Certificates of Engineer (Form 2) (UT) (Mandatory for only ongoing project)File: FORM 2.pdf9 Mar 2022
Proforma of Allotment letterFile: Proforma of Allotment Letter and Agreement for Sale.pdf9 Mar 2022
Form 2AFile: FORM 2A.pdf9 Mar 2022

How this compares with Dadra & Nagar Haveli

54%of this project is bookeddistrict median 30%
10%of Dadra & Nagar Haveli projects moved their completion datethis one moved by 12 months
28%of Dadra & Nagar Haveli registrations have lapsed or been cancelledthis one is on the register

Computed across the 210+ Dadra & Nagar Haveli projects on ReraGenie, from their own filings.

Keep PARADISE ONE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILLAGE - SAMARVARNI210+ in Dadra & Nagar Haveli

2 kmPARADISE ONECompleted 17Lapsed / revoked 6Other 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 42 registered projects within 2 km.

Builder: JMB REALTY

JMB REALTY has 1 registration on MahaRERA, including PARADISE ONE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Dadra & Nagar Haveli district page.

Frequently asked questions

What are my rights if PARADISE ONE is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARADISE ONE?

The registered promoter entity is JMB REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARADISE ONE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARADISE ONE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARADISE ONE?

The professionals named in the filing: Architect: City Architect; Architect: HARDIK PANCHAL; Engineer: CHETAN H SAPARIYA; Chartered Accountant: KUNAL B SHAH; Chartered Accountant: PRATIKA CHAWLA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARADISE ONE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARADISE ONE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARADISE ONE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.