PALAI COMMERCIAL COMPLEX

By DHANJI GELABHAI GALA

RG-MH-76368 · RERA P51900011317 · Last updated on MahaRERA portal: 13 Sep 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 29 months past the filed date
  • Completion date moved by 58 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
May 2024Possession promised29 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

PALAI COMMERCIAL COMPLEX is a Commercial project by DHANJI GELABHAI GALA in Mumbai City, Maharashtra, registered with MahaRERA as P51900011317 on 31 Aug 2017. Possession was promised by 31 May 2024 and is now 29 months past that date. The completion date has moved by 58 months from the original filing.

At a glance

Project

  • NamePALAI COMMERCIAL COMPLEX
  • TypeCommercial
  • Location
    • Dadar West
    • Senapati Bapat Marg
    • Mumbai City
    • 400028
  • Pincode400028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900011317
  • ReraGenie IDRG-MH-76368

Builder

  • NameDHANJI GELABHAI GALA
  • Entity typeIndividual
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked

Key dates

29 months past promisethis monthRegisteredAug 2017First promiseJul 2019Revised toMay 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Aug 2017
  • Promised completion31 May 2024
  • Revised completionRevised to 31 May 2024 (originally 31 Jul 2019)
  • Buildings1 building record
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PALAI COMMERCIAL COMPLEXNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

PALAI COMMERCIAL COMPLEX: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed49

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots49
Closed/Covered49

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,479 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3241.0
Proposed, not sanctioned2,700 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMATUNGA, MUMBAI 400019

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectACE CONSULTANTS
PartnerRole in project
DHANJI GELABHAI GALA-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900001518Jul 2019 → Jul 2020

Reason as filed by the promoterDear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘Palai Commercial Complex’is registered on the MahaRERA webportal vide Registration Number: P51900011317. The registration certificate was issued for the period ending 31 July 2019 (A copy of the certificate is attached herewith as Annexure 1). We would like to request you to extend the date of completion by a further eleven months i.e 30 June 2020. With reference to the above, we would also like to inform your goodself that the construction and all the major allied activities for the buil

EXT51900010891Jul 2019 → Dec 2022

Reason as filed by the promoterDear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘Palai Commercial Complex’ is registered on the MahaRERA webportal vide Registration Number: P51900011317. The registration certificate was issued for the period ending 31 January 2020 (A copy of the certificate is attached herewith as Annexure 1). We had applied to your goodself to extend the date of completion and the same was accepted with the revised date of completion being 31 January 2021 (A copy of the certificate is attached herewith as Annexure 2). With reference to the above, we

EXT51900017145Jul 2019 → May 2024

Reason as filed by the promoterThe Secretary, Maharashtra Real Estate Regulatory Authority 3rd Floor, A-Wing, Slum Rehabilitation Authority, Administrative Building, Anant Kanekar Marg, Bandra (E), Mumbai 400051 SUBJECT: Extension of Date of Completion of the project ‘Palai Commercial Complex’ RERA Registration Number: P51900011317 Dear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘Palai Commercial Complex’is registered on the MahaRERA webportal vide Registration Number: P51900011317. The registration certificate was issued for the period ending 31 July 2019 (A copy of

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: form 3 pcc june.pdf13 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PCC- Architects_Certificate_NEW.pdf12 Sep 2023
Disclosure of sold/ booked inventoryFile: PCC_Sold flats.pdf12 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PCC- Architects_Certificate_NEW.pdf8 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_230908100421_001_NEW.pdf8 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_230908100403_001_NEW.pdf8 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_230908100403_001_NEW.pdf8 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_230908100403_001_NEW.pdf8 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2717_230821120340_001.pdf22 Aug 2023
Form 2AFile: PT-Form - 2a - N.pdf22 Aug 2023
Declaration in FORM BFile: 2634_230802122901_001.pdf10 Aug 2023
Details of encumbrancesFile: PCC.pdf18 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 PCC.pdf8 Oct 2021
Declaration about Commencement CertificateFile: PCC_CC Declaration.pdf1 Oct 2021
Disclosure of sold/ booked inventoryFile: PCC_Sold flats_compressed.pdf1 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 PCC.pdf25 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: PCC SOCIETY CERTIFICATE.pdf22 Jul 2021
Certificates of CA (Form 3)File: Form 3 Palai Commercial Complex.pdf17 Oct 2019
Certificates of CA (Form 5)File: FORM 5 PCC.pdf11 Oct 2019
Certificates of CA (Form 3)File: PALAI COMMERCIAL COMPLEX (1).pdf23 Jul 2019
Form 2AFile: PCC FORM-2 (1).pdf19 Jun 2019
Certificates of CA (Form 3)File: PCC (1).pdf19 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: further CC Palai COmm Complex.pdf8 Jan 2019
Certificates of CA (Form 5)File: FORM 5 PCC.pdf13 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2, Palai Commercial Complex.pdf9 Oct 2018
Certificates of CA (Form 3)File: Palai Commercial Complex.pdf8 Oct 2018
Certificates of CA (Form 3)File: FORM 5 PCC.pdf1 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect_certificate.pdf14 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect_certificate.pdf14 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect_certificate.pdf14 Jul 2018
Certificates of CA (Form 3)File: PCC - FORM 3.pdf11 Jul 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: PCC-RERA- formation of society Intimation.pdf29 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1.pdf6 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf6 Dec 2017
Certificates of CA (Form 3)File: Palai Commercial Complex.pdf6 Dec 2017
Details of encumbrancesFile: PALAI COMM COMPLEX.pdf28 Nov 2017
Layout approvalFile: 13-Iod Approved Plan_4.pdf31 Jul 2017
Building plan approvalFile: 13-Iod Approved Plan.pdf31 Jul 2017
PAN CardFile: 1-Pan Card.pdf31 Jul 2017
Copy of the legal title reportFile: 2-rectification letter of slum declaration.pdf31 Jul 2017
Copy of the legal title reportFile: 3-Amended Title , 20,02,2015.pdf31 Jul 2017
Copy of the legal title reportFile: 1-TITLE.pdf31 Jul 2017
Details of encumbrancesFile: 08-01-2017(3).pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: 13-Iod Approved Plan_4.pdf31 Jul 2017
Building Plan Approval (IOD)File: 13-Iod Approved Plan.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 12-CC.pdf31 Jul 2017
Declaration in FORM BFile: 06 undertaking.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 08-01-2017(2) (1).pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 PCC.pdf31 Jul 2017
Certificates of CA (Form 3)File: PCC CA CERTIFICATE.pdf31 Jul 2017
Proforma of Allotment letterFile: Allotment format.PDF31 Jul 2017
Proforma of Allotment letterFile: 05 Agreement.pdf31 Jul 2017

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 58 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PALAI COMMERCIAL COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Senapati Bapat Marg780+ in Mumbai City

2 kmPALAI COMMERCIAL COMPLEXCompleted 62Lapsed / revoked 57Other 86Dot size: filed unitsN

Filed coordinates, straight-line distance. 205 registered projects within 2 km.

Builder: DHANJI GELABHAI GALA

DHANJI GELABHAI GALA has 3 registrations on MahaRERA, including RAMSWAROOP PALAI TOWER and PALAI COMMERCIAL COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that PALAI COMMERCIAL COMPLEX shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PALAI COMMERCIAL COMPLEX is delayed beyond 31 May 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PALAI COMMERCIAL COMPLEX?

The registered promoter entity is DHANJI GELABHAI GALA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PALAI COMMERCIAL COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PALAI COMMERCIAL COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PALAI COMMERCIAL COMPLEX?

The professionals named in the filing: Architect: ACE CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PALAI COMMERCIAL COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PALAI COMMERCIAL COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PALAI COMMERCIAL COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.