Home / Browse projects / Thane, Maharashtra / ORBIS PHASE 1

Registered Litigation declared Residential / Group Housing project

ORBIS PHASE 1

RG-MH-96438 · RERA PR1331012601575 · Last updated on MahaRERA portal: 5 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
Jump to the 20 documents Report an error

ORBIS PHASE 1 is a Residential / Group Housing project by INFOPARK DEVELOPERS PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as PR1331012601575 on 18 Aug 2026. Possession is promised by 31 Aug 2032.

At a glance

Project

  • NameORBIS PHASE 1
  • TypeResidential / Group Housing
  • Location
    • MIDC 30m Central Road
    • Ghansoli
    • Navi Mumbai (M Corp.)
    • Thane
    • 400701
  • Pincode400701
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1331012601575
  • ReraGenie IDRG-MH-96438

Builder

  • NameINFOPARK DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU24100MH1968PTC014142
  • GSTIN27AAACI0958C2ZU

Key dates

todayRegisteredAug 2026PromisedAug 2032

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Aug 2026
  • Promised completion31 Aug 2032
  • Revised completionNone
  • Buildings2 building records
  • Documents filed20 files

Current status

0%0 of 522 units booked

Figures as on 5 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 6NA44422980298
TOWER 7NA44422240224

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 5 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing.

TOWER 60%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TOWER 70%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNo0%
Community BuildingsNo0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed810

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots810
Mechanical492
Podiums / Upper Parking Floor318
BuildingMechanicalPodiums / Upper Parking FloorTotal
TOWER 6148224372
TOWER 734494438

Land and ownership

Land area190,670 sq m
Promoter owns the landYes
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Aug 2026

Approvals and building plan

Permissible FSI65877.62
Proposed, not sanctioned65,878 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA.

Separate project accountDeclared
Bank branchEXPRESS TOWERS,GROUND FLOOR,NARIMAN POINT,MUMBAI 400021

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPARIN SHAH ARCHITECTS
EngineerJACOB BASTYAW DSOUZA
Chartered AccountantNehali Doshi
PartnerRole in project
INFOPARK DEVELOPERS PRIVATE LIMITED-

Litigation declared2

CaseCourtStatus
9536 of 2018/2018Bombay high courtOngoing
WRIT PETITION NO.147 OF 2022/2020BOMBAY HIGH COURTOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

Documents filed20

As listed on the registration. The files themselves are on the MahaRERA portal.

DocumentUploaded
Layout Plan tower 6 and 7 1-1 (1)5 Aug 2026
Approved plan tower 7-2-2_11zon5 Aug 2026
approved plan tower 7-3-3_11zon5 Aug 2026
approved plan tower 7-4-45 Aug 2026
approved plan tower 7-5-55 Aug 2026
approved plan tower 7-6-65 Aug 2026
approved plan tower 7-7-75 Aug 2026
approved plan tower 7-8-85 Aug 2026
approved plan tower 7-9-95 Aug 2026
approved plan tower 7-10-105 Aug 2026
approved plan tower 6-11-115 Aug 2026
approved plan tower 6-12-125 Aug 2026
approved plan tower 6-13-135 Aug 2026
approved plan tower 6-14-145 Aug 2026
approved plan tower 6-15-155 Aug 2026
approved plan tower 6-16-165 Aug 2026
approved plan tower 6-17-175 Aug 2026
approved plan tower 6-18-185 Aug 2026
approved plan tower 6-19-195 Aug 2026
Annexure A _ Declaration cum Affidavit5 Aug 2026

How this compares with Thane

0%of this project is bookeddistrict median 27%
23%of Thane projects moved their completion datethis one has not
24%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,552 Thane projects on ReraGenie, from their own filings.

Track ORBIS PHASE 1

Save this project to your account and get an email when its filing changes: status, dates, complaints, new documents. Free during the pilot beta.

How alerts work

Other projects near Ghansoli7,552 in Thane

Builder: INFOPARK DEVELOPERS PRIVATE LIMITED

INFOPARK DEVELOPERS PRIVATE LIMITED has 1 registration on MahaRERA, including ORBIS PHASE 1. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ORBIS PHASE 1 is delayed beyond 31 Aug 2032?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ORBIS PHASE 1?

The registered promoter entity is INFOPARK DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U24100MH1968PTC014142 and GSTIN 27AAACI0958C2ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ORBIS PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ORBIS PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ORBIS PHASE 1?

The professionals named in the filing: Architect: PARIN SHAH ARCHITECTS; Engineer: JACOB BASTYAW DSOUZA; Chartered Accountant: Nehali Doshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ORBIS PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Planning to buy here? The Rs 499 buyer report adds red flags, the progress-versus-promise read, this promoter's other registrations and what the filed documents say, plus a ZIP of every document on the filing. It includes the Rs 299 project watch free for 90 days: an email in plain words every time this project's filing changes. See a real sample report before you buy. Get the buyer report · Rs 499
Studying this micro-market? The developer project analysis maps every registration within 5 km of this project from filed coordinates, reads what the market absorbs and what competes, prices the parcel, and takes the promoter's whole book apart, facts with their N, never a verdict. See a complete sample first. Get the developer analysis · Rs 2,999

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ORBIS PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.