Home / Browse projects / Thane, Maharashtra / Goldcrest Residency - Phase 2

Registered Litigation declared Residential / Group Housing project

Goldcrest Residency - Phase 2

By SAVITA HOMEMAKERS LLP

RG-MH-24985 · RERA P51700010579 · Last updated on MahaRERA portal: 11 May 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 92 complaints at MahaRERA
  • Completion date moved by 69 months
  • 7 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 69 months from the original
18 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 97%
0 of 316Units unsoldnot recorded sold or booked
92Complaints at MahaRERAon this registration
Jump to the 224 documents Report an error

Goldcrest Residency - Phase 2 is a Residential / Group Housing project by SAVITA HOMEMAKERS LLP in Thane, Maharashtra, registered with MahaRERA as P51700010579 on 31 Aug 2017. Possession is promised by 31 Mar 2027. The completion date has moved by 69 months from the original filing. 316 of the 316 units on this registration are recorded sold or booked, and 18 of 33 construction stages are filed complete. 92 complaints are on record with the regulator.

At a glance

Project

  • NameGoldcrest Residency - Phase 2
  • TypeResidential / Group Housing
  • Location
    • NEW PALM BEACH ROAD
    • GHANSOLI
    • Navi Mumbai (M Corp.)
    • Thane
    • 400701
  • Pincode400701
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700010579
  • ReraGenie IDRG-MH-24985

Builder

  • NameSAVITA HOMEMAKERS LLP
  • Entity typePartnership
  • PartnersViivek M Jain, Madanlal Pukhraj Jain, Savita Madanlal Jain, Prachi Akkshay Jain, Ashika Viivek Jain
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJun 2021Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Jun 2021)
  • Buildings3 building records
  • Documents filed224 files

Current status

100%316 of 316 units booked
88.4%Work done, per cost certificate

Figures as on 11 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Harmony - Wing BNA302591091
Peace - Wing CNA30251340134
Pride - Wing ANA302591091

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 11 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 97%.

Harmony - Wing B98%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises96%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.94%
Peace - Wing C96%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises81%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.91%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
Pride - Wing A98%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.96%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.93%

Progress on shared amenities15

As on 11 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes96%
Water SupplyYes88%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes85%
Street LightingYes93%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes97%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes91%
Electrical meter room, sub-station, receiving stationYes93%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed307

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots307
Closed/Covered306
Open Space1
BuildingClosed/CoveredOpen SpaceTotal
Harmony - Wing B88088
Peace - Wing C1301131
Pride - Wing A88088

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,025 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on18 Jun 2025

Approvals and building plan

Sanctioning authorityNavi Mumbai Municipal Corporation
Permissible FSI11137.91
Proposed, not sanctioned11,138 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchINDUSIND HOUSE 425 DADASAHEB BHADKAMKAR MARG MUMBAI 400004
Estimated costRs 134.81 cr
Cost incurredRs 119.21 cr
Work done88.43%
BuildingWingEstimatedIncurred
Peace - Wing CNARs 42.34 crRs 34.49 cr
Harmony - Wing BNARs 31.21 crRs 28.78 cr
Pride - Wing ANARs 31.07 crRs 28.45 cr
-NARs 30.19 crRs 27.49 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSoyuz Talib
EngineerAli Abbas Jaffrey
Chartered AccountantK KAveria and Co.
Chartered AccountantNitesh Jain
PartnerRole in project
SAVITA HOMEMAKERS LLP-

Extensions applied for7

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700009982Jun 2021 → Jun 2022

Reason as filed by the promoterForce Majeure as defined under RERA to mean "a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project". The Govt., looking at the COVID scenario across the country since March 2020 have already declared the current pandemic as force majeure adversely affecting development of real estate projects. The ongoing pandemic situation which resulted in reverse migration of the workers to their native places and break in supply chain of the construction material causing an adverse impact on the construct

EXT51700013366Jun 2021 → Dec 2023

Reason as filed by the promoterDue to space constraint the Reasons for Extension of the Project has been uploaded hereunder. You are requested to kindly go thru the same & accord your consent for Extension of the Project. We sincerely assure your good offices that the Project would be completed along with O.C & all amenities as mentioned well within Dec 2023.

EXT51700024214Jun 2021 → Dec 2024

Reason as filed by the promoterPhase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc have been obtained and OC is expected shortly. For obtaining the final OC and completion of balance amenities in the project, it is just and necessary to obtain RERA extension. Exigencies faced by the Promoter resulting delay in completion of the project include: i. Inclusive Housing Scheme imposed ii. COVID phase of 2 years creating unprecedented challenges i

EXT51700018457Jun 2021 → Jun 2024

Reason as filed by the promoterPhase II comprise Wing A, B &C of which Wing A&B Part OC has been received on 11th July 2023 and the possession of flats handed over. Further, application for OC for Balance area is currently under process. For obtaining the final OC and completion of balance amenities in the project, it is deemed necessary to obtain RERA extension so that all approvals can be obtained during the project validity. Impediments/ exigencies faced by the Project Proponent in the past from time to time resulting delay in completion of amenities/construction mentioned hereunder: i. Inclusive Housing Scheme imposed c

EXT51700025812Jun 2021 → Jun 2025

Reason as filed by the promoterPhase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc have been obtained and OC is expected shortly. For obtaining the final OC and completion of balance amenities in the project, it is just and necessary to obtain RERA extension. Exigencies faced by the Promoter resulting delay in completion of the project include: i. Inclusive Housing Scheme imposed ii. COVID phase of 2 years creating unprecedented challenges i

EA30062501867Jun 2021 → Mar 2026

Reason as filed by the promoterPhase II comprise Wing A, B &C of which Wing A&B Part OC upto 26th Floor has been received on 11th July 2023. An OC application for Wing C has already been made and all NOCs including CFO NOC, Health NOC, Debris NOC, Tree NOC, MHADA NOC etc have been obtained. Part OC for C Wing is expected shortly. For obtaining the final OC and completion of balance amenities in the project, it is just and necessary to obtain RERA extension. Exigencies faced by the Promoter resulting delay in completion of the project include: (i) Inclusive Housing Scheme imposed ii. COVID phase of 2 years creating unprecede

EA11052620901Jun 2021 → Mar 2027

Reason as filed by the promoterPhase II comprises Wings A, B, and C. Full applications for Occupancy Certificate (OC) have been submitted for all three wings. In respect of Wings A and B, Part Occupancy Certificate has been received up to the 26th floor on 11th July 2023. In respect of Wing C, Part Occupancy Certificate has been received up to the 20th floor on 1st July 2025. In order to obtain the Final Occupancy Certificate for the entire Phase II project and to complete the balance amenities, it is just, necessary, and in the interest of justice that an extension of the project registration under RERA be granted. Exigenc

Litigation declared2

CaseCourtStatus
000385/2016Supreme Court of Indiato be listed for final hearing before the regular bench
97/2015High court of Bombayto be listed for final hearing before the regular bench

Complaints filed with MahaRERA92

Case no.ComplainantRespondentFiled
CC006000000192330Sheetal ShirkeSavita Homemakers LLP08/09/2020
CC006000000193706Bharat KudalkarSavita Homemakers LLP12/08/2020
CC006000000195050MAHESH SHIVAJI DIGHEM/S. SAVITA HOMEMAKERS LLP01/12/2020
CC006000000198702Sandeep Satyawan ParabSavita Home Makers LLP17/10/2021
CC006000000199170Laxmikant Kolge,Suchitra KolgeSavita Home Makers LLP28/11/2021
CC006000000209942Rohan Darekar, Lata DarekarSavita Homemakers LLP07/02/2022
CC006000000398053Rohan Rohidas DarekarSavita Homemakers LLP03/11/2023
CC006000000210412Mr.Bajirao Kolhe Mrs Manisha Kolhesavita homemaker llp15/03/2022
CC006000000210423Savita Homemakers LLPSandeep Parab17/03/2022
CC006000000540732Akkshay JainSandeep Satyawan Parab10/06/2024
CC006000000591532Akkshay JainMAYUR RAMCHANDRA AKADE13/08/2024
CC006000000591534Akkshay JainLAXMIKANT POPAT KOLGE13/08/2024
CC006000000220642Suraj BhushannawarSAVITA HOMEMAKERS LLP31/03/2022
CC006000000220709Oawis IdrisSavita Homemakers LLP25/04/2022
CC006000000220853Nikhil RaoM/s Savita Homemakers LLP17/04/2022
CC006000000220895Arunkumar Upendra RaiM/s Savita Homemakers LLP20/04/2022
CC006000000220947Tushar korgaonkarSavita Home Makers LLP24/04/2022
CC006000000398062Tushar korgaonkarSavita Homemakers LLP04/11/2023
CC006000000221106Vijay ChavanSavita Home Makers LLP06/05/2022
CC006000000398037Vijay ChavanSAVITA HOMEMAKERS LLP01/11/2023
CC006000000221107chandrakant KhareSavita Home Makers LLP06/05/2022
CC006000000398059chandrakant KhareSavita Homemakers LLP03/11/2023
CC006000000231283Mayur Ramchandra AkhadeM/s Savita Homemakers LPP24/05/2022
CC006000000251359Sri Rama Chandra Murty JokaSavita Homemakers LLP05/06/2022
CC006000000251411Jeevan JainSavita Home Makers LLP10/06/2022
CC006000000292400Raviteja YanamandraSavita Home Makers LLP19/08/2022
CC006000000292745Hitesh Dhanraj PaliwalSavita Homemakers LLP19/09/2022
CC006000000292746Naresh Dhanraj PaliwalSavita Homemakers LLP19/09/2022
CC006000000302931udhayasankar shanmugasundaramSavita Homemakers LLP05/10/2022
CC006000000398057udhayasankar shanmugasundaramSavita Homemakers LLP03/11/2023
CC006000000303168ramkrishna kamathSavita Home Makers LLP28/10/2022
CC006000000303761Harshal SonawaneSavita Home Makers LLP22/12/2022
CC006000000323766Arun AgrawalSavita Homemakers LLP23/12/2022
CC006000000333878Shivanand katakdhondSavita Home makers LLP03/01/2023
CC006000000333954shailesh dSavita Home makers LLP14/01/2023
CC006000000364585Parag ShringarpureSavita Homemakers LLP03/03/2023
CC006000000374848Maninder Singh BhumraSavita Homemakers LLP20/03/2023
CC006000000374910mohandas shettySavita Home makers LLP23/03/2023
CC006000000374967Bhanudas NakadeSavita Homemakers LLP27/03/2023
CC006000000374989Deepak RoundhalSavita Home Makers LLP28/03/2023
CC006000000375315Mahesh Ashok MordeSavita Homemakers LLP18/04/2023
CC006000000375400Avinash PatilSavita Homemakers LLP26/04/2023
CC006000000375385Dinesh BhanushaliSavita Homemakers LLP24/04/2023
CC006000000375381Shivaji MindeSavita Homemakers LLP24/04/2023
CC006000000375387maruti mindeSavita Homemakers LLP25/04/2023
CC006000000395504mayur pawarSavita Homemakers LLP03/05/2023
CC006000000395509namrata desaiSavita Homemakers LLP03/05/2023
CC006000000395525Akash GhadgeSavita Homemakers LLP04/05/2023
CC006000000395542Meraj KhanSavita Homemakers LLP05/05/2023
CC006000000395840yash gajraSavita Home Makers LLP17/05/2023
CC006000000395838Ayandeep MSavita Home Makers LLP17/05/2023
CC006000000395851Vaibhav JadhavSavita Home Makers LLP18/05/2023
CC006000000395995Dinesh R SomaniSavita Home Makers LLP30/05/2023
CC006000000395996Suresh P MantriSavita Home Makers LLP30/05/2023
CC006000000395992Harsh SethiSavita Home Makers LLP30/05/2023
CC006000000395994Nirupam ChowdhurySavita Home Makers LLP30/05/2023
CC006000000396043Vishal v PrasadeSavita Home Makers LLP02/06/2023
CC006000000396104Amit Uttam sarangSavita Home Makers LLP07/06/2023
CC006000000396191Bhavna ThakurSavita Home Makers LLP14/06/2023
CC006000000396228Swati TawdeSavita Home Makers LLP15/06/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Jul 2023

Documents filed224

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 224 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Q4-Form 1 architects certificate_03-04-2026.pdf11 May 2026
Withdrawal Update Form 2File: GCR PHASE II RERA FORM 2 For MARCH 2026.pdf11 May 2026
Withdrawal Update Form 3File: Form 3 Q4 25-26.pdf11 May 2026
Withdrawal Update Form 1File: Q3-Form 1 architects certificate_17-04-2026.pdf20 Apr 2026
Withdrawal Update Form 1File: Q3-Form 1 architects certificate_17-04-2026.pdf20 Apr 2026
Withdrawal Update Form 2File: GCR PHASE II RERA FORM 2 For DEC 2025.pdf20 Apr 2026
Withdrawal Update Form 2File: GCR PHASE II RERA FORM 2 For DEC 2025.pdf20 Apr 2026
Withdrawal Update Form 3File: FORM 3 DEC 25.pdf20 Apr 2026
Withdrawal Update Form 3File: FORM 3 DEC 25.pdf20 Apr 2026
Withdrawal Update Form 1File: Q1-Form 1 architects certificate_17-04-2026_Scan.pdf18 Apr 2026
Withdrawal Update Form 1File: Q2-Form 1 architects certificate_17-04-2026.pdf18 Apr 2026
Withdrawal Update Form 2File: GCR PHASE II RERA FORM 2 For JUNE 2025.pdf18 Apr 2026
Withdrawal Update Form 2File: GCR PHASE II RERA FORM 2 For SEPT 2025.pdf18 Apr 2026
Withdrawal Update Form 3File: FORM 3 JUNE 25.pdf18 Apr 2026
Withdrawal Update Form 3File: FORM 3 SEPT 25 .pdf18 Apr 2026
Form 1File: Q4 Architech Certificate Form1.pdf30 Jun 2025
Form 2File: Q4 Engineer Certificate Form2.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Q4 Sold Unsold data 2025.pdf30 Jun 2025
OthersFile: Q4 Quality Certificate Form 2A.pdf30 Jun 2025
Form 3File: Q4 CA Certificate From 3 c.pdf30 Jun 2025
Self-declaration of Quarterly ProgressFile: Self Declaration MArch 2025.pdf30 Jun 2025
Declaration in FORM BFile: form B REVISED.pdf7 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA FORM 1 GCR Sep 2024.pdf27 Dec 2024
Disclosure of sold/ booked inventoryFile: GCR A WING SOLD UNSOLD Inventory till Sep 2024.pdf27 Dec 2024
Disclosure of sold/ booked inventoryFile: GCR B WING SOLD UNSOLD Inventory till Sep 2024.pdf27 Dec 2024
Disclosure of sold/ booked inventoryFile: GCR C WING SOLD UNSOLD Inventory till Sep 2024.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RERA FORM 2A GCR Sep 2024.pdf27 Dec 2024
Disclosure of sold/ booked inventoryFile: GCR PHASE II ALL WING SOLD UNSOLD LIST FOR JUNE 2024.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: GCR PHASE II ALL WING SOLD UNSOLD LIST FOR DEC 2023_.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: GCR PHASE II ALL WING SOLD UNSOLD LIST FOR March 2024_.pdf11 Jul 2024
Declaration in FORM BFile: Form B New.pdf10 Jul 2024
Layout approvalFile: 19 20 sheet to upload.pdf9 Jul 2024
Layout approvalFile: 21 22 sheet to upload.pdf9 Jul 2024
Layout approvalFile: 23 24 sheet to upload.pdf9 Jul 2024
Layout approvalFile: 25 26 sheet to upload.pdf9 Jul 2024
Layout approvalFile: 27 28 sheet to upload.pdf9 Jul 2024
Layout approvalFile: 29 30 sheet to upload.pdf9 Jul 2024
Layout approvalFile: 31 32 33 sheet to upload.pdf9 Jul 2024
Details of encumbrances concerned to FinanceFile: Form B Declaration 01_07_2024-4.pdf9 Jul 2024
Details of encumbrances concerned to LegalFile: Form B Declaration 01_07_2024-4.pdf9 Jul 2024
Copy of Layout Approval (in case of layout)File: 19 20 sheet to upload.pdf9 Jul 2024
Copy of Layout Approval (in case of layout)File: 21 22 sheet to upload.pdf9 Jul 2024
Copy of Layout Approval (in case of layout)File: 23 24 sheet to upload.pdf9 Jul 2024
Copy of Layout Approval (in case of layout)File: 25 26 sheet to upload.pdf9 Jul 2024
Copy of Layout Approval (in case of layout)File: 27 28 sheet to upload.pdf9 Jul 2024
Copy of Layout Approval (in case of layout)File: 29 30 sheet to upload.pdf9 Jul 2024
Copy of Layout Approval (in case of layout)File: 31 32 33 sheet to upload.pdf9 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GCR PHASE II RERA FORM 1 For DEC 2023.pdf9 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GCR PHASE II RERA FORM 1 For March 2024.pdf9 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA June 2024.pdf9 Jul 2024
Layout approvalFile: 15 18 sheet to upload.pdf8 Jul 2024
Copy of Layout Approval (in case of layout)File: 15 18 sheet to upload.pdf8 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GCR RERA FORM 2 For Dec 2023.pdf8 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GCR RERA FORM 2 For March 2024.pdf8 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -1 of 33_BUA calculation Sheet _19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -2 of 33_Ground Floor Plan _19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -3 of 33_First Floor Plan _19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -4 of 33_Second Floor Plan _19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -5 of 33_Third Floor Plan _19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -6 of 33_Layout Plan _plot area _19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -7 of 33_BUA calculation for commercial _19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -8 of 33_BUA Ground floor _19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -9 of 33_BUA 1st floor podium _19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -10 of 33_BUA 2nd floor podium _19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -11 of 33_BUA 3rd floor podium_19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -12 of 33_BUA Typical floor podium_19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -13 of 33_Block Plan_19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -14 of 33_Typical floor Layout Plan_19-03-2019.pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -16 of 33_19-03-2019 (4).pdf6 Jul 2024
Building plan approvalFile: 40_GCR_amend CC_sheet -17 of 33_21st floor Layout Plan_19-03-2019.pdf6 Jul 2024
Building Plan Approval (IOD)File: 40_GCR_amend CC_sheet -1 of 33_BUA calculation Sheet _19-03-2019.pdf6 Jul 2024
Building Plan Approval (IOD)File: 40_GCR_amend CC_sheet -2 of 33_Ground Floor Plan _19-03-2019.pdf6 Jul 2024
Building Plan Approval (IOD)File: 40_GCR_amend CC_sheet -3 of 33_First Floor Plan _19-03-2019.pdf6 Jul 2024
Building Plan Approval (IOD)File: 40_GCR_amend CC_sheet -4 of 33_Second Floor Plan _19-03-2019.pdf6 Jul 2024
Building Plan Approval (IOD)File: 40_GCR_amend CC_sheet -5 of 33_Third Floor Plan _19-03-2019.pdf6 Jul 2024
Building Plan Approval (IOD)File: 40_GCR_amend CC_sheet -6 of 33_Layout Plan _plot area _19-03-2019.pdf6 Jul 2024
Building Plan Approval (IOD)File: 40_GCR_amend CC_sheet -7 of 33_BUA calculation for commercial _19-03-2019.pdf6 Jul 2024
Building Plan Approval (IOD)File: 40_GCR_amend CC_sheet -8 of 33_BUA Ground floor _19-03-2019.pdf6 Jul 2024
Building Plan Approval (IOD)File: 40_GCR_amend CC_sheet -9 of 33_BUA 1st floor podium _19-03-2019.pdf6 Jul 2024
Building Plan Approval (IOD)File: 40_GCR_amend CC_sheet -10 of 33_BUA 2nd floor podium _19-03-2019.pdf6 Jul 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
FOUR SEASONSPLOT NO 2 and 3 SECTOR 12 VASHI NAVI MUMBAI10CompletedJan 2009Jan 2009

How this compares with Thane

100%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 69 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Goldcrest Residency - Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GHANSOLI7,600+ in Thane

2 kmGoldcrest Residency - PhCompleted 31Lapsed / revoked 4Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 60 registered projects within 2 km.

Builder: SAVITA HOMEMAKERS LLP

SAVITA HOMEMAKERS LLP has 2 registrations on MahaRERA, including GOLDCREST RESIDENCY - PHASE 1 and Goldcrest Residency - Phase 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Goldcrest Residency - Phase 2 is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Goldcrest Residency - Phase 2?

The registered promoter entity is SAVITA HOMEMAKERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Goldcrest Residency - Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Goldcrest Residency - Phase 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Goldcrest Residency - Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Goldcrest Residency - Phase 2?

The professionals named in the filing: Architect: Soyuz Talib; Engineer: Ali Abbas Jaffrey; Chartered Accountant: K KAveria and Co.; Chartered Accountant: Nitesh Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Goldcrest Residency - Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Goldcrest Residency - Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Goldcrest Residency - Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.